ORA RM QUIZ 3 (M5) Flashcards
ISO 31000 considers that _____ is the main heading under which various options exist, such as:
Avoiding the risk by deciding not to start or continue with the activity,
Taking or increasing the risk in order to pursue an opportunity,
Removing the risk source;
Changing the likelihood or the consequences;
Sharing the risk with another party or parties,
Retaining the risk by informed decision.
TREAT RISK
NOTE:
RISK RESPONSES
AVOIDING
TAKING
REMOVING
CHANGING
SHARING
RETAINING
_________defines RISK TREATMENT Process of Developing, Selecting, and Implementing Controls
Note: Controls
BS 31100
_________defines RISK TREATMENT as development and implementation of measures to modify risk
NOTE: risk
ISO 3100
4 Ts of Hazard Risks
Tolerate
Treat
Transfer
Terminate
4 Ts of Hazard Risks
The exposure may be _____ without any further action being taken. Even if it is not, the ability to do anything about some risks may be limited, or the cost of taking any action may be disproportionate to the potential benefit gained.
tolerable
4 Ts of Hazard Risks
For some risks the best response may be to ______ them. This might be done by conventional insurance, or it might be done by paying a third party to take the risk in another way. This option is particularly good for mitigating financial risks or risks to assets.
transfer
4 Ts of Hazard Risks
By far the greater number of risks are addressed this way. The purpose of ______ whilst continuing within the organization with the activity giving rise to the risk, action (control) is taken to constrain the risk to an acceptable level.
TREAT
4 Ts of Hazard Risks
to reduce likelihood
Treat
risk tolerance defined by ______ as the orgs readiness to BEAR the risk after risk treatment in order to achieve its objective
guide 75
______ can be influ by legal or regul reqs
risk toler
t o f
tolr risk is norm concerned with org being willing to retain or tolr a risk, even if its higher than the org would choose to accept
t
____ is a RM strat to offset losses in investments by taking an ______ position in a related asset. the reduction in risk provided by it also typically results in a ______ in potential profits
Hedging
OPposite
reduction
_____ often be undertaken with the risk at the inherent and/or current level, so that when the risk has been treated, the new current level or target level may become tolerable.
Risk treatment
Insurance is estb. mech for _______ the financial impact of losses arising from hazard risks and to control risks
transferring
2 were considered to be risk transfer and treatment options
R. hedging and Neutralization
the cost of risk transfer is a component of ____
risk financing
___ of risk is done by stopping the process or activity
elim
_____ involves cost of contingent arrangements for the provision of funds to meet the financial impat of risk materializing.
risk financing
___ overall approach to the mgmt of CONTROL and OPPT. risks is similar to the approach adopted for the management of hazard risks
Project and Strategic Risk Response
4 RISK CONTROL TECHNIQUES
limit the possibility
preventive
strongest control
4 RISK CONTROL TECHNIQUES ARE
DIRECT
DETECT
CORRECT
PREVENT
…IVE
4 RISK CONTROL TECHNIQUES
limit the scope for loss and reduce any bad outcomes
corrective
4 RISK CONTROL TECHNIQUES
outcome is achieve
directive
4 RISK CONTROL TECHNIQUES
identify occasiosn of bad outcomes
detective
weakest control