MCQ Mock Revision Flashcards
What is the are the most critical components of the triple constraint
- Quality
- Time
- Scope
- Budget
- Cost
What is the typical role senior management on a project
Support the project and resolve resources and other conflicts
What difficulties could working on a project have for a business analyst in a company with a matrix organizational structure
Being away from the group and on a project that might make it more difficult to get promoted
What is the product life cylce
The time the product is used after completion of the project
Who are not members of a scrum
Executive VP, General Manager and the Customer
What are common examples of variable costs
Direct Labour, Expedite, Material
What are the most common methods of cost estimation
- Ballpark (order of magnitude)
- Comparative
- Feasibility
- Definitive
What are common examples of significant project risk
- Financial risk
- Technical risks
- Commercial risk
- Legal risk
Recent research in organisational leadership declares that the new project leader generates and sustains what?
Trust
How do you calculate activity slack (a.k.a. float)
Late start (LS) - Early Start (ES)
What does the network diagram tool show?
Activity precedence
A finish to start lag delay is shown where?
On the line adjoining the two activity nodes
The most common type of logical sequencing between tasks is referred to as what
Finish to start relationship
The classic project S-curve is a plot of what?
Labour hours versus expended
A project manager who uses milestones as a project control device is using what sort of system?
Reactive control system
An excellent way to coordinate schedules with vendors and suppliers is through the use of what?
Milestones