Lecture 7 (Lags) Flashcards

1
Q

what are the four logical relationships between tasks

A

1) Finish to Start
2) Finish to Finish
3) Start to Start
4) Start to Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the most common type of lag

A

Finish to start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Finish to stat lag

A
  • Shown on the line
  • Added during the forward pass
  • Subtracted during the backward pass
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Finish to finish lag

A

Where one activity requires multiple preceding activities to be completed before starting it can make sense to add a lag to ensure all preceding activities finish at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Start to Start lag

A

Logic must be maintained by both the forward and backward pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the least common type of lag

A

Start-to-finish lag where the successors finish depends on the predecessor’s start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly