Lecture 7 (Crashing) Flashcards

1
Q

Why is crashing used

A

To accelerate a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the primary methods for crashing

A
  • Change work methods
  • Compromise quality/ reduce scope
  • Institute fast-tracking
  • Work overtime
  • Increase the quantity of resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Crashing Process

A

1) Identify fixed and variable costs of activities
2) Crash point is a fully expedited activity
3) Optimise time-cost trade-offs
4) Shorten CP activities only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When should you cease crashing

A
  • Target completion time is reached
  • Crashing cost exceeds penalty cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you calculate the cost of crashing

A

Crash cost - normal cost / normal time - crash time