Mocks Flashcards
(57 cards)
Talk me through the payments process with jct minor works
What was the implication of issuing an EOT & why was an EOT needed?
Named v nominated sub contractors
Naming sub-contractors allows the client to influence the main contractor’s selection of sub-contractors, whilst leaving responsibility for their performance with the main contractor. It can be seen as an alternative to nominating sub-contractors as the contractual relationship is less complicated, and indeed, some forms of contract (such as Joint Contracts Tribunal (JCT) contracts) no longer include provision for the nomination of sub-contractors.
How were consultants appointed what were the non-compliant combination of materials
Why was it non complaint mix-matching of materials
Manufacturers test their fire stopping projects as complete systems.
It’s easy to assume if two products individually have a fire certification they should work together. But this is not how how certification works.
Mixing products that haven’t been tested together introduces uncertainty. Materials may expand at varying rates or bond differently which creates a risk of failure leaving gaps in the fire barrier. 
When is loses and expense claimable
When a contractor suffers a direct financial loss or incurs an additional expense due to matters for which the employer is responsible 
What was your clients response to the strict deadlines?
We were initially appointed in late October and needed to be finished for the staff regional day in April
What’s in an f10 form
Location, key dates, team members , project description, client and contractor information
 number of people on site
How could you have examined tender returns using design and build contract? 
Schedule of rates.
What do you do at the end of a rectification period. Talk me through your process
Schedule of rates.
This is a list setting out the labour, plant ride rates that a contractor will use for pricing. It does not contain quantities
What is the British standard for a fire door
BS 476 Part 22
BS EN 1634
What are the building regulations
2010
Minimum set of standards to ensure building work is safe
Building act 1984
Was planning permission needed for bic 1?
No, there was no material change. The height of the roof was the same. Permitted development.
What is a letter of intent
A temporary agreement entered into whilst parties conclude formal Building contract negotiations. Letters of intent may be used when the parties need to start to procure materials, commence our preparations or start the works before agreement of the formal contract terms. 
Why use lime mortar
-breath ability. Allows water to pass through the building. The permeability allows evaporation. Whereas cement is less porous and seals the Building envelope. Moisture won’t be able to evaporate and will be forced out through the face of the brick causing damage and spalling. 
Sacrificial to masonry
-flexibility. Allows the building to move whereas cement is hard and brittle 
CEMENTITIOUS MORTAR NOT CONCRETE
Regent house. What was the contractural impact of the contractor not completing on time
My eye design acting as consultants to LSH? What mechanism is in place for potential claims of negligence?
Procedure if you found asbestos on site
What type of lime mortar would you specify
Non-Hydraulic lime
Old, soft masonry
Natural Hydraulic lime
Most common 2,3.5,5
2=soft 3.5=normal 5=hard, harsh conditions
I’d recommend an NHL 3.5
• When you become Chartered, say you wanted to set up your own business, what would you need to consider?
Insurance
Comply with ROC & obligations for firms to RICS
• If you were instructed on a CA job in a different part of the country, or usual contractors weren’t available in your area, how would you find suitable others?
First, I would research the local market by consulting professional networks such as RICS, using contractor databases like Constructionline, and seeking recommendations from trusted industry contacts. I would also review local tender lists and frameworks if applicable.
Next, I would conduct due diligence on potential contractors — checking references, reviewing past project experience, financial stability, health and safety records, and accreditations like CHAS or ISO standards. Where possible, I would meet them in person and visit ongoing or completed projects to assess quality firsthand.
• When using BCIS online, what do you need to consider when using the rates/information provided?
What is in pre construction information
Information in the client’s possession all which is reasonably obtainable by the client which is relevant to the construction work and is unappropriate level of detail and proportionate the risks involved including information about
The project
Planning and management of the project
Health and safety hazards.
Existing health and safety file
MIGHT INCLUDE
Key dates / contacts
Security
Means of escape
Fire precautions
emergency procedures
Boundaries and access
SIGNIFICANT RISKS
Welfare