MCQ Mock Revision Flashcards

1
Q

What is the are the most critical components of the triple constraint

A
  • Quality
  • Time
  • Scope
  • Budget
  • Cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the typical role senior management on a project

A

Support the project and resolve resources and other conflicts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What difficulties could working on a project have for a business analyst in a company with a matrix organizational structure

A

Being away from the group and on a project that might make it more difficult to get promoted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the product life cylce

A

The time the product is used after completion of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who are not members of a scrum

A

Executive VP, General Manager and the Customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are common examples of variable costs

A

Direct Labour, Expedite, Material

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the most common methods of cost estimation

A
  • Ballpark (order of magnitude)
  • Comparative
  • Feasibility
  • Definitive
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are common examples of significant project risk

A
  • Financial risk
  • Technical risks
  • Commercial risk
  • Legal risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Recent research in organisational leadership declares that the new project leader generates and sustains what?

A

Trust

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you calculate activity slack (a.k.a. float)

A

Late start (LS) - Early Start (ES)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does the network diagram tool show?

A

Activity precedence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A finish to start lag delay is shown where?

A

On the line adjoining the two activity nodes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The most common type of logical sequencing between tasks is referred to as what

A

Finish to start relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The classic project S-curve is a plot of what?

A

Labour hours versus expended

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A project manager who uses milestones as a project control device is using what sort of system?

A

Reactive control system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

An excellent way to coordinate schedules with vendors and suppliers is through the use of what?

A

Milestones