Monitoring And Controlling Flashcards

(8 cards)

0
Q

Calculate CV and SV

A
Cost variance (CV) = earned value (EV) - actual cost (AC)
Scheduled variance (SV) = earned value (EV) - planned value (PV)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Change tracking and log

A

A spreadsheet that lists the baseline cost identified in the project plan dated and identifies any additions and changes which result from project execution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Calculate CPI and SPI

A

Cost performance index (CPI) = earned value (EV)/actual cost (AC)
Scheduling performance index (SPI) = earned value (EV)/planned value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When calculating CPI and SPI describe the meaning of the index values

A

CPI. SPI
>1. Under cost. Ahead of schedule
=1. On cost. On schedule
<1. Over cost. Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Calculate ETC

A

Estimate to completion (ETC) = work remaining (BAC - EV)/CPI

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

calculate EAC

A

Estimate at completion (EAC) = BAC/CPI

EAC = ETC + AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does BAC mean? What is the equeation?

A

Total budget of the baseline

BAC = original / planned budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Closing reports

A

Final report
Post mortem/ lessons learned
Outcomes management report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly