Monitoring And Controlling Flashcards
(8 cards)
Calculate CV and SV
Cost variance (CV) = earned value (EV) - actual cost (AC) Scheduled variance (SV) = earned value (EV) - planned value (PV)
Change tracking and log
A spreadsheet that lists the baseline cost identified in the project plan dated and identifies any additions and changes which result from project execution.
Calculate CPI and SPI
Cost performance index (CPI) = earned value (EV)/actual cost (AC)
Scheduling performance index (SPI) = earned value (EV)/planned value (PV)
When calculating CPI and SPI describe the meaning of the index values
CPI. SPI
>1. Under cost. Ahead of schedule
=1. On cost. On schedule
<1. Over cost. Behind schedule
Calculate ETC
Estimate to completion (ETC) = work remaining (BAC - EV)/CPI
ETC = EAC - AC
calculate EAC
Estimate at completion (EAC) = BAC/CPI
EAC = ETC + AC
What does BAC mean? What is the equeation?
Total budget of the baseline
BAC = original / planned budget at completion
Closing reports
Final report
Post mortem/ lessons learned
Outcomes management report