Lecture 7 (Lags) Flashcards
1
Q
what are the four logical relationships between tasks
A
1) Finish to Start
2) Finish to Finish
3) Start to Start
4) Start to Finish
2
Q
What is the most common type of lag
A
Finish to start
3
Q
Finish to stat lag
A
- Shown on the line
- Added during the forward pass
- Subtracted during the backward pass
4
Q
Finish to finish lag
A
Where one activity requires multiple preceding activities to be completed before starting it can make sense to add a lag to ensure all preceding activities finish at the same time
5
Q
Start to Start lag
A
Logic must be maintained by both the forward and backward pass
6
Q
What is the least common type of lag
A
Start-to-finish lag where the successors finish depends on the predecessor’s start