Organizational influences and Project lifecycle Flashcards
(36 cards)
Lesson learned learned are best completed by A) PM B) stake holders C) Sponsor D) Team
B
Which of the following is NOT characteristic of a Project? A)It has a beginning and an end B)Creates a unique product or service C)Temporary D)Repetitive and ongoing for years
D
You are working in a software company. In order to provide better quality in projects, your company is initiated an infrastructure renewal project. This is an example of which project initiation reason? A)Market Demand B)Technological Advance C)Customer Request D)Legal Requirement
B
Which of the following is an example for operational work?
A)Extending a subway line with 2 more stations
B)Manufacturing a new car with new features customized for women
C)Sending password renewal e-mails every 3 months for each user working in a bank.
D)Sending a satellite to space
C
Project management includes processes in order to manage and deliver a project successfully. Which of the following is NOT a process group of project management? A)Tracking & Reporting B)Initiating C)Executing D)Closing
A
Project management profession requires knowledge and expertise in project management knowledge areas. All of the following are project management knowledge areas EXCEPT: A)Stakeholder Management B)Procurement Management C)Budget Management D)Schedule Management
C
Which of the following about projects, programs and portfolios is NOT correct?
A)Interrelating projects can be groups under a program for better coordination.
B)All projects and programs under a portfolio must be related to each other.
C)Programs and projects serving to same business goal can be grouped under a portfolio
D)Unrelated projects cannot be grouped under same program
B
Project Management Office (PMO) centralizes the management of projects in organizations. Depending on the organizations, PMO can be in all of the following structures EXCEPT: A)Supportive B)Controlling C)Directive D)Managing
D
Project Management Office (PMO) in an organization may do all of the following in an organization except: A)Test the functional requirements of products developed.
B)Provide guidance
C)Manage interdependencies between projects
D)Gather lessons learned document
A
Project manager reports to different people depending on the organization type. A project manager can report to all of the following EXCEPT: A)Functional Manager B)Program Manager C)Senior Team Member D)Portfolio Manager
C
All of the following are roles of Project Manager EXCEPT:
A)To lead the team to achieve project objectives
B)Perform the most critical tasks of the project
C)Using interpersonal skills while managing project
D)Linking the strategy of the project or organization with the project team
B
Which of the following is NOT required to exist in a Project Manager?
A)Knowledge about project management
B)Performance on applying project management methodologies
C)Personal skills to manage communication
D)Subject matter expertise on the technology used in project
D
Your company will hire a project manager for its Project Management Office (PMO) department. Hiring process of the company evaluates several aspects of the candidates. Which of the following is the MOST important aspect that needs to be assessed in a Project Manager candidate? A)Team Building B)Communication C)Leadership D)Coaching
B
Objectives of a project define what needs to be achieved as a result of project. All of the following about objectives are correct EXCEPT:
A)If 95% of the objectives have been met in a project, it can be considered successful
B)A trade-off exists between requirements and objectives
C)Meeting project objectives is under Project Manager’s responsibility
D)Quality activities are done for checking project meets its objectives
A
Which of the following is NOT a common type of project constraint? A)Time B)Resources C)Technological Advance D)Cost
C
Organizational Process Assets is input or output in most of the project management processes. Which of the following about Organizational Process Assets is NOT Correct?
A)Functional Organization structures do not need Organizational Process Assets in the company
B)Includes lessons learned documentation and historical information from past projects
C)Acts as corporate knowledge base for storing and retrieving information
D)Includes plans, processes, and procedures used by organization
A
You are working as a project manager in a smartphone manufacturer. There is a harsh competition in smart phone market and several patent conflicts are ongoing between the smartphone manufacturers in courts. This is an example of: A)Stakeholder B)Objective C)Organizational Process Assets D)Enterprise Environmental Factor
D
You are working as a project manager in a health products manufacturer. All of the following are examples of Enterprise Environmental Factors EXCEPT:
A)Structure of the organization
B)Budget provided for your new project
C)Standards published by World Health Organization (WHO)
D)Market conditions
B
Stakeholders are the people whose interests may be positively or negatively impacted by the project. All of the following about stakeholders are correct EXCEPT:
A)Requirements of all stakeholders’ must be met in a project
B)Project team members are part of stakeholders
C)Stakeholders might have competing requirements with each other
D)Meeting expectations of stakeholders are critical to success of the project
A
Project governance provides the project manager and team with structure, processes, decision-making models and tools for managing the project. In this concept, which of the following is not an example of project governance?
A)Documentation of the organization for how to assign tasks to resources
B)Tool for requesting resources from line managers
C)Requirements of the customer
D)Source selection procedure of the organization for procurement
C
Organizations choose different types of organizational structures for their organization. Which of the following is not a type of organizational structure? A)Functional B)Line C)Projectized D)Matrix
B
Which of the following is NOT true about Functional Organizational Structure?
A)People are grouped by areas of specialization
B)Team members do project work and departmental work
C)Information is exchanged through heads of regarding departments
D)Least common type of organizational structure seen in market
D
You are working in a software company and your company has a projectized organizational structure. Which of the following is TRUE?
A)People in resources will turn back to their departments after project finishes
B)Functional managers have control of projects
C)Company is organized by departments based on specializations
D)Project manager has the ultimate control of the project
D
Organizations which have Matrix type of organizational structures can adopt three different types of Matrix Organizational Structure. Which of the following is NOT type of a matrix type organizational structure? A)Tight Matrix B)Strong Matrix C)Balanced Matrix D)Weak Matrix
A