PMBOK BOOK Flashcards

(596 cards)

1
Q

What is “Organizational context”?

A

When the type of organization and other environmental factors greatly influence how a project is carried out.

Example: Pharmerica projects are dramatic due to limited operational support and resources available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a process?

A

A process does or creates something necessary and valuable for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is “Identify Risks”?

A

Identify risks is the process where the list of risks is created.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Processes consist of only three types of ingredients…what are they?

A

I.T.T.Os

Inputs
Tools & Techniques
Outputs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does each phase of a project produce?

A

A deliverable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is an “Exit Gate”?

A

An exit gate is the point at the end of a phase where the deliverable (what is produced at end of phase) will be evaluated to determine whether or not next phase should be started.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are two characteristics of a project?

A

Time limited
A project is unique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is project elaboration?

A

Simply means that you do not know all of the characteristics of a product when you begin the project.

Like a science experiment…you learn more as you go.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Historical Information?

A

Organizational Process Assets.

Used to help predict trends and avoid mistakes for the current project and to evaluate the project’s feasibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a “baseline”?

A

A version of a plan once it has been stabilized.

The plan cannot be changed whenever…any changes will need to be approved and documented through a change control process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a “regulation”?

A

A regulation is a official document that provides a guideline.

Regulations are issued by government agencies or other official organizations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a project manager?

A

The person who is ultimately responsible for the project.

Formally empowered
Authorized to spend money
Authorized to make decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a project coordinator?

A

Sometimes project managers don’t exist - coordinators then step in.

  • Weaker than a PM.
  • may not have many abilities to spend or make decisions.

Found in weak or functional organizations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a “project expeditor”?

A

Weakest role. Usually an assistant to an executive.

Part time.

Can be found in functional organizations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a “functional manager”?

A

The departmental manager in most companies….like Director of Marketing.

Owns the resources. (Pharmacy example would be the Pharmacy Director.)

Functional managers tend to argue with project managers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a “organic organization”?

A

Teams and groups naturally form to address priorities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Who is In charge in an organic organization?

A

Varies based on company priority and personality of employees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a benefit of an organic organization?

A

Due to its loose nature can be adaptive to environment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Negatives of organic organization?

A

Lack of company maturity.

Short sighted.

RLH

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is a “functional organization”?

A

Most common organization type.

Company is separated in departments.

Project managers have low influence due to working with functional managers (directors).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Who is in charge in a functional organization?

A

Functional department manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are benefits of a functional manager?

A

Deeper company expertise by area (ops, billing, marketing, IT)

High degree of specializations (pharmacists, masters in Marketing, etc)

Defined career paths for your team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Negatives of a functional organization

A

Project manager is weak.
Projects aren’t as big of a priority due to everyone having day to day tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is a “matrix organization”?

A

A hybrid organization where individuals (Melissa mannino) has a functional manager (olaitan) and a project manager (Jared).

Weak matrix has Melissa favoring olaitan. A strong matrix has Melissa favoring PM, Jared.

Balanced matrix has equal respect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Who is in charge in a matrix organization?
Power is shared between a functional manager and a project manager.
26
Benefits of a matrix organization?
Best of both worlds. Project managers can gain a deep expertise of a functional organization while still managing resources of a project.
27
Negatives of a matrix organization?
High overhead. Individuals (melissa) get confused on who to report to. High chance of conflict between functional and PM. Staff tends to favor Functional Manager.
28
What is a "projectized organization"?
Company is structured around projects rather than departments. Project manager is over both staff and project. Consulting environments usually have this.
29
Who is in charge in a projectized environment?
Project managers
30
Benefits of a projectized environment?
PM has complete authority. Communication is easy. Loyalty is strong (no FM conflict)
31
Negatives of a projectized organization?
Team members aren't as expertise. Team members don't have anywhere to go when job is done. Development can be difficult.
32
What is a "virtual organization"?
Contains part time and full time workers. Communication can be peer to peer.
33
Who is in charge in a virtual organization?
Varies.
34
Benefits of virtual organization
No cost of transportation Projects can be worked around the clock due to time zones and part time hours.
35
Negatives of a virtual organization
Relationships are weak. Accountability is challenging.
36
What is a "composite" organization
Has both functional and projectizer structures. Combination of function, matrix and projectized.
37
Who is in charge in a compsote organization
Varies
38
Project life cycle phases Cpctic
Concept Planning Construction Testing Implementation Closure
39
What is the triple constraint (or iron triangle)?
Concept that scope, time, and cost are closely interrelated. You can't change one side without affecting the others.
40
What is a "work authorization system"?
Used to ensure that work gets performed at the right time and in the right sequence.
41
What is a project management plan?
A single approved document that guides how to execute, monitor & control and close a project.
42
What is an organizational process asset?
Anything that your organization owns or has developed to help you on a current or future project. Example: templates, lessons learned , estimating data.
43
What are a few examples of enterprise environmental factors?
Company structure. Corporate culture. Stakeholder appetite for risk. Laws and regs are different in states/countries.
44
Who writes the project charter?
The project sponsor and/or Customer. Signed by the organizations sponsor.
45
What does a project charter do?
Explains a need. Designates the project manager and assigns authority regarding $ or resources. High level.
46
When is work performance data an input/output?
Output after the execution phase. That's when you can pull it. It is an input in the monitoring/controlling phase.
47
What is a project management information system?
Sharepoint. Automated system that optimizes schedule and helps collect and distribute information.
48
What is the point of a configuration management?
To manage different configurations of a product. Alpha Beta Final product
49
What is the process of Perform l integrated change control?
Requested changes within a project are evaluated for impact on whole project and ultimately approved/denied.
50
What is a methodology?
A set of processes and practices performed a specific way to accomplish a project.
51
Organizations with no methodology tend to rely on....
Organizations with no methodology rely on heroic effort of their employees. No methodology means success is not repeatable and lessons from failures are not learned.
52
Types of Agile Methodology
Scrum Lean Kanban Feature-driven development Extreme programming
53
Describe predictive methodology
Plan Do Check Act
54
Systems development life cycle (waterfall approach)
Analysis Design Implementation Testing Evaluation
55
What do agile projects value?
Self organizing teams w/ no formal manager. Meetings and projects are conducted out in the open, with communication freely among all team members.
56
Describe scrum meetings
Daily Each member communicates What they covered yesterday, will do today What obstacles they are encountering.
57
How does agile teams handle change?
They welcome change. Team will meet, evaluate the change, and look at impact
58
What is Incremental development (destiny)
Usable features are delivered in each new version of the software.
59
What is iterative development?
The practice of performing small work circles/iterations/sprints that include planning, development and control activities.
60
How long does an iteration/sprint last?
21 days, performed in succession.
61
Benefit of delivering results in small updates would be....
Keeps teams focus sharp..priority Gets feature to customer more quickly Allows to get used tested and quicker feedback.
62
What is a spike in agile?
When problems come up and you don't know which path to take a team will host a spike or experiment to determine best route.
63
What is a retrospective and when?
Retrospective is held at end of each iteration. What went well vs what didn't. Goal is for continuous improvement.
64
What is kaizen?
Continuous improvement.
65
Difference between agile and traditional regarding customer.
Traditional includes customer in beginning then tends to keep them at arms length. Agile includes customer throughout and gathers input.
66
What situation does an agile method work best in?
When there is complex decision making
67
When would a predictive methodology be the best choice?
When a project team knows most of the details and is rational.
68
What is a Stacy diagram?
Illustrates spectrum of environments....rational to chaos. Helps determine agile vs traditional
69
Does an agile practice have a PM?
No coach or servant leader.
70
Do agile projects have a project plan?
No
71
What is the agile manifestos? (Agile vs traditional) 4 of em
Value individuals and interaction over processes and tools. Working software over documentation Customer collaboration over contract negotiation Responding to change vs following a plan
72
Agile principles
1) our highest priority is to satisfy the customer through early and continuous delivery of valuable software. 2) welcome changing requirements, even late in development. Agile processes harness change for the customers competitive advantage. 3) Deliver working software frequently, from a couple of weeks to a couple of months, with a preference to the shorter time scale. 4) business people and developers must work together daily throughout the project. 5) build projects around motivated individuals. Give them the environment and support they need, and trust them to get the job done. 6) the most efficient and effective method of conveying information to and within a development team is face to face conversation. 7) working software is the primary measure of progress. 8) agile processes promote sustainable development. The sponsors, developers, and users should be able to maintain a constant pace indefinitely. 9) continuous attention to technical excellence and good design enhances agility 10) simplicity - the art of maximizing the amount of work not done - is essential. 11) the best architectures, requirements, and designs emerge from self-organizing teams. 12) at regular intervals, the team reflects on how to become more effective, then tunes and adjusts its behavior accordingly.
73
Agile principles (easy to remember)
1) continuous value 2) accept change 3) Deliver frequently and asap 4) no gap between AM and Ops 5) avoid micromanagement 6) face to face exchange 7) progress is results 8) constant pace/ development 9) better design, easier to maintain 10) simplicity is essential 11) teams are self organizing 12)daily stand up meetings
74
Ideal agile team description and team roles
Around 8 (plus or minus 3 team members) Includes: The development team The product owner Agile coach
75
What is the customer role in an agile methodology?
AKA product owner. Customer works with project sponsor to make sure adequately funded. Customer will help create the initial Backlog of features (tells us what they want) Customer writes the user stories.
76
Agile team members (role)
Team members are highly interchangeable. Should be cross functional T shaped skills (broad skills with in depth knowledge)
77
Agile coach (role)
A servant leader. When a new team member is hired, the coach helps this person understand how agile is interpreted. Helps eliminate obstacles. Can be called a team facilitator, Project manager, scrum master or a team lead. Title doesn't matter.
78
Stakeholders (role)
Anyone involved in the project.
79
Cone of uncertainty
Beginning of project = large estimate variability The longer the project, the more progress which means less margin of error for estimates.
80
Product roadmap
Overview of each planned release and its features
81
What is a wire frame
Rare agile documentation that shows user experience and user elements. It's quick and dirty.
82
Agile theme relates to?
What you are accomplishing during the current initiation.
83
Describe a good agile user story (INVEST)
Independent Negotiable Valuable Estimable Small Testable
84
Value stream mapping
Lean technique used to focus on value and identify waste.
85
Rolling wave planning
Instead of planning everything in beginning you plan in phases.
86
What is Relative sizing
Estimating by ranking stories based on their relative size to other stories. Goal is to rank one at a time not focusing being on precise but a rough estimate of most difficult to easiest tasks. Once done the team will assign points to each story Used when planning the next iteration.
87
What is wideband Delphi estimating?
Goal is to get expert estimates without group member bias. During meeting, issue is discussed without assigning numbers. After the meeting, individuals prepare estimates alone. Take data, graph it (without name of estimator) and then group discuss range.
88
What is planning poker?
Estimating technique. Works with about 10 people...assign value at once at end of each user story.
89
What is affinity estimating?
A way to rapidly estimate your back log. 1) team decides ranking system (xl,l,m,s,xs) 2) each story is read out loud 3) with no discussion team assigns value
90
What is ideal time?
The literal definition of how much time a project would take without interruptions or distractions.
91
What is elapsed time?
Ideal time plus distractions or delays. Ideal would be 6 hour drive. Elapsed time would be 8 hours.
92
What is iteration 0?
First iteration for planning
93
What is iteration h?
Last iteration where there are no need features.
94
What is Parkinsons law?
States an activity will take as much time as you allow it.
95
What is time boxing?
Sets a fixed reasonable time allotment for each user story. Positive: maintains urgency and focus. Negative: could result in wasted effort. Iteration stops regardless.
96
What is continuous integration?
All code changes are checked in and entire system is built and tested at end of each day. Helps determine what change broke the system.
97
What is reported in an agile meeting?
1) What they have been working on 2) what they plan to do today 3) what obstacles they are encountering.
98
What is an information radiator?
Big visual in an effort for transparency. Shows progress so nobody can lie and highlites who is failing.
99
Ideal physical environment for agile?
Large open environment where employees are face to face no head phones no large barriers. Open door policy. All about the team.
100
What is servant leadership?
Modeling the behaviors and values that you desire the team to adopt and not asking anything from your team that you would not do yourself. Allows teammembers to take lead. Egoless. Mostly applies to the "coach" but could be anyone.
101
What is a Hybrid approach?
Can use agile type of meetings/communication bit the project plan is more traditional. Can be traditional but use agile mindset to overcome hurdles.
102
Which approach is best (agile vs traditional)?
No one size fits all. The more uncertain the more you should be agile. Construction is usually more predictive/traditional Gravitate toward answer where we work together to adapt to their needs and adopt a hybrid approach. Hybrid is best!
103
What is an "input"?
just as ingredients are the building blocks for recipes. inputs are raw materials.
104
What are "tools and techniques"?
action or method used to turn an input into an output. tool could be a software to help plan the project. technique could be flowcharting.
105
What are "outputs"
part of a bigger deliverable. output is the result of our effort.
106
Words associated with "initiating"
Start Begin
107
Words associated with "Planning" AND "Initiating"
Create Develop Identify
108
Words associated with "Planning"
Start, Begin
109
Words associated with "Executing"
Manage Acquire Do
110
Words associated with "Monitoring and Controlling"
Validate Review Control Monitor Compare Adjust
111
Words associated with "Closing"
Close
112
What is one of the biggest misconceptions people have of project groups/ phases?
They think that you only do: - initiating/ planning/ executing/ monitoring and controlling/ closing once. All 49 processes could be performed one or more times in each project phase.
113
What consists in Process Group One - Initiating? (3 items)
Made up of only two processes: - Develop Project Charter - Identify Stakeholders - assumption list
114
When should the initiating process be performed?
should try to be done first or early on in the process. This is important because we want the project to be initiated properly.
115
How do you know a project was initiated properly?
a project was initiated properly because it would have: - clear business need defined (project charter) - clear direction for scope of project (project charter) - clear list of why the project was chosen (Project charter) - list of project stakeholders (identify stakeholders)
116
Can you "initiate" a project more than once?
Yes - it can be beneficial to initiate the project during each phase of a long or riskier project to maintain focus
117
What makes Process Group Two - Planning? (25 processes memorize)
1) Develop Project Management Plan 2) Plan Scope Management 3) Collect Requirements 4) Define Scope 5) Create Work Breakdown Structure 6) Plan Schedule Management 7) Define Activities 8) Sequence Activities 9) Estimate Activity Durations 10) Develop Schedule 11) Plan Cost Management 12) Estimate Costs 13) Determine Budget 14) Plan Quality Management 15) Plan Resource Management 16) Estimate Activity Resources 17) Plan communication Management 20) Plan risk management 21) Identify Risks 22) Perform Risk Analysis 23) Plan Risk responses 24) Plan procurement management 25) Plan Stakeholder Engagement
118
What consists in Process Group Three - Executing?
This phase the work of the project actually gets carried out. manage team manage commnunications manage stakeholder engagement (control scope creep) direct and manage project work manage project knowledge manage quality acquire resources develop team
119
What consists in Process Group Four - Monitoring and Controlling?
taking results from the execution phase and comparing to the plan. if the results differ - we either change the plan or we go back to the execution phase and change how we did something. - monitor and control project work - perform integrated change control - validate scope - control scope - control schedule - control costs - control quality - control resources - monitor communications - monitor risks - control procurements - monitor stakeholder engagement
120
How many "inputs" will the monitoring and controlling processes have?
They will have two inputs. One of these will be something that was planned - the other will be an actual result. Comparing the product with the expectation. Work experiment and project management plan.
121
What Makes Process Group Five - Closing?
The project does NOT end with customer acceptance. After a project has been verified against scope and delivered to satisfaction - post project (update records, lessons learn, team release, project archives are carried out).
122
What is "Integration Management"?
7 processes that are soley on the project manager. the practice of making certain that every part of the project is coordinated. In integration management, the project is started, the project manager assembles the project plan, executes the plan, and verifies the results of the work, and then the project is closed.
123
What is the philosophy behind integration management (threefold):
Planning is a team activity - decision making in execution phase is not. plans/ projects change over time and will need to be updated. integration processes need to be tailored to fit the size and complexity of a project.
124
What are the 7 Integration Processes?
Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Manage Project Knowledge Monitor and Control Project Work Perform Integrated Change Control Close Project
125
What is the Integration Management Process in the Initiation Process Group?
Develop Project Charter
126
What is the Integration Management Process in the Planning Process Group?
Develop Project Management Plan
127
What is the Integration Management Process in the Executing Process Group?
Direct and Manage Project Work Manage Project Knowledge
128
What is the Integration Management Process in the Monitoring and Controlling Process Group?
Monitor and Control Project Work Perform Integrated Change Control
129
What is the Integration Management Process in the Closing Process Group?
Close Project or Phase
130
What is the Primary Output for the "Develop Project Charter" Process?
Project Charter and Assumption Log
131
What is the Primary Output for the "Develop Project Management Plan" Process?
Project Management Plan
132
What is the Primary Output for the "Direct and Manage Project Work" Process?
Deliverables Work Performance Data Issue Log
133
What is the Primary Output for the "Manage Project Knowledge" Process?
Lessons Learned Register
134
What is the Primary Output for the "Monitor and Control Project Work" Process?
Work Performance Reports goes in. Work performance reports come out.
135
What is the Primary Output for the "Perform integrated Change Control" Process?
Approved Change Requests Project Documents Updates (Change log)
136
What is the Primary Output for the "Close Project" Process?
Final Product Final Report Project Documents Updates
137
Initiating > Develop Project Charter > Project Charter & Assumption Log What is the project charter?
The project's birth certificate. document that starts the project.
138
Initiating > Develop Project Charter > Project Charter & Assumption Log Why is the Project charter important?
Essential for creating a project. No project charter = no official project = no official power as a Project Manager
139
Initiating > Develop Project Charter > Project Charter & Assumption Log When is the project charter performed?
Earliest performed. some light pre-planning can occur before the charter but nothing is official until it is done.
140
Initiating > Develop Project Charter > Project Charter & Assumption Log Input for a project charter?
Business case Project benefit plan Business case - describes the need for the project, the problem it will solve and its benefit cost analysis. project benefits plan - describes how the project contributes to the organization
141
Initiating > Develop Project Charter > Project Charter & Assumption Log What are project selection Methods?
Benefit Measurement methods - most common method used to quantify monetary benefits to selecting the project. Constrained Optimization - calculus/ programming methods. Benefit Cost Ratio Economic Value Add Internal Rate of Return Net Present Value Opportunity Cost Payback Period Return on Investment Return on Invested Capital
142
Initiating > Develop Project Charter > Project Charter & Assumption Log What is the Benefit Cost Ratio?(BCR)
Ratio of benefits to cost. cost of shrimp lights: $50 market rate for shrimp lights: $200 BCR/ Benefit Cost Ratio is $4:$1 profit.
143
Initiating > Develop Project Charter > Project Charter & Assumption Log What is Economic Value Add (EVA)?
What you made minus what you could have made. how much value a project has truly created for shareholders....factors in opportunity cost. After tax profit - (capital expenditures x cost of capital) = Economic Value Added Example: invested into xbox: $175 returned net profit: $10 could have made 6% in interest = $10.50 $175 - (175 x 0.06) = -0.50 we would have been better off investing in savings.
144
Initiating > Develop Project Charter > Project Charter & Assumption Log What is Internal Rate of Return (IRR)?
compares the projects value in a percentage...looks at it as an interest rate.
145
Initiating > Develop Project Charter > Project Charter & Assumption Log What is Opportunity Cost?
Determines the cost of investing in other opportunities....the smaller the opportunity cost the better the project looks
146
Initiating > Develop Project Charter > Project Charter & Assumption Log What is Payback Period?
determines how long would it take to get back the money you invested in the project. The goal would be the quicker the better.
147
Initiating > Develop Project Charter > Project Charter & Assumption Log What is Present Value and Net Present Value?
Present value is the idea that a dollar today is worth more tomorrow. takes time out of the equation. 3 payments of $300; project is worth less than $300 since it won't be paid until completion. Bigger is better. Net Present Value takes out time but factors in cost. constructed an xbox for present value of $500 but it cost $350 to make the Net Present Value is actually $150.
148
Initiating > Develop Project Charter > Project Charter & Assumption Log What is Return on Investment (ROI)?
shows % a company makes by investing. Buy $20 in eggs but it normally costs $25; the ROI would be 25% bigger the better.
149
Initiating > Develop Project Charter > Project Charter & Assumption Log What is Return on Invested Capital (ROIC)?
For every dollar I invest, how many dollars will I get back in return? ROIC = Net income (after tax)from a project / total capital invested Invested: $250 Generated: $60 in revenue Cost: $20 Tax: $8 ROIC = $32/ $250 ROIC = 12.5% ROIC annually
150
Initiating > Develop Project Charter > Project Charter & Assumption Log What are the tools/technology for a Project Charter?
Expert Judgement Data Gathering Interpersonal and Team Skills Meetings
151
Initiating > Develop Project Charter > Project Charter & Assumption Log What is the output for developing a Project Charter?
Project Charter Assumption Log (allows us to move forward without fact checking everything we know)
152
Planning > Develop Project Management Plan > Project Management Plan Why is a project Management plan important?
specifies the who, what, when, where and how. guides the team's work on the project.
153
Planning > Develop Project Management Plan > Project Management Plan When is the Project Management Plan performed?
The plan is progressively elaborated; meaning it is continually updated.
154
Planning > Develop Project Management Plan > Project Management Plan What would be the inputs for a project management plan?
Project Charter Enterprise Environmental Factors Organization Process Assets
155
Planning > Develop Project Management Plan > Project Management Plan What would be the tools/ techniques used for a project management plan?
Expert Judgement Data Gathering Interpersonal and Team Skills Meetings
156
Planning > Develop Project Management Plan > Project Management Plan What would be the output of a Project Management Plan?
The output would be the Project Management Plan itself. It is a formal, approved document that defines how the project is managed, executed and controlled. Keys: Formal, single document.
157
Planning > Develop Project Management Plan > Project Management Plan Who approves a Project Management Plan?
could be any of the following: NOT THE CUSTOMER - Project Manager - Project Sponsor - Functional Manager - The team who is putting in the work.
158
Planning > Develop Project Management Plan > Project Management Plan What is in a project management plan?
basically its a combination of all the other management plans and baselines in one formal document. Scope management plan REquirements management plan schedule management plan Cost management plan quality management plan resource management plan communications management plan risk management plan procurement management plan stakeholder engagement plan change management plan configuration management plan scope baseline schedule baseline cost baseline performance measurement baseline project life cycle description development approach managmeent reviews
159
Executing > Direct and Manage Project Work > Deliverables, Work Performance and Issue Log What is the Direct and Manage Project Work?
contrary to how it seems.....most of the time a PM spends is in execution phase. This is where you create the project deliverables.
160
Executing > Direct and Manage Project Work > Deliverables, Work Performance and Issue Log Why is the Direct and Manage Project Work so important?
This process is where you start to see real progress. buildings get built; roads get paved; websites get coded, etc.
161
Executing > Direct and Manage Project Work > Deliverables, Work Performance and Issue Log When is the Direct and Manage Project Work phase performed?
No finite amount of time. You could repeat this process multiple times. this is not a singular occurrence - but occurs anytime you are creating deliverables.
162
Executing > Direct and Manage Project Work > Deliverables, Work Performance and Issue Log What are the Inputs to Directing and Managing Project Work phase?
Inputs: Project Management Plan (guides the management and execution of project) Project Documents Any approved change request (tells you new specifications of the deliverable you are making) Enterprise Environmental Factors Organized Process Assets
163
Executing > Direct and Manage Project Work > Deliverables, Work Performance and Issue Log What are the tools/ techniques used during the Direct and Manage Project work phase?
Expert Judgement Project Management Information System (keeps you on schedule, updates files) Meetings
164
Executing > Direct and Manage Project Work > Deliverables, Work Performance and Issue Log What are the outputs of the Direct and Manage Project work (within the execution phase)?
Deliverables (tasks accomplished to evaluate for project approval) Work Performance Data (inputs into M and C) Issue Log (unresolved problems)
165
Executing > Direct and Manage Project Work > Deliverables, Work Performance and Issue Log What comes out of an issue log?
potential change requests potential project management plan updates project document updates organizational process assets updates (lessons learned register, etc)
166
Executing > Manage Project Knowledge > Lessons Learned Register What is managing project knowledge?
Use previous lessons learned to help during your own execution phase. also plan to update this as you go along a swell.
167
Executing > Manage Project Knowledge > Lessons Learned Register Why is the managing project knowledge phase important?
history is doomed to repeat itself if we don't learn from it.
168
Executing > Manage Project Knowledge > Lessons Learned Register When do you manage project knowledge?
technically anytime update AFTER a deliverable has been completed.
169
Executing > Manage Project Knowledge > Lessons Learned Register Inputs for managing project knowledge
Project Management Plan (influences how you do your project) Project Documents Deliverables Enterprise Environmental Factors Organizational Process Assets
170
Executing > Manage Project Knowledge > Lessons Learned Register What are tools and techniques for managing project knowledge?
Expert Judgement Knowledge Management Information Management System (sharepoint)
171
Executing > Manage Project Knowledge > Lessons Learned Register What is the difference between explicit and tacit knoweldge?
explicit knowledge is info written down for future lessons learned. tacit knowledge is belief or opinion or ability.
172
Executing > Manage Project Knowledge > Lessons Learned Register What is the output of managing project knowledge?
updates the lessons learned register with what did and did not work out.
173
Monitoring and Controlling > Monitor and Control Project Work > Work Performance Reports What is the process of monitoring and controlling project work?
takes a look at the work being done on a project and compares the deliverables to the project plan
174
Monitoring and Controlling > Monitor and Control Project Work > Work Performance Reports What is the process of Monitor and Control Project Work?
Compares the work already done (deliverable) with the project maanagement plan to make sure everything is gravy.
175
Monitoring and Controlling > Monitor and Control Project Work > Work Performance Reports Why is the M & C project work important?
identifies any necessary changes that need to happen to either the work process or the project management plan itself.
176
Monitoring and Controlling > Monitor and Control Project Work > Work Performance Reports When is M&C performed?
closely tied to the Direct and Manage Project Work phase and takes place as long as there is work on the project to be carried out.
177
Monitoring and Controlling > Monitor and Control Project Work > Work Performance Reports What are inputs for Monitoring and Controlling?
Project Management Plan Project Documents (assumption Log, estimates) Cost Forecasts (issue log, lessons learned, milestone list, quality reports, risk register, risk report) Schedule Forecasts Work Performance Information
178
Monitoring and Controlling > Monitor and Control Project Work > Work Performance Reports What are the tools/techniques used for M & C?
Expert Judgement Data Analysis Decision Making Meetings
179
Monitoring and Controlling > Monitor and Control Project Work > Work Performance Reports What is the output for the M and C phase?
Work Performance Reports (they go in...they go out...actionable items) Change Requests (if work performance is bad then we need to make changes) Project management plan updates (if we need to fix something) Project Document Updates (if we change one we change them all)
180
Monitoring and Controlling > Perform Integrated Change Control > Approved Change Requests and Update Change Log What does it mean to perform integrated change control?
one of the most important processes. every change (whether requested or not) needs to be processed through Perform Integrated Change Control. Allows you to assess real impact on a project. Change the project to accept the deliverable or change the plan to create a diff deliverable.
181
Monitoring and Controlling > Perform Integrated Change Control > Approved Change Requests and Update Change Log Why is the Perform Integrated Change Control Log important?
assesses real impact across project. Monitor and Controlling manages the way the work is carried out - Integrated Change Control is how we decide if its responsible to allow the change.
182
Monitoring and Controlling > Perform Integrated Change Control > Approved Change Requests and Update Change Log When is Perform Integrated change control performed?
takes place as long a sthere is work on the project to be carried out. some organizations have a change control board that reviews the change requests.
183
Monitoring and Controlling > Perform Integrated Change Control > Approved Change Requests and Update Change Log What are the inputs to perform integrated change control?
Inputs: Project Management Plan Project Documents Work Performance Reports Change Requests (enterprise Environmental Factors and Organizational Process Assets)
184
Monitoring and Controlling > Perform Integrated Change Control > Approved Change Requests and Update Change Log What tools/techniques are used for the perform integrated change control phase?
Expert Judgement Change Control Tools (any system or if there is a formal board) data analysis decision making meetings
185
Monitoring and Controlling > Perform Integrated Change Control > Approved Change Requests and Update Change Log What type of outputs come from a perform integrated change control request?
An approved Change Request (or denial) Update of change log and lessons learned (formal documents)
186
Closing>Close a project or phase > Final Product, Service or Result; Final report; Project Document Updates What does it mean to close a project?
projects are temporary. all about shutting down a project properly. Includes the paperwork to do so like archives, lessons learned, and updating all organizational process assets.
187
Closing>Close a project or phase > Final Product, Service or Result; Final report; Project Document Updates Why is closing a project important?
projects that skip this are left open and ongoing. ensures these documents become organizational process assets for future use on new projects.
188
Closing>Close a project or phase > Final Product, Service or Result; Final report; Project Document Updates When is closing a project performed?
performed as the last process on a project or phase.
189
Closing>Close a project or phase > Final Product, Service or Result; Final report; Project Document Updates What are inputs to closing a project?
Project charter - charter shows exit criteria so we can validate it is truly complete. Project management plan - confirm all requirements are completed Project documents - need to complete accepted deliverables (make sure we are done) business documents (closed out) organizational procsss assets procurement documentation
190
Closing>Close a project or phase > Final Product, Service or Result; Final report; Project Document Updates What tools are used for closing a project?
Expert Judgement Data Analysis Meetings
191
Closing>Close a project or phase > Final Product, Service or Result; Final report; Project Document Updates What are the outputs for closing a project?
Lessons learned updated (project documents updated) final product or service final report
192
What is the "Agile perspective on integration management"?
- the team does the work of the pm - project charter is developed by team - Project Management plan is used to mitigate risk; agile welcomes and embraces the change. - Direct and Manage project work has an output of deliverables, work performance data and issue log. this is delivered in smaller iterations during an agile. - managing project knowledge is shared in a lessons learned register for PM; shared in daily meetings iwth agile. - managing and controlling work is done through daily meetings with hurdles and face to face discussions - agile teams do not need an integrated change control. they welcome change. - agile teams don't produce much documentation so not as formal of a closure.
193
What is Scope Management?
Scope Management is a logical group of processes to help you understand: - requirements how many rooms do we paint - breakdown how do we paint, when do we paint - control Scope make sure we are painting and quality of paint - verify project was completed. Ensure all rooms have been painted.
194
What does scope mean?
Everything that must be completed to meet the product requirement. work needed to successfully complete the project AND ONLY the work.
195
What is the two philosophies behind scope management?
Project manager is ALWAYS in control. Any change should be handled in a structured way.
196
What would be "good" scope management?
Makes sure the scope (what is needed to be accomplished to be succesful) is well communicated. un-necessary changes are limited.
197
What are the overall goals of scope management?
define the need set stakeholder expectations deliver expectations (communicate) manage changes minimizes surprises
198
What is "gold plating"?
deliver more than agreed upon exceed quality - sometimes customers will ask for more.
199
what are negatives to "gold plating"?
increase risk increase uncertainty increase cost potentially add probelms
200
What is the formal Scope Management Process?
Plan Scope Management - figure out how to stop Microsoft from changing the specs of xbox. Gather the requirements - what do we need to do to create the xbox. Define the Scope - break project into objectives Create the Work Breakdown - break objectives into activities Structure (and baseline) Validate and Control the Scope make sure we are making xbox well.
201
What process groups does Scope Management engage in?
Planning Monitoring and Controlling
202
Planning > Plan Scope Management > Scope Management and Requirements Management Plan What would be an input for Planning Scope Management?
Inputs: - Project Charter - Project Management Plan - Enterprise Environmental FActors - Organizational Assets
203
Planning > Plan Scope Management > Scope Management and Requirements Management Plan What would be the Tools/Techniques for Planning Scope Management?
Expert Judgement Data Analysis Meetings
204
Planning > Plan Scope Management What would be the output for when you Plan Scope Management?
Create the Scope Management Plan Create the Requirements Management Plan
205
Planning > Plan Scope Management > Scope Management and Requirements Management Plan What is a Requirements Management Plan?
Defines the activities the team will perform in order to gather and manage the project requirements. This is the PLAN for how the requirements will be managed. DOES not contain the requirements itself.
206
Planning > Plan Scope Management > Scope Management and Requirements Management Plan Why is the Requirements Management Plan important?
Shows how requirements will be gathered. Shows how decisions will be made. How requirements will be documented.
207
Planning > Collect Requirements > Requirement Documentation What is Collecting Requirements?
Process of understanding what it will take to satisfy the stakeholders. Then documenting that understanding.
208
Planning > Collect Requirements > Requirement Documentation Why is Collecting Requirements important?
This document helps keep everyone focused on the stakeholders expectations. Refers to this document during scheduling, budgeting, quality specifications, risk factoring and resource planning.
209
Planning > Collect Requirements > Requirement Documentation What are inputs when collecting requirements?
Inputs: - Stakeholder Engagement plan - Project Charter - Project Management Plan - Project Documents (Assumption Log, Lessons Learned, Stakeholder Register) - Business Agreements - Enterprise Environmental Factors - Organizational Process Assets
210
Planning > Collect Requirements > Requirement Documentation What are the Tools/ Techniques for Collecting Requirements?
T&T: - Data Gathering (brainstorming, interviews, focus groups, questionaires, benchmarking) - Data Analysis - Decision Making - Data Representation
211
Planning > Collect Requirements > What are the outputs for Collecting Requirements?
Outputs: - Requirement Documentation - Requirements Traceability Matrix
212
Planning > Collect Requirements > Requirement Documentation What is a "Requirements Traceability Matrix"?
A document that identifies the source of each requirement (product feature needed or service completed). Can include information about who owns the requirement, the status of the requirement, etc.
213
Planning > Define Scope> Project Statement and Project Documents What is defining Scope?
Develop a clear understanding of the requirements to be: - executed - verified - delivered
214
Planning > Define Scope> Project Statement and Project Documents Why is defining scope important?
Scope is what drives the execution of a project. The importance of defining scope correlates with the amount of risk you are willing to tolerate. The greater you define the exact needs - the more likely you are to succeed.
215
Planning > Define Scope> Project Statement and Project Documents When do you 'define scope'?
As soon as the collect requirements process has been completed. you need to know the requirements before you can plan how you accomplish them/ how you get there.
216
Planning > Define Scope> Project Statement and Project Documents Inputs for Defining Scope?
Inputs: Project Charter Project Management Plan Project Documents (assumption log, requirements documentation, risk register) Environmental Factors Organizational Process Assets
217
Planning > Define Scope> Project Statement and Project Documents What are the Tools and Techniques for Defining Scope?
T&T: Expert Judgement Data Analysis Decision Making Product Analysis
218
Planning > Define Scope> What are the outputs for defining scope?
Outputs: - Project Scope Statement - Project Documents Updates
219
Planning > Define Scope> Project Statement and Project Documents What is included in a Project Scope Statement (6)?
Contains: - Goal of the project - Project Description - Requirements of a Project - Constraints of a Project - Assumption of a Project - Identified Risks related to the scope
220
Planning > Create Work Breakdown Structure> Scope Baseline (includes actual Work Breakdown Structure) Why is the Work Breakdown Structure Important?
Once created, is a hub of info. and is most important component of a project plan. A WBS is used when creating risk analysis, activities, costs, quality attributes and procurement decisions.
221
Planning > Create Work Breakdown Structure> Scope Baseline (includes actual Work Breakdown Structure) What is the primary tool for verifying and controlling the project scope?
The primary tool is Creating a Work Breakdown Structure
222
Planning > Create Work Breakdown Structure> Scope Baseline (includes actual Work Breakdown Structure) When do you create a WBS?
After a project charter is created, you identify who is making these expectations (stakeholders), after you collect their expectations (requirements) and the scope has been defined (determined how you are going to meet their expectations).
223
Planning > Create Work Breakdown Structure> Scope Baseline (includes actual Work Breakdown Structure) What are Inputs for WBS?
Inputs: - Project Management Plan - Project Scope Statement - Project Requirements Documentation - Enterprise Environmental Factors - Organizational Process Assets
224
Planning > Create Work Breakdown Structure> Scope Baseline (includes actual Work Breakdown Structure) What are the Tools and Techniques for creating a WBS?
T & T: - Expert Judgement - Decomposition (main tool - breaks down deliverables into smaller components
225
Planning > Create Work Breakdown Structure> Scope Baseline (includes actual Work Breakdown Structure) How do you know you have broken down your work flow small enough for a WBS to be effective?
Ask yourself: - are your work packages small enough to be estimated for time and cost? - is the team satisifed that the current level of detail provides enough info to proceed? - is each "work package" small enough that you can assign a value to a single person?
226
Planning > Create Work Breakdown Structure> What is the outputs when you create a Work Breakdown Structure?
The Scope Baseline: A baseline is the original plan plus all approved changes. Work Breakdown Structure: A document that defines each language in a WBS
227
Planning > Create Work Breakdown Structure> Scope Baseline (includes actual Work Breakdown Structure) What is the following: Control Account Planning Package Work Package
How you break down your wbs Control Account = Monthly Concur/ Online Purchasing App Planning Package = Onboarding Supplies Work Package = Blue Books (assigned to one specific person)
228
Monitor and Controlling > Validate Scope > Accepted Deliverables & Work Performance What is Validating Scope?
Validate Scope is the process of ensuring the product, service or result that matches the documented scope. Making sure we aren't wasting our time.
229
Monitor and Controlling > Validate Scope > Accepted Deliverables & Work Performance What is the difference between controlling quality vs validating scope?
Controlling quality is done before you validate. Control quality is concerned with correctness Control Scope is concerned with completeness
230
Monitor and Controlling > Validate Scope > Accepted Deliverables & Work Performance Why is validating Scope important?
Once the validation of scope is completed - the project goes to be accepted by: - Project Manager - Customer - The Sponsor Sometimes functional manager or stakeholder
231
Monitor and Controlling > Validate Scope > Accepted Deliverables & Work Performance When do you validate scope?
Validate scope after the quality has been controlled. Can be performed multiple times throughout a project usually performed after at least some of the product components have been delivered
232
Monitor and Controlling > Validate Scope > Accepted Deliverables & Work Performance What are the inputs to Validating Scope?
Main one is a verified deliverable Work performance data Remember you are in the monitoring and controlling phase
233
Monitor and Controlling > Validate Scope > Accepted Deliverables & Work Performance What would be the T&T for validating scope?
Inspections Decision Making
234
Monitor and Controlling > Validate Scope > What are the outputs for Validating Scope?
"Accepted" Deliverables MandC - input work data you get back work data Change Requests (assuming the output sucks) Project Document Updates
235
Monitor and Controlling > Control Scope > Work Performance Data/ Change Requests What is Controlling Scope?
Maintain Control by preventing scope change requests from overwhelming the project. Keeps the scope baseline current.
236
Monitor and Controlling > Control Scope > Work Performance Data/ Change Requests Why is controlling scope important?
Makes sure all change requests are understood and managed. This prevents un-necessary changes from occuring.
237
Monitor and Controlling > Control Scope > Work Performance Data/ Change Requests When is controlling scope performed?
ongoing process. Begins as soon as the scope baseline is created. Aka after WBS
238
Monitor and Controlling > Control Scope > Work Performance Data/ Change Requests What are the Inputs of Controlling Scope?
Work Performance Data Updates to Project Management Plan Updates to Project Documents/ Process Assets
239
Monitor and Controlling > Control Scope > Work Performance Data/ Change Requests What is the Tool and Technique for Controlling Scope?
Analyzing Data
240
Monitor and Controlling > Control Scope > Work Performance Data/ Change Requests What is the output for Controlling Scope?
Work Performance Information (anytime you input work info you output work info) Change Requests (any decision making still goes to a change request) Project Management Plans Project Document Updates
241
What is the Agile Perspective on Scope Management?
Predictive Approach tries to identify all and control change. Agile approach tries to get product in customer's hands and then embrace any new requirements discovered.
242
Agile perspective on "Plan Scope Management" phase
low emphasis because the overall process is flexible.
243
Agile perspective on "Collect Requirements" Phase
In agile setting, this is an ongoing process because we give you the prototype and you tell me new features you would like or changes.
244
Agile perspective on "define scope" phase How does agile define scope?
Agile setting defines scope through user stories, story maps and release plans. Predictive breaks it down to objectives and activities. (WbS)
245
Agile perspective on "Create WBS"
Predictive WBS is broken down through Decomposition of activities. Agile WBS is broken through disaggregation of Story Maps into smaller stories.
246
Agile perspective on "Validate Scope"
every phase/ iteration in an agile setting is validated by the teams approval of "done"
247
agile perspective on controlling scope
large amount of change requests for predictive setting would be troublesome (because all risk is already predicted) large amount of change requests in agile is encouraging as there is high user engagement
248
What is the philosophy of Schedule Management?
The project manager should be in control of the schedule (and not vice versa) A schedule should be rigorously managed but as flexible as possible.
249
What are the six (6) processes related to schedule management?
1) Plan Schedule Management (planning out the next five processes) 2) Define Activities (list the project activities) 3) Sequence Activities (order the activities and create the project diagram) 4) Estimate Activity Durations (determine time estimates for each activity) 5) Develop Schedule (create the schedule) 6) Control Schedule (monitor and adjust schedule performance)
250
Planning > Plan Schedule Management > What is the main output of "Plan Schedule Management"?
The Schedule Management Plan
251
Planning > Define Activities > What is the main output of "Define Activities"?
Activity List Activity Attributes
252
Planning > Sequence Activities > What is the main output of "Sequence Activities"?
Project Schedule Network Diagrams (activity sequence list or visual)
253
Planning > Estimate Activity Durations > What is the main output of "Activity Duration Estimates"?
Activity Duration Estimates
254
Planning > Develop Schedule > What is the main output of "Develop Schedule"?
Project Schedule Schedule Baseline
255
Planning > Control Schedule > What is the main output of "Control Schedule"?
Work Performance Information Change Requests Schedule Forecasts
256
Planning > Plan Schedule > Schedule Management Plan What is the main input when planning a schedule management plan?
Project Charter Project Management Plan Enterprise Factors Organizational Assets
257
Planning > Plan Schedule > Schedule Management Plan What is the T&T for planning a schedule management plan?
Expert Judgement Data Analysis Meeting
258
Planning > Plan Schedule > Schedule Management Plan What is the output for a schedule management plan?
Schedule Management Plan
259
Planning > define activities > List Activities & Activity Attributes What is defining the activity?
Once you create the scope baseline, you can use this to decompose (breakdown) the work into the smaller activities that are necessary to do the project. This list is what needs to occur for the project to be completed.
260
Planning > define activities > List Activities & Activity Attributes Why is defining the activity important?
You cannot build a schedule until you know what needs to happen.
261
Planning > define activities > List Activities & Activity Attributes When is defining the activity performed?
Common to create the activity list after the requirements documentation.
262
Planning > define activities > List Activities & Activity Attributes What are the inputs for Defining Activities?
Project Management Plan Scope Baseline Schedule Management Plan
263
Planning > define activities > List Activities & Activity Attributes What tools and techniques does defining activities involve?
Expert Judgement Decomposition Rolling Wave Planning (plan is continuously evolving)
264
Planning > define activities > What are outputs?
Activity List Activity Attributes Milestone List Change Requests Project Management Plan UPdate
265
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What is sequencing activities?
arranging the activity list in order they should be performed.
266
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What is a network logic diagram?
a picture in which each activity is drawn and placed in order it must be performed. think of dominos
267
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update When is sequencing activities performed/
after you define your activity but before you schedule
268
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What are inputs to sequencing activities?
Schedule Baseline Schedule Management Plan Activity List
269
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What are the tools and techniques used sequencing activities?
Precedence Diagramming Method (PDM) Dependency Determination and Integration Lead and Lags
270
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What is Precedence Diagramming Method?
Precedence Diagramming Method creates a graphical visual of the schedule activities in order in which they must be performed. rectangles and lines/nodes
271
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What is Dependency Determination and Integration?
Dependencies influence which activities must be performed first. In making a scrambled egg - the mixing of the egg is dependent on cracking the egg.
272
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What are the 4 main kinds of dependecies?
Mandatory Dependencies (one that can't be broken) Disretionary Dependencies (best practice dictates we paint before we lay down carpet...but technically we still could carpet first) External Dependencies (manufacturer etas...capsa) Internal Dependencies (marketing team has to finish logos before website can be released)
273
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What is Leads and Lags?
A lead is one activity getting a jumpstart on another. a lag is a waiting period that exists between two activities.
274
Planning > Sequence Activities > What are the outputs for sequencing activities?
The project Schedule Network Diagram (diagram shows a visual way of depicting schedule activities and their dependencies. project document updates
275
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What is estimating activity durations?
analyzing each activity to see how long it will take.
276
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What are inputs to estimating activity durations?
Project Management Plan (Schedule Management Plan & Scope Baseline) Project Documents (Activity List, Activity Attributes, Resource Requirements, Resource Calendars) Enterprise Factors Organizational Process Assets
277
Planning > Sequence Activities > Project Schedule Network Diagram and Project Update What are the 4 main kinds of dependencies?
Mandatory Dependencies (one that can't be broken) Disretionary Dependencies (best practice dictates we paint before we lay down carpet...but technically we still could carpet first) External Dependencies (manufacturer etas...capsa) Internal Dependencies (marketing team has to finish logos before website can be released)
278
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is Estimate Activity Durations?
This is monitoring how long each activity will take - not focusing on the effort.
279
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates Why is Estimating Activity Durations Important?
These activity duration estimates will become a primary input into creating the schedule.
280
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates When is Estimating Activity Durations performed?
After the activity resource requirements have been gathered and before the schedule is developed.
281
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What are the inputs for Estimating Activity Durations?
Project Management plan Project Documents (Activity List, Activity Attributes and Resource Requirements, Resource Calendars) Enterprise Environmental Factors Organizational Process Assets
282
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What are the tools/techniques for Estimating Activity Durations?
Expert Judgement Analogous Estimating (comparing to previously done project [top down]) Parametric Estimating (Parametric Estimating is dimensional analysis....takes 1 person 10 minutes...takes 1000 people 100000 minutes Three Point Estimating (PERT: use three data points innstead of one. These are pessimistic, most likely and optimistic estimates) Bottoms Up Estimating (opposite of analogous estimating)
283
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is analogous estimating?
Top down estimating Comparing to an estimate from a previous project.
284
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is parametric estimating?
Scaleable estimating. If it takes 100 feet one day Then it will take 10 days to do 1000
285
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is 3 point estimating?
Aka PERT (program evaluation and review technique) Uses pessimistic, most likely, optimistic
286
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What are the two types of 3 point estimating?
Beta distribution Triangular distribution
287
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is Beta Distribution?
(Pessimistic + 4 x realistic/most likely+ optimistic)÷ 6
288
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is the standard deviation of a beta distribution?
(Pessimistic - optimistic)÷6
289
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is triangular distribution?
Evenly weighted. (Pessimistic + realistic/most likely+optimistic)/3
290
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is bottom-up estimating?
Opposite of analogous estimating Each step of an activity is added together. Accurate when there is few unknowns. Top down is comparing to a previous project and compares entire cost at once. Bottom up is adding up the tasks first then compiling into an estimate. This happens the most.
291
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is alternative analysis?
Make or buy analysis to determine if you should outsource or not. Point is to make optimal decisions.
292
Planning > Estimate Activity Durations > Duration Estimates, Basis Estimates, Project Document Updates What is reserve analysis?
Reserve time/contingency is extra time added to activity duration estimate. Revisited throughout project.
293
Planning > Estimate Activity Durations > What is the output for estimate activity Durations?
Durations Estimates Basis of Estimates (shows how Estimates were determined) Project Document Updates
294
Planning > develop schedule > schedule baseline and project schedule What are the inputs of a schedule?
Like 20 inputs: Project management plan (schedule management plan and scope baseline) Project documents (activity list, activity attributes, assumption log, Basis of Estimates, lessons learned, milestone list, Project schedule network diagrams, project team assignments, resource calendars, resource requirements, risk register) Agreements Enterprise environmental factors Organizational process assets
295
Planning > develop schedule > schedule baseline and project schedule What are the T&T used to create the schedule?
Schedule network analysis (group of techniques) Critical Path Method Resource optimization Data analysis Lead and lag PMInfomation system
296
Planning > develop schedule > schedule baseline and project schedule What is critical path?
A critical path is the combination of activities that, if delayed, will delay the projects finish.
297
Planning > develop schedule > schedule baseline and project schedule What is the purpose of critical path management?
1) calculate the finish date 2) identify the float (which activities can slip) 3) identify highest risk activities (can't slip)
298
Planning > develop schedule > schedule baseline and project schedule Describe traditional way of building the schedule?
Gather realistic activity duration Assemble schedule Identify the longest critical path Basically plan for the longest route.
299
Planning > develop schedule > schedule baseline and project schedule Describe critical chain method
Estimates each activity aggressively Builds the schedule network Adds a lump sum buffer to end of project track You don't let the team know of buffer so they are pressured into the aggressive schedule. Longest path - shortest path = invisible buffer
300
Planning > develop schedule > schedule baseline and project schedule What is resource leveling?
When your resource needs meet up with organizations ability to supply resources. Resource leveling is more about people/material Resource smoothing is about time constraint.
301
Planning > develop schedule > schedule baseline and project schedule How do you resource level?
1) use critical path method to calculate and analyze all network paths for project. 2) apply resources to see what effect is made to schedule. 3) creates a change to critical path and project completion date.
302
Planning > develop schedule > schedule baseline and project schedule What is resource smoothing?
Looks at the schedule when there is resource constraints. Resource smoothing is less disruptive - completion date and critical path do not change.
303
Planning > develop schedule > schedule baseline and project schedule What is "What-if scenario analysis"?
A way of looking at risk to determine how certain events or scenarios would impact the schedule. Goal = is schedule practical? Are the reserves and buffers appropriate?
304
Planning > develop schedule > schedule baseline and project schedule What is "schedule compression"?
Completing the schedule earlier without cutting the project scope.....without eliminating features.
305
Planning > develop schedule > schedule baseline and project schedule What is Crashing? What is fast tracking?
crashing means adding resources to an activity to complete more quickly. Crashing almost always increases costs. fast tracking means that you reorder the sequence of activities so that some of the activities are performed at the same time.
306
Planning > develop schedule > schedule baseline and project schedule What is "agile release planning"?
agile projects use the product backlog to create an overall release plan. prioritized by value to the customer and then estimated by difficulty. then the team selects the planned releases.
307
Planning > develop schedule > schedule baseline and project schedule What are the outputs to developing the schedule?
Create the schedule baseline Create the project schedule Create bar charts (or Gantt charts) to show length of activity schedule. Create Milestone Charts (represents key events) Project Schedule Network Diagram
308
Planning > develop schedule > schedule baseline and project schedule What are the outputs to developing the schedule?
Create the schedule baseline Create the project schedule Create bar charts (or Gantt charts) to show length of activity schedule. Create Milestone Charts (represents key events) Project Schedule Network Diagram Schedule Data Project Calendars Change Requests Project Management Plan Updates Project Document Updates
309
Planning > monitoring and controlling > Control Schedule What is the concept behind monitoring and controlling processes in general?
Compare the work results to the plan and ensure that they line up.
310
Planning > monitoring and controlling > Control Schedule What is controlling the schedule?
Making sure the time related performance on the project is in line with the plan.
311
Planning > monitoring and controlling > Control Schedule What are the inputs to controlling the schedule?
Project Management plan Project Documents (Lessons leanred, project calendars, project schedule, resource calendars, schedule data, work performance data, organizational process assets)
312
Planning > monitoring and controlling > Control Schedule What is the T&T for controlling the schedule?
Data Analysis (Earned Value Analysis, Iteration Burndown chart, performance reviews, trend analysis, variance analysis, What-if scenario analysis) Critical Path Method Project Management Information System Resource Optimization Leads and Lags Schedule Compression
313
Planning > monitoring and controlling > Control Schedule What are the outputs for controlling schedule?
Work Performance Information Schedule Forecasts Change Requests Project Management Plan Updates Project Document Updates
314
Planning > monitoring and controlling > Control Schedule What is the agile perspective of Schedule management?
Agile do not try to define scope up front. Agile expects sscope to change. The agile approach is to plan in much smaller, more flexible increments, prioritized by what is most most valuable. On-demand scheduling.
315
Planning > monitoring and controlling > Control Schedule What is agile perspective on Plan Schedule management?
low applicability to agile projects. each iteration or sprint has a plan for that particular sprint. one at a time.
316
Planning > monitoring and controlling > Control Schedule What is agile perspective on Estimating Activity Durations?
Agile projects do estimate, alhtough they do it differntly (planning poker, or relative sizing exercies)
317
Planning > monitoring and controlling > Control Schedule What is agile perspective on "Develop Schedule"?
Agile projects may develop release plans which show features
318
Planning > monitoring and controlling > Control Schedule What is agile perspective ofcontrolling schedule?
Agile monitor and adjust schedule performance during either their iteration planning or their respective at the end of an iteration.
319
What is "network path"?
a network path refers to a sequence of events that affect each other on the project from start to finish. highlite different sets of sequences in which activities must be performed.
320
What is a "critical path"?
made up of activities that cannot be delayed without delaying the finish of the project. critical path is the longest path.
321
Can you have more than one critical path in a project?
Yes - there could be two paths that tie for the longest path. In this event, schedule risk is increased because there is an increased number of ways the project could be delayed.
322
What is "float"?
Float is slack - how much time an activity can slip before it changes the critical path. maximum amount of time an acitivty can slip.
323
how much float does an item on a critical path take?
Zero float
324
What is "Early Start" and how do you calculate it?
Early start is the earliest date that something can start factoring in other dependencies.
325
What is the technique "forward pass"?
AKA Early Start. We are moving forward through the diagram.
326
What is "Early Finish" and how do you calculate it?
Early start date plus the duration estimate minus 1 unit.
327
What is "forward pass"?
AKA Early Finish
328
What is "Late Start" and how do you calculate it?
Says this is the latest the activity could start and not delay the project's finish date. You calculate this by adding the float to the early start
329
What is "backward pass"?
AKA late start
330
What is "Late Finish" and how do you calculate it?
Late finish is the late start plus the activity duration - 1 unit. Early finish would be week 8 day 1 Late finish would be week 8 day 6
331
What is "Free Float"?
AKA Free Slack. free float is the amount of time an acitivyt can be delayed without affecting the early start date of dependent acitivites. 9 - 10 - 4 9 - 6 - 4 19-15 = 4 free float.
332
What is "Negative Float"?
occurs when an activity's start date occurs before a precedening acitvity's finish date. negative float tells you when an activity's finish date happens vefore its scheduled start date. TELLS YOU YOUR SCHEDULE IS WRONG.
333
hOW do you fix a negative float ?
reworking the logic of the schedule "crashing" "fast tracking"
334
What is a "dummy" activity?
a activity visual in a chart that shows the relationship but doesn't show the time associated.
335
What does a float sample look like? Formulas
ES Duration EF LS FLOAT LF EF (aka forward pass)= ES + D - 1 ES= EF - D + 1 LS= LF - du + 1 LF= LS +du - 1 Critical Path has zero float Float = LF- EF simultaneously Float = LS - ES
336
What is a lead/lag time? video
value added to work. lag time is + time (increases duration) Example: anytime you are waiting. Concrete is poured - takes two days to harden. lead time is negative (-) time (reduces duration) Example: procurement takes 30 days; need cabinets in 45 days....lead time is 15 days (when you reorder)
337
Life-Cycle Costing
Estimating total cost from start to finish.
338
Value-Engineering
Squeeze more benefits w/o reducing scope. Gets more out of project in every phase.
339
What is the "general rule" regarding scope, schedule and cost/budget activities?
Scope is first Schedule is second Cost and budget is 3rd.
340
Planning > Plan Cost Management > Cost Management Plan What are the inputs for planning cost management plan?
Input: Project charter Project management plan Enterprise environmental factors Organizational process assets
341
Planning > Plan Cost Management > Cost Management Plan What are the tools and techniques for Plan Cost Management?
Tools and techniques: Expert judgement Data Analysis Meetings
342
Planning > Plan Cost Management > What is planning cost management?
Plan that describes how the processes of Estimate costs, determine budget, and controlled costs will be carrier out.
343
What are the 3 types of cost estimates?
Rough order of magnitude estimate Preliminary estimate Definitive estimate
344
What is the range for "rough order of magnitude estimate"?
-25% to +75%
345
What is the preliminary estimate?
-20% to + 30%
346
What is the definitive estimate?
-5% to +10%
347
Planning > Estimate costs > cost estimates, Basis of Estimates, project document updates What are the inputs to estimating cost?
Project management plan Project Documents (lessons learned, Project schedule, resource requirements, risk register) Enterprise factors Org. Process Assets
348
Planning > Estimate costs > cost estimates, Basis of Estimates, project document updates What are the tools and tech for estimating costs?
Expert judgement Analogous estimating Parametric Estimating Bottoms up estimating 3 point estimating Alternative analysis Reserve analysis Cost of quality Project management info system Decision making
349
Planning > Estimate costs > What are the outputs?
cost estimates Basis of Estimates Project document updates
350
What is the basis of Estimates?
Never enough detail Include info on how you derived the activity cost estimates
351
Planning > planning determine budget > cost baseline, Project funding requirements, project document updates What is a budget?
Time phases the cost estimates so that the company will know how to plan for cash flow and expenditures.
352
Planning > planning determine budget > cost baseline, Project funding requirements, project document updates When is a project performed?
Performed after you define activities, estimate activity Durations, estimate activity resources and developed the schedule.
353
Planning > planning determine budget > cost baseline, Project funding requirements, project document updates What are the inputs to a budget?
Project management plan (cost management, resource management plan, scope baseline) Cost management Cost estimate Schedule Project Documents (basis of Estimates, cost estimates. Project schedule, risk register) Business documents (business case and benefits management plan) Agreements Environmental factors Organizational process assets
354
Planning > planning determine budget > cost baseline, Project funding requirements, project document updates What are tools and techniques?
Expert judgement Cost aggregation Data Analysis Historical info Funding limit reconcilliation Financing
355
Planning > planning determine budget > cost baseline, Project funding requirements, project document updates What is cost aggregation?
Cost estimates should be rolled up to the work package level where they will be measured, managed and controlled.
356
Planning > planning determine budget > cost baseline, Project funding requirements, project document updates What is funding limit reconciliation?
Companies can be required to budget for projects in advance. When this happens there can be a funding limit when project has begun.
357
Planning > planning determine budget > What are the outputs when determining a budget?
Cost baseline (budget = cost baseline plus management reserves) Project funding requirements Project Documents updates
358
Planning > monitoring and controlling control costs > work performance, cost forecasts, change requests, Project management plan, project document plans What are two important things to keep in mind about controlling processes?
1) they are proactive - they do not wait for changes to occur. 2) controlling processes measure what was executed against vs what was planned. If the results do not match the cost baseline, then steps are taken to bring them in line.
359
Planning > monitoring and controlling control costs > work performance, cost forecasts, change requests, Project management plan, project document plans What is control costs concerned with?
Cost variance. Good or bad variance need to be understood and the plan needs to be adjusted.
360
Planning > monitoring and controlling control costs > work performance, cost forecasts, change requests, Project management plan, project document plans When do you control costs?
Throughout the project. The greater change something could peak or change the more often you measure/ check
361
Planning > monitoring and controlling control costs > work performance, cost forecasts, change requests, Project management plan, project document plans What are the inputs for controlling costs?
Project management plan Project Documents Project funding requirements Work Performance data Organizational process assets
362
Planning > monitoring and controlling control costs > work performance, cost forecasts, change requests, Project management plan, project document plans What are the tools and tech to control costs?
Expert judgement Data Analysis (Earned Value Analysis: actual performance vs plan, variance analysis, trend analysis, reserve analysis) To-complete performance index Project management info system
363
Planning > monitoring and controlling control costs > work performance, cost forecasts, change requests, Project management plan, project document plans What is To-Complete Performance Index?
Earned Value technique that focuses on the performance needed in order to achieve your targets. based on performance now - can you hit the original budget at completion OR is it more likely to hit your new estimate at completion
364
Planning > monitoring and controlling control costs > What does controlling cost work/output?
Outputs: Work Performance info Cost forecasts Change requests Project management plan updates Project document updates
365
The agile perspective on cost management Thoughts on EVM
Agile favors flexibility vs long term plans and budgets. EVM is powerful tool in predictive but is difficult to apply in agile. To do EVM in agile you would need to define scope, schedule, cost estimates where it would then be barely possible.
366
The agile perspective on cost management Thoughts on plan cost management?
Most agile don't produce a formal cost plan. Agile run burn rates stats which indicate how much the team will cost per month, quarter year or other period.
367
The agile perspective on cost management Thoughts on estimating costs?
Predictive environments measure cost per work package. Agile measures cost per iteration. Hard to be accurate due to changes coming.
368
The agile perspective on cost management Thoughts on determining budget?
More relevant in predictive. Not really able to change much while in middle of iteration.
369
The agile perspective on cost management Thoughts on plan control costs?
Predictive uses EVM to forecast costs and make changes. Agile wants to forecast costs and be transparent just difficult to change cost in middle of iteration.
370
What is Earned Value Management conceptually?
If you spend a dollar you are earning a dollar back into your project.
371
Description and Formula: Budget at Completion (BAC)
How much was originally planned for this project to cost? No formula
372
Description and Formula: Planned Value (PV)
Aka Budgeted Cost of Work Scheduled How much work should have been completed at a point in time based on the plan. PV= planned % complete × BAC (Budgeted at Completion)
373
Description and Formula: Earned Value (EV)
Aka Budgeted Cost of Work Performed How much work was actually completed during a period of time. EV = actual % complete × BAC (Budgeted at Completion)
374
Description and Formula: Actual Cost (AC)
Aka actual cost work performed The money spent during a period. AC = Sum of all costs
375
Description and Formula: Cost Variance (CV)
The difference between what we expected to spend vs what actually was spent CV = EV (Earned Value) - AC (Actual Cost)
376
Description and Formula: Schedule Variance (SV)
The difference between where we planned to be in schedule vs where we are in schedule. SV = Earned Value - Planned Value
377
Description and Formula: Cost performance Index (CPI)
The rate at which the project performance is meeting cost expectations from the beginning up to a point in time. CPI = Earned Value÷Actual cost If it's less than 1 that means we are losing money.
378
Description and Formula: Schedule performance index (SPI)
The rate at which the project performance is meeting schedule expectations up to a point in time. SPI = Earned Value ÷ Present Value
379
Description and Formula: Cost Performance Index (CPI)
The rate at which the project performance is meeting cost expectations from the beginning up to a point in time. CPIC = Earned Value ÷ Actual cost
380
Description and Formula: Estimate at Completion (EAC)
Projecting the total cost at Completion based on project performance up to a point. How much are we going to be at the end of the project based on performance now. EAC= BAC (Budgeted at Completion) ÷ CPIC (Cumulative Cost performance Index)
381
Description and Formula: Estimate to Completion (ETC)
Projecting how much more will be spent on the project based on past performance. how much will we need to complete ETC= EAC (Estimate at Completion) - Actual Cost
382
Description and Formula: Variance at Completion
Difference between what was Budgeted and what will actually be spent. VAC= BAC (Budgeted at Completion) - EAC (Estimate at Completion)
383
Description and Formula: To-Complete Performance Index (TCPIC)
TCPIC = (Budgeted at Completion - Earned Value)÷ remaining funds
384
What is a fixed cost?
Cost that stays the same throughout the project.
385
What is a variable cost?
Hourly labor
386
What is a direct cost?
Expenses billed directly to a project. Example would be materials to construct a building.
387
What is indirect costs?
Costs that are shared and allocated amongst several projects. Example: managers salary.
388
What is a sunk cost?
Costs that have been invested into a project. Example: we spent 10k on this project so we can't turn back now. Sink cost is spilt milk or unrecoverable.
389
What is opportunity cost?
The cost of the loss of potential benefit from alternatives when a choice made excludes it.
390
How do you know if a project is over or under budget? Formula speaking
CPI is less than 1 = over budget VAC is negative = over budget
391
What is the difference between EV and PC and AC?
Earned Value is where you are at in the project Planned Value is where you expected to be at and its cost Actual Cost is what you spent.
392
What is the formula for TCPI if you choose to go with original budget?
TCPI = (BAC - EV/ remaining funds BAC - AC)
393
What is the formula for TCPI if you choose to go with EAC budget?
TCPI = (BAC -EV / remaining funds EAC - AC)
394
IS CPIC CPI or TCPI?
CPIC is another name for CPI
395
What is the philosophy of quality management?
Proactive approach. it costs more to fix an error than it does to prevent them.
396
What does Plan Quality Management, an Control Quality map closely to?
Plan Do Check Act
397
What is the differences between Plan Quality Management, Manage Quality and Control Quality?
Plan quality is how you plan on tackling your project. Manage quality is how you actually do it. Control quality is how you inspect it.
398
What is the definition of quality?
The degree to which a set of inherent characteristics fulfills requirements. AKA a product can be low grade and high quality because that is what the requirement stated or implied.
399
What are the 3 processes for quality management?
Planning = Plan Quality Management [Output = Quality Management Plan; Quality Metrics] Executing = Manage quality [Output = Quality Reports, Test and Evaluation Documents] Monitoring and Controlling = Control Quality [Output = Quality Control Measurements; Verified Deliverables]
400
What is Total Quality Management (TQM)?
Everyone in the company is responsible for quality and is able to make a difference. TQM shifts focus from product that is produced and looks at quality of how it is produced. how something is produced is better than what is produced. Japanese processes
401
What is "Kaizen"?
Kaizen means continuous improvement
402
What is the Continuous Improvement philosophy?
A philosophy that stresses constant process improvement in the form of small changes.
403
What is Just-In-Time (JIT)?
manufacturing method that brings inventory down to zero or (near zero) levels. It forces a focus on quality,m since there is no excess inventory on hand to waste. think of fresh deserts
404
what is ISO 9000?
Ensure companies document what they do and do what they document. Contributes to Manage quality - whats the point of a quality process if nobody does the process.
405
What is statistical Independence?
2 processes that are not linked or dependent upon each other. rolling a dice/roulette
406
What is Mutually Exclusive?
one choice excludes the other. flipping a coin results in heads or tails. if it is heads it excludes tails.
407
What is Standard deviation?
calculated by averaging all data points to get a mean then calculate the differences between each data poiint and the mean square each of hte differences divide the sum of the squared differences by the number of data points minus 1
408
How can standard deviation be used in quality?
1) the higher the standard deviation the more diverse your data points are. 2) Standard deviation can be used to set quailty levels 3) standard deviation can be used to set control limits
409
What is Six Sigma?
popular philosophy of quality management that focuses on achieving very high levels of quality by controlling the process and reducing the defects. strives to make the overwhelming majroity of the bell curve fall consistently within customer quality limi9ts.
410
What is a sigma?
1 standard deviation from the mean. 1 standard deviation should control 68.25% of all outputs will meet quality standards
411
What is the 6 sigma level?
99.99966% of all outputs will meet the quality standards. 3.4 out of every 1,000,000 outputs do not meet quality standards.
412
What is the 6 sigma level?
99.99966% of all outputs will meet the quality standards. 3.4 out of every 1,000,000 outputs do not meet quality standards.
413
What is the goal of Six Sigma?
refine the process so that human error and outside influence no longer influence results and any remaining variations are completely random.
414
What are the error rates of 1 sima, 3 sigma and 6 sigma per million opportunities?
1 sigma = 317,500 defects per million (lowest quality) 3 Sigma = 2,700 defects per milliion (higher quality) 6 sigma = 3.4 defects per million (highest quality)
415
what examples would six sigma not be good enough for?
basically anything with death. pharmaceutical, airline or power utilities.
416
What is the difference between prevention and inspection?
prevention is keeping defects from occuring. inspection is about identifying and catching the errors before they impact others outside of hte project.
417
What does project management favor between prevention and inspection?
prevention
418
Attribute sampling vs variable sampling
Attribute sampling is binary; either a result is quality or is not. variable sampling measures how something conforms to quality. variable is on a continuous scale.
419
Special Causes vs Common Causes
special causes are preventable where as common causes are generally accepted. assembly errors are special causes. quality of materials is common causes
420
Tolerances vs Control Limits
Tolerance is the limit your project has for acceptance. weight between 13 and 15 grams would be your tolerance. Control limit is usually 3 standard deviations above and below a mean. as long as your results fall within the control limits you are in control of your process. tolerance focuses on whether the product is acceptable. control limit focuses on the process itself is acceptable.
421
Customer Satsifaction
does it do the right thing (Whats intended)? Does it do the thing right?
422
What is the management responsibility regarding quality?
project managers job to make sure the focus stays on quality management. however, everyone is responsible for quality.
423
What is the agile approach with quality?
goal is to get the product in the customer's hands as quickly as possible and to adapt constantly. to make this work, agile takes on small tasks (per each iteration) GETS FEEDBACK FROM USERS AND IMPROVES THE PRODUCT. in an agile setting, problems should be detected early and thus cost less and require fewer resources to fix than if it were detected later.
424
Why is planning quality management performed early?
Decisions made about quality directly impact: Scope Time Cost Risk
425
Planning > Quality Management plan > quality management plan and Quality Metrics What are inputs with planning quality management?
Project charter Project Management Plan Requirements Management Plan Risk Management Plan Stakeholder Engagement Plan Scope Baseline Project Documents Enterprise environmental factors Organizational process assets
426
Planning > Quality Management plan > quality management plan and Quality Metrics What are the T&T for Quality Management Plans?
Data representation Test and inspection planning Meetings Expert judgement Data gathering Data Analysis Decision making
427
What is the SIPOC?
Quality management plan for: Supplier Inputs Processes Outputs Customers
428
Quality vs inspection
Quality cannot be inspected in....meaning quality is connected to processes. Inspection is an important part of quality and should be scheduled and planned from start.
429
What is the output to planning quality management plan?
Quality management plan Quality Metrics Project management plan updates Project document updates
430
What is quality metrics?
Objective. Quality Metrics become an input from monitoring and controlling Examples: # of defects, weights, and measures. Hours spent on rework, downtime, customer survey results, response time.
431
What is difference between managing quality and controlling quality?
Manage quality is referred to as quality assurance. It relates to product design and to process improvement. Control quality is the inspection of the product.
432
What are the two primary purposes of managing quality?
1) to put the quality management plan into practice and to see that the product, service or result achieves quality. 2) to improve and streamline the overall process of producing the product, service or result.
433
Why is managing quality important?
If processes are improved then greater efficiency, more quality product and less waste.
434
Agile vs traditional regarding managing quality
Traditional/waterfall = project manager Agile= team is responsible
435
Inputs of managing quality?
Project management plan Project Documents Organizational process assets
436
Tools and tech for managing quality?
Data gathering Data Analysis Decision making Data representation Audits Design for x Problem solving Quality improvement methods
437
What is an affinity diagram?
Example: to solve construction problems..... Get Sticky note cards and use affinity system to categorize the data into four columns and move each note card under one of the cats.
438
What is a fishbone or Ishikawa diagram?
Cause and effect/ why why Identify root causes. Quality problems typically are traced back to their root causes to prevent rather then fix through inspection.
439
What is a histogram?
Bar chart capable of showing multiple views of data. Example: Shows number of defects per month and shows % of defects per each supplier.
440
who performs a quality audit?
Quality audits are usually carried out by an objective person or team and it is best if they are not part of hte project team.
441
What is "Design for X"?
Design for Excellence (DfX) Methodology where design is applied to the top priorities.
442
What are: DfC DfA DfM DfL DfS
DfC = Design for Cost DfA = Design for assembly DfM = Design for Manufacturing DfL = Design for Logisitics DfS = Design for Servicability (prioritize ease of repair and service)
443
How do you approach problem solving in Manage Quality?
Define the problem Root Cause Analysis (Define the problem) Identify Possible Solutions Choose a solution Implement the solution Verify the Solution AKA Plan - Do - Check - Act
444
What are outputs for managing quality?
Quality Reports (quantitative or qualitative) Test and Evaluation Documents Change Requests Project Management Plan Updates Project Document Updates
445
What is "Control Quality"?
Inspected, measured and tested uses statistical sampling rather than inspecting every single item.
446
Monitor and Controlling > Quality Management > Control Quality What are the inputs for controlling quality?
Project Management Plan Project Documents Approved Change Requests Deliverables Work Performance Data Enterprise Environmental Factors Organizational Process Assets
447
Monitor and Controlling > Quality Management > Control Quality What are the Tools and Techniques for Control Quality?
Data Gathering Data Analysis Inspection** Testing and Product Evaluations** Data Representation (such as cause and effect diagram, control chart, histogram, scatter diagram) Control Chart
448
What is a Control Chart?
Upper Control Limit 3 standard deviations Mean 3 standard deviations Lower Control Limit
449
What do you do if a measurement falls outside the control limits?
Process is out of control. cause should be investigated and determined.
450
What is the rule of Seven?
if 7 consecutive data points fall on one sign of the mean they should be investigated.
451
What is output for controlling quality?
quality control measurements verified deliverables that have been inspected and measured to ensure quality Work Performance Information Change Requests Project Management Plan Updates Project Documents Updates
452
What is the Agile Perspective on Quality Management?
Predictive = inspection agile = DoD (definition of done) agile incorporates testing scenarios that incorporate acceptance criteria
453
When is quality controlled in predictive and in agile?
predictive is done in the monitoring and controlling hase > control quality > inspection agile is done in the Iteration H phase (hardening) or by getting the product in the customer's hands quickly.
454
What is the approach to resource management (twofold):
Define and manage the physical resources Define the role and the responsibilities of the team.
455
Relationship between PM and team (related to power)?
PMs are responsible for project - they should delegate power and responsibilities. In return the team provides positive results and accountability
456
Issues with Virutal teams?
Communication and collaboration can be more difficult team building can be harder since you never see each other
457
Inputs, Tools and Techniques and Outputs for Plan Resource Management?
Inputs: Project Charter Project Management Plan Proejct Documents Enterprise Environmental Factors Organizational Process Assets T&T: Expert Judgement Data Representation (Hierarchical Charts, Responsibility Matrix, RACI, Text Oriented) Organizational Theory Outputs: Resource Management Plan Team Charter Project Document Updates
458
R.A.C.I.
Responsibility Assignment Matrix Responsibility Accountable Consult Inform
459
Text Oriented Formats
Basically job position descriptions
460
What is Organizational Theory?
Groups behave differently than individuals
461
What are the 3 main components for Resource Management Plan?
- Identification of Resources - Plan for acquiring resources - Staffing roles and responsibilities
462
What is a resource histogram?
Shows resource usage for a given time.
463
Input, Tools and Tech, Output for Estimating Activity Resources
Inputs: Project Management Plan Project Documents Enterprise Environmental Factors Organizational Process Assets Tools and Technique: Expert Judgment Bottom-Up Estimating Analogous Estimating Parametric Estimating Data Analysis Project Management Information System (PMIS) Meetings Outputs: Resource Requirements Basis of Estimates Resource Breakdown Structure
464
When do you acquire resources?
this process is done usually throughout the project. you may need different skill sets and materials throughout the project.
465
Input Tool And Tech and Output for Acquiring resources
Input: Project Management Plan Project Documents Enterprise Environmental Factors Organizational Process Assets Tools and Techniques: Decision Making Interpersonal Team Skills Pre-Assignment Virtual Teams Outputs: Physical Resource Assignments Project Team Assignments Resource Calendars Change Requests Project Management Plan Updates Project Document Updates Enterprise Environmental Factor Updates Organizational Process Assets Updates
466
Input Tool and Tech and Outputsfor Developing Team
Input: Project Management Plan Project Documents Enterprise Environmental Factors Organizational Process Assets Tools and Techniques: Colocation Virtual Teams Communication Technology (SharePoint or skype) Interpersonal and Team skills Recognition and Rewards Outputs: Team Performance Assessments Change Requests Project Management Plan Updates Project Document updates Enterprise Environmental Factors Updates Organizational Process Assets Updates
467
What is Tuckman's Ladder?
Stages of Team Development Forming Storming Norming Performing Adjourning
468
Forming
the team understands the project and their roles eveyrone first meets each other.
469
Storming
the team begins to do the work but there is conflict and chaos
470
Norming
behavior normalizes and the group functions as a team. PM shares more leadership with the team.
471
Performing
the team is working at an efficient level that exeeds what an individual could accomplish alone. the project manager's role changes to be one of overseeing and delegating.
472
Adjourning
stage where hte project is closed an d the team is released. everyone is sad project is done.
473
What is Maslow's Hierarchy of Needs?
theory of human motivation needs at the bottom (basic survival) must be met before the upper needs can be met (fulfillment and potential met)
474
What is Haslow's Higher Needs?
Self-Actualization (living and working at full potential) Esteem (feeling of importance, recognitions)
475
What is Haslow's Lower Needs?
Acceptance Security Physiological (food clothing sleep)
476
What is expectancy Theory?
Make choices based on the expected outcomes. basically -only work hard if the goal is achievable.
477
What is McGregor's Theory X and Theory Y?
X - unmotivated workers that need micromanagement Y - highly motivated trustworthy people that can work on their own....telecommute
478
Contingency Theory
effectiveness is dependent on two factors: 1) are you a task oriented leader o a relationship - oriented leader 2) how stressful is the environment?
479
What is Herzberg's Motivation-Hygiene Theory?
focuses on the absence of certain factors can lead to unhappy workers. hygiene factors - paycheck allows you to have potential for motivation; recognition is the actual factor.
480
McClellands 3 need theory?
employees are motivated out of theee primary needs achievement power affiliation(feeling of a team)
481
What are the forms of power for a project manager?
Reward Power Expert Power Legitimate Power (formal power) Referent Power (personality or respect) Punishment
482
Input, Tool and Tech and Output for managing teams
Input: Project Management Plan Project Documents Work Performance Reports Team Performance Assessments Enterprise Environmental Factors Organizational Process Assets Tools and Tech: Interpersonal and Team Skills (problem-solving, collaboration, compromise, forcing, smoothing, withdrawal, Decision Making, Emotional Intelligence, Influencing, Leadership, Project Management Information System Outputs: Change Requests Project Management Plan Updates Project Documents Updates Enterprise Environmental Factors Updates
483
What is Forcing vs Confrontation?
Forcing is bringing to bear whatever force or power is necessary to get the door open. Forcing is bad team work. confrontation is problem solving it is tackling the problem head on.
484
What is Smoothing?
AKA Accomodating downplays the problem and talks about what is going well. smoothing basically tries to diminish the problem rather than resolve it.
485
What is "Withdrawal"?
avoidance of the issue
486
What are the Inputs, Technology and tools, and output?
Inputs: Project Management Plan Project Documents Work Performance Data Agreements Organizational Process Assets Tools and Tech: Data Analysis Problem Solving (Identify, Define, Investigate, Analyze, Solve, Check) Interpersonal and Team Skills Project Management Information System (PMIS) Outputs: Work Performance Information Change Requests Project Management Plan Updates Project Document Updates
487
What are the steps (formally) to problem solving? 6 steps
IDENTIFY - Isolate the problem DEFINE - Understand the problem INVESTIGATE - Get more information ANALYZE - Determine the root cause SOLVE - Find the best solution CHECK - Verify the results
488
AGILE on Resource Management
- Agile projects have the team responsible for quality and deliverables - physical resources procured in smaller quantities to satisfy a single iteration - could increase cost but definitely reduces risk - agile don't really rely on plan resource management they refer to the team charter - agile doesn't estimate activity resources they gauge the level of difficulty for user stories - as far as resources go agile teams are made up of generalists rather than specialists - developing a team is highly applicable to agile. Agile is to seek performacne throughout the life of a project - - agile teams are self organiz9zing and self managing. the role of a mentor is to coach not manage.
489
What is a "Dropped Baton"?
Work is handed from 1 group to the next when one team finishes early but the other team cannot start that is a dropped baton.
490
What is a "Student Syndrome"?
Planned procrastination. A student will only start to apply themselves to an assignment at the last possible moment.
491
What is Parkinsons Law?
Work expands so as to fill the time available for it's completion. A task will take as long as you are given. Zero refill report could take 1 hour or 8 hours .
492
What is Self Protection?
People protecting themselves in task or conflict. Saying or doing things that cannot hurt you in the future. Very calculated.
493
What is Sandbagging?
Under promising; over delivery they set low expectations so they can over deliver. Eric Barber with radio sales.
494
What does a communication management plan include? (3 processes)
Plan Communications Management Monitor Communications Manage Communications follows the same mindset of Plan, Execute, and Control
495
What is the project manager's most important job or skillset?
Communication. An effective project manager spends about 90% of his time communicating, and fully 50% of the time is spent communicating with the project team.
496
Planning > Plan Communications Management > Communications Management plan, Project Management Plan Updates, Project Document Updates What does the communication management plan define?
How often communications will be distributed and updated? In what format the communications will be distributed (e.g., e-mail, meetings, printed copy, web site, etc.) What information will be included in the communications. Which project stakeholders will receive these communications.
497
Planning > Plan Communications Management > Communications Management plan, Project Management Plan Updates, Project Document Updates Why is the communications management plan important?
Sets stakeholders' expectations on the project. Let's the stakeholder know what they will receive, when they will receive it and how they will receive it.
498
Planning > Plan Communications Management > Communications Management plan, Project Management Plan Updates, Project Document Updates What is the input for a communication management plan?
Project charter Project management plan Project documents Enterprise Environmental Factors Organizational process assets
499
Planning > Plan Communications Management > Communications Management plan, Project Management Plan Updates, Project Document Updates What is the tool and technology for communication management plan?
-Expert Judgement -Communication Requirements Analysis (identify which stakeholders, what comms they should receive, how they should receive these comms, how often they should receive them) -Communication technology -Communication Models - Communication Methods - Interpersonal and Team Skills - Data representation - Meetings
500
Planning > Plan Communications Management What is the outputs for a communication management plan?
Communications Management plan Project Management Plan Updates Project Document Updates
501
What is the formula for communication channels?
amount of channels = n x (n-1)/2 n is hte amount of people
502
Planning > Plan Communications Management > Communications Management plan, Project Management Plan Updates, Project Document Updates What is a communication model?
a formal way of understanding how messages are sent and received. Sender Message Receiver
503
Planning > Plan Communications Management > Communications Management plan, Project Management Plan Updates, Project Document Updates What is the sender's responsibilities?
- Encode the message clearly (create the message) - select a communication method (email) - send the message (hit send) - Confirm the message was received and understood
504
Planning > Plan Communications Management > Communications Management plan, Project Management Plan Updates, Project Document Updates What is the receiver's responsibilities?
- Decode the message - Acknowledge (confirm that the message was received) - Respond and give feedback
505
What is active listening?
requires the receiver to take steps to ensure that the message was understood. very similiar to effective listening.
506
What is effective listening?
monitor non-verbal and physicals communications and to provide feedback when understood.
507
What is Feedback?
verbal and nonverbal cues a speaker must monitor to see whether the listener fully comprehends the message. Nodding and smiling might be considered positive feedback and indicate the message was understood. asking questions or repeating the speaker's words are feedback.
508
What is "Paralingual"?
vocal but not verbal....tone of voice, volume or pitch.
509
example of a informal written communication?
email messages
510
example of formal written communication?
Contract Project Documents Legal notices
511
example of informal oral?
phone calls conversations
512
example of formal oral?
meetings, speaches, presentations
513
example of internal communication?
emails to team presentations to senior management
514
example of external communication?
messages to customers messages to investors
515
What is an interactive type of communication?
a meeting where people can ask questions
516
What is a push type of communication?
A bulk email blast
517
What is a pull type of communication?
A website where a video presentation or white paper can be downloaded
518
Executing> Manage Communications > Project Communications, Project Management Plan Updates, Project Document Updates, Organizational Process Assets Updates What are the four statements in regards to the approach of managing communications?
1) Always deal with the problem. 2) Always communicate directly 3) Always tell the truth 4) Always distribute accurate information
519
Executing> Manage Communications > Project Communications, Project Management Plan Updates, Project Document Updates, Organizational Process Assets Updates What are the inputs of managing communications?
Project Management Plan Project dDocuments Work Performance Reports Etnerprise Environmetnal Facotrs Organizational Process Assets
520
Executing> Manage Communications > Project Communications, Project Management Plan Updates, Project Document Updates, Organizational Process Assets Updates What are the Tools and Technology of managing communications?
Communication technology Communication Methods Communication Skills Project Management Information System Project Reporting Interpersonal and Team Skills Meetings
521
Executing> Manage Communications > Project Communications, Project Management Plan Updates, Project Document Updates, Organizational Process Assets Updates What are the Tools and Technology of managing communications?
Communication technology Communication Methods Communication Skills Project Management Information System Project Reporting Interpersonal and Team Skills Meetings
522
Executing> Manage Communications > What are the outputs for managing communications?
Project Communications Project Management Plan Updates Project Document Updates Organizational Process Assets Updates
523
Monitoring and Controlling > Monitor Communications > Work Performance Information, Change Requests, Project Management Plan Updates, project document updates What are the inputs?
Project Managment Plan Project Documents Work Performance Data Enterprise Environmental Factors Organizaitonal Process Assets
524
Monitoring and Controlling > Monitor Communications > Work Performance Information, Change Requests, Project Management Plan Updates, project document updates What are the Tools s and technology?
Expert Judgment Project Management Information System ***Data Representation [ Stakeholder Engagement Process ] ***Interpersonal and Team Skills [ Manage By Walking Around....AKA Stay Engaged] Meetings [ lessons learned meeting]
525
The Agile Perspective on Communication Management
- Agile = more open and dynamic communication - Osmotic communication due to being collocated and constantly learni9ng from each other. - Product owner is embedded on the team so effective and efficient communication. - Agile is rapid communication - no barriers all transparent communication. - Information about performance, value delivery and priorities are visible 24/7 on a big board. - communication plan is not important due to reliance on informal communications
526
What are agile examples of communication?
daily stand up meetings retrospectives Visible information (burndown charts, burn up charts, kanban boards and product backlogs)
527
What are the 3 characteristics of "Risk"?
1) Risk is related to an uncertain event. 2) Risk can be negative OR positive. 3) There is a difference between individual project risk and overall project risk. individual project risk = threat to objective. overall project risk = threat to project.
528
What factors do you consider when approaching risk?
Size of project Project Complexity Inherent Project Risk Project Methodology Importance
529
What are the six risk processes?
Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses Implement Risk Responses Monitor Risks Plan Do Check Act
530
Planning > Plan Risk Management > Risk Management Plan What are the inputs?
Project Charter Project Management Plan Project Documents Enterprise Environmental Factors Organizational Process Assets
531
Planning > Plan Risk Management > Risk Management Plan What are the tools and technology for building a risk management plan?
Expert Judgment Data Analysis Meetings
532
Planning > Plan Risk Management What is the output?
you create the risk management plan. Risk management plan level of risk, managed risk, who is responsible of risk activities, the amount of time and resource per each risk, an how risk findings will be communicated.
533
What is a tool used for creeating risk categories?
RBS Risk Breakdown Structure
534
Planning > Identify Risks > Risk Register What are the inputs for identifying risks?
Inputs: - project management plan - Project Documents Agreements (contracts) - Procurement Documentation Enterprise Environmental FActors Organizational Process Assets
535
Planning > Identify Risks > Risk Register What are the tools and techniques used for identifying risks?
Expert Judgment Data Gathering Data Analysis Prompt Lists
536
Planning > Identify Risks > Risk Register What are the methods of data gathering for identfying risks?
Brainstorming Checklists are the right risks that are identified.
537
Planning > Identify Risks > Risk Register What are the methods of data analysis for identifying risks?
- Root Cause Analysis (aka fishbone or ishikawa diagram) ASK "WHY" Five Times > gets to root cause - Assumptions and Constraint Analysis (what are the "relaxed" CONSTRAINTS? IS THE ASSUMPTION INCORRECT?) - SWOT analysis (Strength, weaknesses, opportunities, threats) -Document Analysis
538
Planning > Identify Risks > Risk Register What is a prompt list?
a prompt list is a framework of questions/ categories that are used to help identify risks. PESTLE framework would be political, economic, social, technological, legal and environmental
539
Planning > Identify Risks > Risk Register What is the output for identifying risks?
Risk Register risk register contains the identified risks, the potential risk owners, and a list of potential responses to those risks.
540
Planning > Qualitative Risk Analysis > Project Document Updates What is "Qualitative Risk Analysis"?
Qualitative for a project is about probability of impact and prioritization/ranking.
541
Planning > Qualitative Risk Analysis > Project Document Updates What are the inputs to qualitative risk analysis?
Inputs: Project Management Plan Project Documents Enterprise Environmental Factors Organizational Process Assets
542
Planning > Qualitative Risk Analysis > Project Document Updates What are the tools and techniques to Qualitative risk analysis?
Expert Judgment Data Gathering Data Analysis Interpersonal and Team Skills Risk Categorization
543
Planning > Qualitative Risk Analysis > Project Document Updates What is the data analysis done for qualitative risk analysis?
Risk Data Quality Assessment (garbage in; garbage out. make sure the data is high quality) Risk Probability and Impact Assessment/ Probability and Impact Matrix Assessment of Other Risk Parameters
544
Planning > Qualitative Risk Analysis > Project Document Updates What is a probability and impact assessment/ matrix (PIM)?
each risk in the risk register is evaluated for likelihood of occurring and potential impact on the project. assign values like low, medium, high or 1-10....then multiple each other to determine a value and then rank.
545
Planning > Qualitative Risk Analysis > Project Document Updates What is Propinquity?
Propinquity is the measure of how important the project's stakeholders perceive this risk to be. Lower propinquity is more desirable.
546
Planning > Perform Quantitative risk analysis > Risk Report What is the difference between qualitative and quantitative risk assessment?
qualitative is about ranking or prioritizing quantitative is about how long or how much it would cost
547
Planning > Perform Quantitative risk analysis > Risk Report Inputs to quantitative risk analysis?
project management plan project documents Enterprise Environmental Factors Organizational Process Assets
548
Planning > Perform Quantitative risk analysis > Risk Report What are the tools and techniques?
Expert Judgement Data Gathering Interpersonal and Team Skills Representations of Uncertainty Data Analysis (monte carlo analysis, sensitivity analysis, decision tree analysis and influence diagram)
549
Planning > Perform Quantitative risk analysis > Risk Report What is the representation of Uncertainty?
likelihood of risk occurrence. Beta distribution is uneven where most of risk happens in beginning of project. Triangular distribution is like a triangle - most of risk happens in middle of project.
550
Planning > Perform Quantitative risk analysis > Risk Report What is "Monte Carlo Analysis"?
a computer simulation to help determine quantitative risk analysis - provides what if scenarios to determine potential costs and delays.
551
Planning > Perform Quantitative risk analysis > Risk Report what is a sensitivity analysis or tornado diagram?
shows how risk effects other factors.
552
Planning > Perform Quantitative risk analysis > Risk Report What is a decision tree analysis?
used to determine if you should buy or build type of analysis. factors in risk and associated revenue.
553
What is the Escalate negative risk strategy?
Escalate is when you hand it off to your boss last resort - it is when something is an issue without your authority.
554
What is the Avoid negative risk strategy?
You avoid something is really finding an alternative solution.
555
What is the Transfer negative risk strategy?
Transfer would be hiring a legal consultant. The policy is no longer in your company's problem its another compnay's problem.
556
What is the Mitigate negative risk strategy?
attempt at making a risk "less" to mitigate the heat we will build in the morning. Does not elimintate the heat it could still be hot but greater chance it is less hot.
557
What is the Acceptance negative risk strategy?
if the consequences aren't that bad....if its not too expensive or too long of a delay. you accept risk if you cannot escalate, avoid, transfer or mitigate the risk.
558
What is passive acceptance?
no proactive steps.
559
What is active acceptance?
setting aside a contingency reserve in case the risk event occurs.
560
What is a contingency plan?
where the project team may decide to mitigate a risk upon certain conditions.
561
What is the overall strategy for project risk?
The point is to establish your posture toward risk, understand and analyze the risk and to plan appropriate action. Identify Analyze/Understand Plan Act Monitor
562
What is an Alternatives Analysis?
look to see if there is something else you can use or do instead of the risk.
563
What is Cost-Benefit Analysis?
check to see if the response does not cost more than the risk.
564
What is the difference between work performance data and work performance reports?
Work performance data is what was done. Work performance reports focus on what was done vs the baseline.
565
What are the two types of Data Analysis for monitoring risk?
Technical Performance Analysis (compares the results with the plan) Reserve Analysis (ensure enough reserves are there for cost and schedule)
566
AGILE on Risk Management
- less risk planning/ more of a rapid risk response - uncertainty can change backlog priority (focus on bigger risk - may eliminate smaller features) - Agile has built in risk plan through small incremental changes.
567
What is a buyer?
the purchasing party
568
What is a seller?
The vendor
569
Fixed Price Contract Who bears the risk? Explain
The seller has the risk. Fixed price means the seller has a cap in revenue. any cost overrun is on the seller.
570
Cost Plus Fixed Fee Who bears the risk? Explain
The buyer has the risk. Seller gets the cost of the materials (mulch) PLUS a flat fee. that means the buyer is responsible for all unused inventory.
571
Cost Plus Incentive Fee Who bears the risk? Explain
The buyer AND the seller faces the risk. Buyer faces the burden of cost. The seller faces risk of losing incentive if the costs are high or takes too long.
572
Time and Materials Who bears the risk? Explain
The buyer has the risk. the buyer is paying for all the materials and runs risk of paying more if the employees take too long. the employees don't have an incentive to work faster since faster work equals less pay.
573
What is the best practice for buying externally vs building internally?
If all things are equal (including cost) it is better to buy external.
574
Planning > Plan Procurement Management > Procurement Management Plan, Procurement Strategy, Bid Documents What are the inputs for planning a procurement management plan?
Project Charter Business Documents Project Management Plan Project Documents Enterprise Environmental Factors Organizational Process Assets
575
Planning > Plan Procurement Management > Procurement Management Plan, Procurement Strategy, Bid Documents What are the tools and techniques?
Expert Judgment Data Gathering Data Analysis (make or buy analysis) Source Selection Analysis (how you choose a seller) Meetings
576
Planning > Plan Procurement Management > Procurement Management Plan, Procurement Strategy, Bid Documents How do you choose a seller?
Focus on: - Least Cost (if quality doesn't matter) - Qualifications Only (I need it to be small an black) - Quality-Based (technical score). Usually a compromise is had between cost and quality. - Quality and Cost-Based Ranking (rank the highest of the two) - Sole Source (a buyer negotiates with only one vendor) - Fixed Budget (tell a cake designer I've got $2,000 to spend...what can you give me)
577
Planning > Plan Procurement Management > What are the outputs to Procurement Management Plan?
Procurement Management Plan Procurement Strategy Bid Documents Procurement Statement of work Source Selection Criteria Make or Buy Decisions Independent Cost Estimates Change Requests Project Document Updates Organizational Process Assets Updates
578
What is a Procurement Statement of Work?
Explains a section of the scope to potential sellers in enough detail to decide if they want (or if they can.....qualifications) to do the work in question.
579
Executing > Conduct Procurements > Selected Sellers, Agreements, Change Requests, etc. What does it mean to procurement?
issue the bid package to potential sellers - hold bidder confrences - evaluate proposals you receive -select your seller (in the form of a contract)
580
Executing > Conduct Procurements > Selected Sellers, Agreements, Change Requests, etc. What are the inputs?
Project Management Plan Project Documents Procurement Documentation Seller Proposals**** Enterprise Environmental Factors Organizational Process Assets
581
Executing > Conduct Procurements > Selected Sellers, Agreements, Change Requests, etc. What are the tools?
**Advertising the bid ** bidder conferences Data Analysis Interpersonal and Team Skills
582
Executing > Conduct Procurements > Selected Sellers, Agreements, Change Requests, etc. What are the outputs?
Selected Sellers**** request for proposal was generated, sellers have submitted and negotiations taken place. Agreements****Contracts
583
Monitoring and Controlling > Control Procurements > Closed Procurements, Work Performance Information In a nutshell, what questions does control procurement ask?
Are the goods or services being delivered? Are the goods or services being delivered on time? Are the right amounts being invoiced or paid? Are additional conditions of the contract being met? Is the buyer/seller relationship being properly managed and maintained?
584
Monitoring and Controlling > Control Procurements > Closed Procurements, Work Performance Information What are the inputs?
Project Management Plan Project Documents Agreements(contracts) Procurement Documeentation Approved Change Requests Work Performance Data Enterprise Environmental Factors Organizational Process Assets
585
Monitoring and Controlling > Control Procurements > Closed Procurements, Work Performance Information What are the tools and techniques?
Expert Judgment Claims Administration (disagreements) Data Analysis (Earned Value Analysis) Inspection (product itself) Audits of process
586
Monitoring and Controlling > Control Procurements > Closed Procurements, Work Performance Information Claims Administration is what?
disagreements with a vendor about the scope, impact of a change or interprateation of hte contract. DISPUTES MUST BE MANAGED AND RESOLVED. A Claim Process should be defined in advance.
587
Monitoring and Controlling > Control Procurements > What are the outputs?
Closed Procurements Work Performance Information Procurement Documentation Updates Change Reequests Project Managmeent Plan Updates Project Document Updates Organizational Process Assets Updates
588
Agile Perspective on Procurement Management...
Agile projects like vendors....collaboration. Collaboration over negotiations Agile doesn't plan procurement management-favor creative and adaptive solutions. Predictive Agile would involve the team evaluating bids, select a seller and award a contract. Agile projects may involve the team selecting a seller and possibly even add them to the team. Agile projects under a contract with a vendor or customer will review performances during the control stage.
589
What is "Stakeholder Management"?
Focuses on identifying the relevant stakeholders, creating a plan, executing that plan, and monitoring and controlling. *Manage the expectations that drive stakeholder satisfaction*
590
Initiating > Identify Stakeholders > Stakeholder Register What are the ITTos?
Inputs: Project Charter Business Documents Project Management Plan Project Documents Agreements Enterprise Environmental FActors Organizational Process Assets T&T: Expert Judgment Data Gathering (brainstorming, surveys, questionaires) Data Analysis Data Representation Meetings Outputs: Stakeholder Register Change Requests Project Management plan Updates Project Document Updates
591
Initiating > Identify Stakeholders > Stakeholder Register What are the three main sections of a stakeholder register?
1) Stakeholder identification (names, titles and roles) 2) Stakeholder assessment (their needs are and when those needs are expected to arise in the life of the project. ) 3) Stakeholder classification (grouping of stakeholder)
592
Planning > Plan Stakeholder Engagement > Stakeholder Engagement Plan What are the ITTOs?
Inputs: Project Charter Project Management Plan Project Documents Agreements (contracts) Enterprise Enbironmental FActors Organizational ZProcess Assets Tools and Techniques: Expert Judgment Data Gathering Data Analysis Decision Making Data Representation Meetings Outputs: Stakeholder Engagement Plan
593
Initiating > Identify Stakeholders > Stakeholder Register What is the purpose of the Stakeholder Engagement Assessment Matrix?
The purpose of this is to chart the current and desired states of project stakeholders which will inform the stakeholder engagement plan.
594
Executing> Manage Stakeholder Engagement > Change Requests, Project Man. Plan Updates, Project Document Updates What are the ITTOs?
Inputs: Project Management Plan Project Documents Enterprise Environmental FActors Organizational Process Assets T&T: Expert Judgment Communication Skills (FEEDBACK) Interpersonal and Team Skills (soft skills) Ground Rules (apply to stakeholders and team) Meetings Outputs: Change Requests Project Management Plan Updates Project Documents Updates
595
Monitoring and Controlling > Monitor Stakeholder Engagement > Work Performance, Change Requests, Project Management Plan Updates, Project Documents Updates What are the ITTOs?
Input: Proj. Management Plan Project Documents Work Performance Data Enterprise Environmental Factors Organizational Process Assets T&T: Data Analysis Decision Making Data Representation Communication Skills Interpersonal and Team Skills (active listening) Meetings Outputs: Work Performance Information Change Requests Project Management Plan Updates Project Document Updates
596
Agile Perspective on Stakeholder Management...
Agile approach to stakeholder management is different than the waterfall approach. Stakeholders are actively engaged and even part of the team. Public places have progress and team performance to keep stakeholders up to date and well informed. Agile and predictive identify stakeholders....stakeho9lder register is important!!!!! agile stakehoolders receive transparent communication. Issues or issue log is visible to the team and all stakeholders.