Integration Management Knowledge area Flashcards

(49 cards)

1
Q

What is integration management

A

Putting all pieces of project together into a cohesive whole

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Processes of integration management

A

Develop project charter (Initiating)
Develop project management plan (Planning)
Direct and manage project work (Executing)
Manage project knowledge work (Executing)
Monitor and control project work (Monitoring and controlling)
Perform Integrated change control (M & C)
Close project or phase (Closing)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Develop project charter process (Initiating)

What is included

A

Project Title and Description
Project Manager and Authority level
Business Case (Reason for initiation of project)
Resources Pre-Assigned - high level
Stakeholders - high level
Stakeholder Requirements - competing requirements resolved
Product description and deliverables
Measurable project objectives
Project approval requirements
High Level project Risks (+ve and -ve risks)
Project Sponsor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who is responsible for the distribution of project charter. Publishing project charter.

A

Sponsor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Benefits of Project charter

A

Recognizes and authorizes the project
appoints PM and authority to spending money and commit resources
High level requirements
Links project to ongoing work of the organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Does project charter change during execution

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the different project selection methods

A

Benefits Measurement Methods (Comparative)

Constrained optimization methods(Mathematical approach)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what are benefit measurement method

A
Murder board (a panel of pple who try to shoot down
Peer review
Scoring models
Economic models
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Constrained optimization methods(Mathematical approach)

A

Linear programming
Integer programming
Dynamic Programming
Multi-objective programming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

different Economic Models - Benefit measurement method

A
Present Value (PV)
Net Present Value (NPV)
Internal rate of return
Payback period
Benefit cost ratio
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Present value

A

Dollar today is worth more than a dollar tomorrow
Pv=fv/(1+r)^2
fv = future value
r = interest rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

calculate PV for project with three installments below
1st installment of 100,000 at the start of the project
2nd installment of 100,000 at the end of 1st year
3rd installment of 100,000 at the end of 2nd year

A

1st installment PV = 100000/(1+0.10)^0 = 100,000
2nd installment PV = 100,000/(1+0.10)^1 = 90909
3rd installment PV = 100,000/(1+0/10)^2 = 82,645

Total Cashflow = 300000
present value for project= 273554

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Net present Value(economic model)

NPV > 0 project can be selected

A

present value of total benefits(revenue or income) minus the costs over time

Higher NPV is selected
NPV = PV of Income - PV of Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Internal rate of return IRR (Economic model)

A

project with higher IRR should be selecting

how much percent a project will give back after a certain period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Pay back period

A

Number of time periods to recover the investment on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Benefit cost ratio

A

Ratio of Benefit v/s cost

> 1 should be selected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Economic value added (EVA)

A

EVA is the amount of added value the project produces for the company’s shareholders above the cost of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Opportunity Cost - Cost of selecting project over another project.

NPV 1 = 200000
NPV 2 = 150000
what is the opportunity cost of selecting project 1 only

A

150000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Sunk cost

A

Cost already expended on the project. All money that has been spent until now.
Sunk cost is not considered when deciding whether to continue a troubled project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Law of diminishing return

A

after a certain point adding more resources will not produce proportional increase in work or productivity.

Reason - co-ordination

21
Q

Working capital

A

Working capital = current assets - current liabilities

22
Q

Depreciation
Methods to calculate depreciation
Straight line depreciation
Accelerated depreciation

A

depreciation - capital assets looses value over time

straight line - constant reduction of amount
accelerated - aggressive reduction in initial years

23
Q

Project Statement of work (SOW)

A

Describes the needs, product scope and strategic plan

requirements

24
Q

Who creates the SOW

A

Created by customer or sponsor

25
Project charters with work under contract
Buyer and seller should have independent charters for their own use
26
Develop project management Plan process
2nd process of integration management plan defines strategy for managing the project and the process in knowledge area Unique for each project creation of management plans
27
Management plan
covers how you will define, plan, manage and control the project looks forward in time to address management concern
28
Project management plan - how is it different than other plan
integrates all knowledge area management plans into a cohesive whole includes a series of plans because of iteration and baselines
29
what does project management plan include
``` project management process management plans for knowledge areas scope, schedule and cost baseline Requirements management plan change management plan configuration management plan - versioning Process improvement plan ```
30
Baseline
snapshot of project at a certain time baseline can only be changed by change request or with acknowledgment of project sponsor
31
Performance measurement baseline
scope baseline + schedule baseline + Cost baseline
32
WBS, wbs dictionary
Work breakdown structure, provides definition of wbs
33
change control board
changes are evaluated and approved
34
deviation in baseline
are often due to incomplete risk identification and risk management
35
Requirement management plan
is part of scope management plan | describes how requirements will be identified, managed and controlled
36
change control system
includes standardized forms, processes, procedures, and software to track and control changes.
37
Configuration management plan
defines how to manage deliverables and resulting documentation. which organizational tools will be used on the project. Version management and defines versioning
38
configuration management system
part of PMIS - PM information system tools for versioning may include change control system
39
Project documents
documents used to manage a project updated during the project not part of project management plan project charter, SOW, activity list, quality matrics are eg.
40
kick off meeting
just before execution. Last step of planning process | main purpose is to make sure everyone is on the same page
41
project plan approval
Management Sponsor Project team stakeholder
42
Direct and mange project work process (executing) Integration management knowledge area
managing people, doing work and implementing approved changes requesting changes, and completing approved change requests
43
input and output of direct and manage project work
inputs project planning approved changes corrective actions preventive action defect repair output new change requests deliverables work performance information implementation of changes, corrective action, defect repair and preventive action updates to project management plan and project document
44
Manage project Knowledge (executing) Integration management
main output is lessons learned register. Starts early in the project Knowledge can be explicit or tacit
45
Monitor and control project work process (M&C) integration management
from initiating to closing output - change request and updates to project management plan and project documents monitoring performance measures
46
Perform integrated change control process
``` changes are accepted/rejected/handled access the change look for options change is approved/rejected update the status of change in change control system ```
47
change control board (CCB) Perform integrated change control process
evaluates and approves/rejects changes ``` members customers PM sponsor experts etc. ```
48
Process for making changes Perform integrated change control process
Prevent root cause of changes identify the change impact of change - options or alternative change request submission perform integrated change control process adjust the PM plan, project documents and baselines manage stakeholder expectations manage the project to the revised project plan and project documents
49
Close project or phase process
focuses on closing out all knowledge areas acceptance of documents closure of documents and archival in OPA's getting final approval of the overall project from customer. project will be closed even if its terminated.