Design Economics and Cost Planning Flashcards
What is a Section 106 agreement?
Agreements between local authorities and developers- negotiated to grant planning consent
What is contingency?
Sum included in estimate to cover unknown expenses / unmitigated risks during project
How is contingency assessed?
- Should reflect risks, unknown specific items associated with project
- Early design stage, may be % (say 5-10%)
- As risk register is compiled throughout project, this total can be included as contingency
What is meant by a base date within a cost estimate?
- Date where rates and prices within cost estimate based on
- Included for basis of calculations (i.e. starting point for inflation adjustments)
What RIBA stage is an OCE typically produced?
Stage 0 - 1
What RIBA stage is a Cost Plan typically produced?
Stage 2 - 4
What are the RIBA stages of work?
- Strategic definition
- Preparation and briefing
- Concept design
- Spatial coordination
- Technical design
- Manufacturing and construction
- Handover
- Use
What information do you receive at Stage 0 and 1?
- Architectural brief with unit aspirations
- Level of specification
What information do you receive at Stage 2?
Floor plans, elevation drawings, structural, civil, M&E notes, proposals, reposts and strategies
What information do you receive at Stage 3?
Coordinated design packages from architectural, civil, structural and M&E
What information do you receive at Stage 4?
Fully detailed technical design, enough to produce BoQ or schedule of works
What are the changes from RIBA Plan of Work 2013 to 2020?
- Stage 3 - develop design -> spatial coordination
- Stage 5 - construction -> manufacture and construction
- More recognition of MMC and focus on sustainability
What is construction to ‘shell and core’?
- Basis structure, services and building envelope
- Usually includes fitout of landlord and common areas (i.e. main reception, bathrooms, lifts, stair cores)
- Base services typically terminated at entry points to each lettable floor plate
- Life safety services infrastructure typically provided
What is a CAT A fit out?
‘developer’s fit out’
- Generic fit out items to suit most developers, i.e. safety elements, basic fittings (suspended ceiling tiles, raised floors, lighting, power distribution to floor plates)
What is CAT B fit out?
- Additional works to CAT A provision, such as bespoke elements specific to building user needs, enables tenant to occupy and use space
- Typically includes partitions, power distribution to floor boxes, data cabling, artwork and branding, toilet finishes
Where can you find definitions for levels of fit out?
BCO (British Council of Offices) fit-out guide
What is an order of cost estimate (OCE)?
NRM1 definition
- method of cost prediction- estimate based on benchmark data for a similar type of project, based on strategic definition / initial brief
- purpose to establish affordability of client’s proposed development
- takes place prior to full set of working drawings, forms initial build up to cost planning process
Purpose of an order of cost estimate?
Establish if proposed building project is affordable and, if affordable, establish a realistic cost limit
(cost limit = max expenditure the client is prepared to spend on proposed building project)
Difference between an order of cost estimate and cost plan?
- OCE typically stage 0-2, provides possible cost based on higher level info- Initial phase of cost planning process, usually completed with sqm areas or functional units
- Cost Plan typically stage 2 onwards more detailed elemental breakdown, shows how costs are distributed across project, based on a more detailed, specific design
Difference between feasibility study, order of cost estimate and cost plan?
- Feasibility - sets budget
- Order of cost estimate - reviews options
- Cost plan - analyses how budget is being spent
Can you explain the term ‘cost per functional unit’?
NRM1 definition - Unit rate that, when multiplied by no. functional units gives building works estimate
- Can help recommend cost limit
What typical information accompanies an order of cost estimate?
- Covering letter / email
- Executive summary
- Cost limit
- Notes, assumptions and exclusions(i.e. on spec)
- Drawing and info on which the estimate is based
- Schedule of value enhancing options
- Risk register
Format of a feasibility / order of cost estimate?
- Presented on cost per sqm/functional unit/elemental basis, potentially as a range
- Range -> i.e. for element rates for main elements
- Considerations for any site abnormal costs / enabling works
- Prelims, contingency (risk), inflation, location factor adjustments
What is a functional unit?
- unit of measurement considering prime use of building
- i.e. how many apartments / beds / bedrooms
- i.e. retail - net lettable retail space
Where would you get your rates for a preliminary estimate?
Previous similar projects, historical cost data, in house models, Spon’s, BCIS
What information do you need to be able to carry out an order of cost estimate?
No established minimum information, but availability affects accuracy and detail
- Building location and type / purpose
- Floor area / no. functional units
- Assumed storey height and whether RAF / suspended ceilings envisaged
- Initial floor plans and drawings
- Indication of spec, M&E
- Budget and cashflow restraints
- Site conditions
- Indicative professional fees
What is a cost plan?
NRM1 definition
- Estimate based on specific design
- Statement showing apportionment of estimate / agreed budget between cost headings
- Method of cost prediction
Purpose of a cost plan?
- Cost consultant document to control design development
- Identify agreed cost limit and how money allocated to different building elements
When would you do a cost plan?
- Typically between RIBA Stage 2-4, increasing detail throughout project
- Stage 4 typically forms basis of PTE (to compare against tender submissions)
PTE no longer referenced in RIBA plan of work
What benefits does a cost plan provide to a project and its team?
- Help predict final project cost
- Designers aware of cost implications and proposals to help arrive at practical and balanced designs
- Provides info for the employer to make informed commercial decisions
Do you need a programme to complete the cost plan?
- Would be helpful- prelims presented as a weekly rate in developed cost plan, so programme or at least high level dates would be required
- Key info required = design and tendering periods, start on site date, construction period, completion date
How do you structure an elemental cost plan? / Typical components?
In accordance with company templates, which follows NRM recommended structure:
- Elemental summary, then breakdowns on separate sheets (facilitating, substructure, superstructure etc)
- Area schedule
- Depending on info, I would provide a cost for contractor’s prelims based on weekly rates / benchmarking / programme
- Add % for OH&P, professional fees, other project costs, then any risk and inflation
- List of drawings and information used
What is a cost plan risk allowance?
NRM1 definition
- Quantitative allowance set aside as precaution against risk and future requirements, to allow for uncertainty of outcome
How do you quantify risk on a cost plan?
- Benchmark from similar projects, consider any abnormals
- Risk register as design develops to work out expected monetary value, build priced risk register
When calculating the total fee estimate for a project, what fees might be included?
- Consultant fees (design team, consultants)
- Contractor fees (management and staff)
- Others (statutory undertaker, planning permission application)
What benefit does the client get out of accurate cost planning?
- Confirms to the client whether scheme is affordable or not
- Places client in informed position to make commercial decisions
- Acts as value management tool- ensure client gets building meeting their needs and representing best value
How would you deal with a cost plan which is over budget?
- Analyse costs to assess sources of increase
- Communicate matter to client and project team clearly
- Identify any abnormally high elements of work
- VE- identify where potential savings can be made, or offer scope reduction
How can the cost manager help control the design to keep the project within budget?
- Explain where cost plan is vs budget, discuss limitations
- Identify areas where design may not be economical
- Regular project risk reviews, focus on mitigating key design risks
- Explain how design changes have impacted the cost plan
- Contribute to VE / cost saving sessions
What are some key reasons for cost overrun on a project?
- Ambiguous client brief
- Changes in later stages of project
- Project risk not properly managed
- Inadequate management of control and change processes
- Design not coordinated
- Changing external factors / market conditions (inflation, pandemic, legislation updates)
- Unsuitable selection of procurement strategy
- Statutory authority influences (i.e. onerous planning permission conditions)
What is BWIC?
Builder’s work in connection
- Builder’s work necessary to allow other work to proceed (typically M&E / speciallist installations -> drilling, fixing, cutting, penetrations)
- Usually put within cost plans as % of services cost
Why is VAT usually excluded from the cost plan?
- Not a tax specialist - we wouldn’t know correct rate unless informed
- Employers may incur different levels of VAT
- Therefore usually excluded to ensure incorrect rate not applied
How are subcontractor’s preliminaries captured in the cost plan?
Should be included in unit rates applied to components and sub-elements