Wherever the existing ground is above the constructed section, the construction is said to involve?
Cut or excavation
Wherever the existing ground is below the constructed section, the construction is said to involve?
Fill or embankment
The points at which the cut or fill slopes intersect the existing ground are referred to as?
Catch points
The points at which the cut or fill slopes intersect the nearly horizontal roadway surface are referred to as?
Hinge points
A graph of cumulative volume of earthwork versus distance in stations from the beginning of the job, in which cut is considered to be positive and fill negative.
Mass diagram
The product of a volume of material times the average distance it is hauled is referred to as?
Haul
The longest distance material should ever be hauled is called the?
Limit of economic haul