Formula for EVA Flashcards

(12 cards)

1
Q

CPI = ?

A

EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what does it mean when CPI <1

A

under 1 then under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

SPI = ?

A

EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what does it mean when SPI > 1

A

ahead of shedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

ETC =?

A

estimated cost to complete = (BAC - EV)/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is the BAC

A

sum of your budget column

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EAC = ?

A

Estimated cost at completion = AC + ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CV

A

(AC - BAC)/BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

project cost variance = ?

A

BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what does it mean when your AC > EC ?

A

project is over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does it mean when your EV<PV ?

A

project is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

plot the LOGON project cost/schedule performance plotted graph