AGILE:
In an agile project if you have a team member unable to complete the tasks….what should you do?
Remove a few items from the sprint after checking in with the product owner.
AGILE:
Who determines the length of the sprint in an Agile setting?
The product owner determines the spring duration.
AGILE:
What type of analysis is identifying risks?
Qualitative analysis
if you were analyzing risks then you would want to quantify that in a quantitative analysis
TRADITIONAL:
What should a project manager do if a senior executive is not responding to communications?
Identify a direct solution.
Use whatever networking or communication method you can to contact the senior executive to get a response.
HYBRID:
What should a project manager do if team members are frustrated and leaving?
Develop a new social contract to empower the team.
a social contract paves the way for everyone in the team to work together better.
TRADITIONAL:
What is the ultimate goal for negotiation?
Achieve a win-win outcome
HYBRID:
What should a project manager do to ensure proper training?
conduct individual and team assessments on their preferred learning methods.
This helps project manager interact with the team and can provide an understanding amongst team members and facilitate a more productive team.
HYBRID:
What should you do if you have to plan against another project?
Develop a schedule based on the info available from the program management team.
program managers are over the project managers so they have access to both sets of info and can help make sure they don’t overstep.
HYBRID:
What should you do first when you have two team members conflicting each other?
Observe the team members first and talk wit them about their complaints before applying a conflict resolution technique.
PMP Mindset:
Plan Do Check ACT
HYBRID:
How do you help resolve virtual communication issues?
Use a myriad of tools to facilitate working with virtual and remote teams.
A fishbowl window alleviates lag by providing a long-lived video link that remains open.
HYBRID:
What does a PM do if you have team members wanting to do new tasks but you don’t want to accept new risks?
compromise/ reconcile.
keep your current process but consider implementing the improvements in future projects.
HYBRID:
If a PM team has been using predictive and wants to start using some agile initiatives, what should the PM do first?
Invite key stakeholders to the daily stand-ups and project review meetings.
this allows you to build awareness within the organization that you are now doing agile things.
PMP Mindset - cannot act before all is informed.
HYBRID:
What should you do if there is an government regulatory requirement that might impact your project?
Confirm that the project is in compliance.
IF NOT - then update the risk registry and project management plan
HYBRID:
What does a PM do to accelerate their project if both the SPI and CPI are under 1.0 (over budget off schedule)?
Adjust the procedure to be more efficient
rearrange the schedule to product crash (efficiency)
anything you can do to increase the efficiency.
HYBRID:
How does a PM ensure that virtual team meetings are effective?
Don’t focus on the agenda.
Instead, focus on the communication method/ time/ schedule to make the meeting. The team will handle the agenda your job is to handle the participation.
AGILE:
What should a PM do if the team spent way too long on an item?
Incorporate an adaptive approach for the rest of the project.
Agile = adaptive approach
Traditional= predictive approach
AGILE:
When it comes to validation, what should a PM try to incorporate?
Develop a type of testing (unit and/or integration testing)
Identify acceptance criteria….you are need to know what results are passing when you test.
HYBRID:
What should a PM do if a project is behind schedule?
Try to either add resources to get it back on track (more hours) [crashing]
Try to run multiple activities at the same time as long as it doesn’t impact each other. [fast tracking]
HYBRID:
What should a PM do if a project conflicts with a contract?
outside contracts are not in the scope of the project - continue with your project activities but bring it up to your legal contract department.
AGILE:
How can a project manager improve team performance?
Analyze the team to see strengths and weaknesses.
You can utilize active listening to address the needs of the team.
HYBRID:
What should a PM do if there is conflict in a diverse team?
Analyze the team to see what the issues could be. Scheduling a team meeting to understand the conflicts.
PM Mindset:
Plan/Analyze/Understand
think before you act.
AGILE:
When switching from a predictive to an agile approach, how do you ensure features/ product is being made?
Align the benefits management plan with the product backlog.
In order to ensure a feature is being made when switching from a predictive to an agile approach, the relevant user stories need to be planned and prioritized in the product backlog. In this case, the project manager should make sure that a measurement system is in place to track the benefits, so the benefits measurement plan should be planned in alignment with the product backlog.
HYBRID:
What should a PM do if a product has been delivered but continue to get contacted by users - even if the project is closed?
After a project has been closed, it gets transferred from the the PM team to the operations team.
Once QuickMAR goes live - Rachel Rice steps out and is between pharmacy and QuickMAR support.
HYBRID:
If you take over a project team and you notice morale is low - what should you first do?
Assess/Understand/Identify any issues.
Identify the cause of the morale issue.