Practitioner 2- Flashcards
The record company’s finance director has asked the executive to ensure that work
packages agreed with team managers are signed off by the project board before the team
starts the work.
Is this an appropriate application of the ‘manage by stages’ principle?
A. Yes, because the executive should ensure that the business investment provides value
for money
B. Yes, because the project should be divided into at least two management stages
C. No, because the finance director should sign off work packages within a stage
D. No, because the project manager should have authority to manage the project on a dayto-day basis
1.1.1d A. Incorrect. Although it is true that the executive needs to
ensure that business investment provides value for money, it
is not appropriate for work packages agreed with team
managers to be signed off by the project board. It is not
appropriate because it conflicts with the ‘manage by stages’
principle as the project manager should have delegated
responsibility to manage the day-to-day delivery of the
stages. Ref 3.4
B. Incorrect. Although it is true that the project should be
divided into at least two management stages, it is not
appropriate for work packages agreed with team managers
to be signed off by the project board. Ref 3.4
C. Incorrect. It is not appropriate for work packages agreed
with team managers to be signed off by the project board.
This conflicts with the ‘manage by stages’ principle as the
project manager should have delegated responsibility to
manage the day-to-day delivery of the stages. Ref 3.4
D. Correct. The ‘manage by stages’ principle requires that
the project board delegates the authority for day-to-day
control of a management stage, within agreed
tolerances, to the project manager. Requiring the project
board to sign off work packages before the project board
starts work breaches this principle. Ref 3.4
At the end of stage 2, the risk that production costs could exceed the sales for the music
album is estimated to be high, as all of the cost tolerance for stage 2 has been used. As a
result, the project manager has defined tight cost and time tolerances for the work packages
to produce the ‘artwork’ and record the album during stage 3.
Which principle is being applied, and why?
A. ‘Manage by exception’, because the level of control retained by the project manager
must match the tolerance available
B. ‘Manage by exception’, because action should be taken so that production costs do not
exceed the album sales
C. ‘Manage by stages’, because cost tolerance should be set for each work package in a
stage
D. ‘Manage by stages’, because team managers should be given authority before work can
commence
A 1.1.1e A. Correct. Applying the ‘manage by exception’ principle
enables appropriate governance by defining distinct
responsibilities for directing, managing and delivering
the project and clearly defining accountability at each
level. This is achieved by delegating authority from one
management level to the next by setting tolerances for
the respective level of the plan. Ref 3.5
B. Incorrect. It is true that action needs to be taken so that the
production costs do not exceed the album sales. However,
this does not explain why the principle being applied is
‘manage by exception’. Ref 3.5
C. Incorrect. While it is true that cost tolerance should be set
for each work package in a stage, this is an application of the
‘manage by exception’ principle, not the ‘manage by stages’
principle. Ref 3.5, 3.4
D. Incorrect. The ‘manage by stages’ principle ensures that
key decisions are made prior to the detailed work needed to
implement them. However, this relates to decisions by the
project board and not the authorization of work packages by
the project manager. Ref 3.5
The Graphic Designer appointed by the external agency is the team manager responsible for
creation of the ‘artwork’. Before assigning a work package to the Graphic Designer, the
project manager ensured that the ‘artwork’ product description attached to the work
package had measurable and prioritized features defined in it.
Is this an appropriate application of the ‘focus on products’ principle, and why?
A. Yes, because it reduces disputes during handover, by agreeing what will be delivered
B. Yes, because the ‘artwork’ is a specialist product and the team members are responsible
for its delivery
C. No, because as an external party, the graphics designer should not access the
product description
D. No, because the ‘artwork’ product description is a management product, and not a
specialist product
A 1.1.1f A. Correct. Applying the ‘focus on products’ principle
helps a PRINCE2 project to be more product/outputoriented rather than work-oriented. An output-oriented
project is one that agrees and defines the project’s
products prior to undertaking the activities required to
produce them, thus reducing the risk of user
dissatisfaction and acceptance disputes. Ref 3.6
B. Incorrect. It is true that the team is responsible for the
delivery of the product(s). However, this does not explain why
the action described follows the ‘focus on products’ principle.
The product(s) should be defined in the work package to
ensure that only the work that directly contributes to the
delivery of the desired product is carried out. Ref 3.6
C. Incorrect. It is an appropriate application of the ‘focus on
products’ principle. Also, external team managers/members
should be able to access the description documents of the
products they are creating or modifying. Ref 3.6
D. Incorrect. It is true that the product description is a
management product, not a specialist product. However, this
does not explain why the action described follows the ‘focus
on products’ principle. Ref 3.6
The Music Album Project team has identified that another department within the company is
producing a similar album of the same type of music. As it is only a small company, it cannot
resource two similar album projects.
Which principle should have been applied more effectively to avoid this situation, and why?
A. ‘Defined roles and responsibilities’, because cross-functional projects involve people
from different departments
B. ‘Defined roles and responsibilities’, because a project management team structure
enables effective communication between team members
C. ‘Continued business justification’, because linking projects to the organizational
objectives ensures benefits are aligned to strategy
D. ‘Continued business justification’, because the justification for projects should be
reviewed regularly throughout the project lifecycle
A. Incorrect. It is true that a project is typically crossfunctional, may involve more than one organization, and may
involve a mix of full-time and part-time resources. However, it
is the ‘continued business justification’ principle that ensures
alignment with corporate strategies. Ref 3.1, 3.3
B. Incorrect. It is true that to be successful, projects must
have an explicit project management team structure
consisting of defined and agreed roles and responsibilities for
the people involved in the project and a means for effective
communication between them. However, it is the ‘continued
business justification’ principle that ensures alignment with
corporate strategies. Ref 3.1, 3.3
C. Correct. Organizations that lack rigour in business
justification may find that projects proceed even where
there are few real benefits or where a project has only
tentative associations with corporate, programme or
customer strategy. Poor alignment with corporate,
programme or customer strategies can also result in
organizations having a portfolio of projects that have
mutually inconsistent or duplicated objectives. Ref 3.1
D. Incorrect. The ‘continued business justification’ principle
requires for all projects that the justification remains valid,
and is re-validated, throughout the life of the project.
However, this does not explain why this principle could have
assisted in avoiding a duplicate project being started. Ref 3.1
It was found that one of the songs approved for the album had quality issues even though a
quality inspection was carried out. It was therefore decided that a further objective check of
recording quality should be conducted by the studio for the songs that are yet to be
approved.
Is this an appropriate application of the ‘learn from experience’ principle, and why?
A. Yes, because lessons should be learnt and applied during a project
B. Yes, because an objective check should accompany a quality inspection
C. No, because lessons should be learnt at the beginning of a project
D. No, because lessons are passed on at the end of a project
A. Correct. In this situation, the project team are learning
from an experience within the project. Lessons should be
sought and learning applied throughout the project
lifecycle, as well as being sought and passed on at the
beginning and closure of a project. Ref 3.2
B. Incorrect. It is not always necessary to carry out checks
additional to a quality inspection. However, in this situation,
the project team have learnt, during the project, that this is
necessary. Ref 3.2, 8.3.13
C. Incorrect. Lessons are looked for, recorded and acted upon
throughout the life of the project, not just at the beginning of
a project. Ref 3.2
D. Incorrect. Lessons are looked for, recorded and acted upon
throughout the life of the project, not just at the closure of a
project. Ref 3.2
The project’s products are being delivered by both external suppliers and record company
staff. A member of the recording studio staff has been appointed as a senior supplier on the
project board. It has also been decided that the Vice President of the record company, who
is the executive for the project, will also be a senior supplier, representing the record
company.
Is this an appropriate application of the ‘defined roles and responsibilities’ principle, and
why?
A. Yes, because the Vice President should be able to represent both the business and
supplier interests
B. Yes, because the Vice President is responsible for achieving the expected sales from the
music album
C. No, because there should be one senior supplier representing the supplier interests on
the project board
D. No, because the executive role cannot be shared and therefore cannot also act as the
senior supplier
A. Correct. One person can carry out more than one role,
as long as that person has the capacity to undertake the
combined responsibilities and there is no conflict of
interest. In this situation it may be necessary to have two
or more senior suppliers to represent different supplier
stakeholders. The Vice President can carry out the role of
executive and represent the record company, which is
supplying some of the products itself. Ref 7.2.1.10, 7.2.1.4
B. Incorrect. It is an appropriate application of ‘defined roles
and responsibilities’ principle that one person can carry out
more than one role, as long as that person has the capacity to
undertake the combined responsibilities and there is no
conflict of interest. However, the senior user, not the senior
supplier, should represent the user interest and ensure that
the expected benefits (derived from the project’s outcomes)
are realized. Ref 3.3, tab 6.1
C. Incorrect. It is an appropriate application of ‘defined roles
and responsibilities’ principle. There can be more than one
senior supplier on the project board. Ref 3.3
D. Incorrect. It is an appropriate application of ‘defined roles
and responsibilities’ principle. The executive role cannot be
shared between two or more individuals, however the
executive can carry out another role in addition. The Vice
President of the record company supervises the production
of the album and can act as senior supplier to represent the
record company. Ref 3.3
The project manager has been recruited from a large, multi-national record company. To
reduce the time spent on the initiation stage, the project manager decided to use PRINCE2
management approaches from projects at the previous company.
Is this appropriate, and why?
A. Yes, because the project manager is learning from experience on previous projects
B. Yes, because the project manager is improving business justification by reducing costs
C. No, because the previous company’s project management approaches are unlikely to
meet the needs of the project
D. No, because the project should focus on specialist products rather than project
management approaches
A. Incorrect. The project manager may be learning from
experience, but is not using that experience appropriately.
Without tailoring to suit the project, it is unlikely that the
project management effort and approach would be
appropriate for the needs of the project. Ref 3.7
B. Incorrect. Cost may be reduced but the proposed course of
action is contrary to the ‘tailor to suit the project’ principle. It
is unlikely that the project management effort and approach
would be appropriate for the needs of the project. Ref 3.7
C. Correct. Unless PRINCE2 is tailored to suit the project
environment, size, complexity, importance, team
capability and risk, it is unlikely that the project
management effort and approach would be appropriate
for the needs of the project. Using PRINCE2 approaches
from a large multi
-national record company are unlikely
to be appropriate. Ref 3.7
D. Incorrect. The project should focus on specialist products,
but also ensure that the project management approaches are
appropriate. Without tailoring to suit the project, it is unlikely
that the project management effort and approach would be
appropriate for the needs of the project. Ref 3.7
The record company is concerned that the songs to be included on the album should be
agreed before work on the ‘recorded album’ starts. Therefore, the project board has decided
that no changes to the list of songs will be accepted after the work package has been agreed.
Which principle is being applied when making this decision, and why?
A. ‘Continued business justification’, because it sets limits on delegated change authority
B. ‘Continued business justification’, because it enables funds to be invested in worthwhile
objectives
C. ‘Focus on products’, because this will ensure that the album is delivered on budget
D. ‘Focus on products’, because it should ensure the album will meet expectations
A. Incorrect. The ‘focus on products’, not the ‘continued
business justification’ principle, is being applied, as the
project board is making sure there is a common
understanding of the product required. Moreover,
establishing limits of delegated authority is necessary to
apply the ‘manage by exception’ principle. Ref 3.5, 3.6
B. Incorrect. The ‘focus on products’, not the ‘continued
business justification’ principle, is being applied, as the
project board is making sure there is a common
understanding of the product required. This does not ensure
that funds are invested in worthwhile objectives. Ref 3.6, 3.1
C. Incorrect. It is true that applying the ‘focus on products’
principle helps in delivering products to budget, however it
does not ensure this. Applying other principles, primarily
‘manage by exception’ ensures that budget limits are not
exceeded. Ref 3.5, 3.6
D. Correct. The ‘focus on products’ principle is being
applied, as the project board is making sure there is a
common understanding of the product required.
Agreeing what is to be produced reduces the risk of user
dissatisfaction and acceptance disputes. Ref 3.6
BUSINESS CASE
Here are three statements from the business case for the Music Album Project.
Under which heading of the business case (A-F) should the statements be recorded?
Choose only ONE heading for each statement. Each heading can be used once, more than once,
or not at all.
9. It has been decided to invest in a new singer
10. We need to keep up with our competitors who
have seen an increase in sales from the new
singers they are signing with
11. Current customers may not buy from us if they see
a change in the style of music we sell. This may
cause a decrease in overall sales
A. Reason
B. Business options
C. Expected benefits
D. Expected dis-benefits
E. Timescale
F. Major risks
B 2.1.1a B. Correct. This identifies why the recommended
business option was chosen. Ref A.2.2
A, C, D, E, F. Incorrect. Ref A.2.2
10
A 2.1.1a A. Correct. This is one of the reasons why the project is
required. Ref A.2.2
B, C, D, E, F. Incorrect. Ref A.2.2
11
F 2.1.1a F. Correct. The focus of this project is to increase sales.
This is a threat to the company’s existing sales, and is
therefore a major risk. Ref A.2.2
- During the ‘initiating a project’ process, the Vice President (VP) estimated that the Music
Album Project should generate sales that exceed production costs. However, the sales
estimate may be too high, and therefore the record company may not make a profit. The VP
will undertake business assurance and the Marketing Manager, who is the senior user, will
undertake user assurance.
Is it appropriate for the VP to be responsible for assessing the effect of low sales on the
business case, and why?
A. Yes, because the VP should monitor whether the album sales are high enough
B. Yes, because business assurance reviews risks and their impact on the business case
C. No, because the executive is ultimately accountable for the project’s success
D. No, because the Marketing Manager should take responsibility for any risk to sales
A. Incorrect. Sales are generated and monitored after the
project. However, this is not why the Vice President (VP), who
is undertaking business assurance, should assess the impact
of the risk of low sales on the business case during the
project. Ref C.7, A.2.1
B. Correct. The role of business assurance, which the Vice
President (VP) is undertaking, should assess the impact of
the risk of low sales on the business case. Ref C.7, A.2.1
C. Incorrect. The executive is ultimately accountable for the
project’s success. However, this does not invalidate the VP
carrying out business assurance on the executive’s behalf. Ref
C.7, A.2.1
D. Incorrect. The Marketing Manager could undertake the
role of risk owner/actionee for this risk. However, this is not a
reason why the VP, undertaking business assurance, should
not assess the impact of the risk of low sales on the business
case. Ref C.7, A.2.1
The Vice President (VP) was appointed as executive of the Music Album Project, which is now
closing. During the project, extra funding was required and approved by the CEO. However,
this funding was given on the condition that, when closing the project, the executive
prepares an end project report showing the results of the project against its planned targets
in the business case.
Is this an appropriate condition, and why?
A. Yes, because the VP secures project funding and is accountable for the business case for
the duration of the project
B. Yes, because the VP is responsible for assessing the results of the project against the
expected benefits in the business case
C. No, because the project manager is responsible for preparing the end project report to
assess project performance and results
D. No, because the project manager verifies that the project was justified against external
events and project progress
C 2.1.2 A. Incorrect. The executive is responsible for both the
business case and the benefits review plan for the duration of
the project. During the ‘closing a project’ process, it is the
project manager who is responsible for reporting the results
of the project against the expected benefits in the business
case. Ref tab 6.1, C.2
B. Incorrect. The end project report is used to report project
performance during project closure. Preparing this report is
the responsibility of the project manager. Ref tab 6.1, 20.4.4,
C.2
C. Correct. The project manager is responsible for
preparing the end project report. One section in this
report is the assessment of the results of the project
against the expected benefits in the business case. Ref
tab 6.1, 20.4.4, C.5.1, A.8.2
D. Incorrect. The project manager is responsible for preparing
the end project report which includes an assessment of the
results of the project against the expected benefits in the
business. However, project assurance verifies and monitors
the business case against external events and project
progress. Ref tab 6.1, 20.4.4, C.5.1, C.7.1
ORGANIZATION
Here are three roles relating to the Music Album Project.
Which individual (A-F) would be most appropriate for each role?
Choose only ONE individual for each role. Each individual can be used ONCE, more than once, or
not at all.
14. Executive
15. Senior supplier
16. Delegated business assurance
A. CEO
B. Vice President
C. Contracts Manager
D. Marketing Director
E. Singer’s agent
F. Singer
14
B 2.2.1c B. Correct. The CEO, part of corporate management,
delegates management of new singers to the Vice
President. The Vice President supervises the production
of albums and has an interest in their success. Therefore,
the Vice President is the most appropriate person to be
the executive and take responsibility for the business
case. Ref C.2
A, C, D, E, F. Incorrect. Ref 7.3.4, C.2, C.4, C.7.1
15
C 2.2.1c C. Correct. There are a number of specialist suppliers to
this project. The Contracts Manager is responsible for
each of their contracts and is therefore the most
appropriate person to be senior supplier. Ref 7.3.4, C.4
A, B, D, E, F. Incorrect. Ref 7.3.4, C.2, C.4, C.7.
16
D 2.2.1c D. Correct. According to the scenario, the Marketing
Director verifies whether the sales of the album will
exceed the production costs and should therefore fulfil a
business project assurance role. Ref C.7.1
A, B, C, E, F. Incorrect. Ref 7.3.4, C.2, C.4, C.7.1
During the project, the CEO decides that the project should become a pilot project within a
programme to establish new ways to launch new singers quickly into the market.
Which action is appropriate, and why?
A. Project and programme management roles should be integrated, to ensure there are
clear lines of authority from top to bottom
B. Project and programme management roles should be integrated, to ensure there is
continued business justification for the project
C. Additional project roles should be defined, to ensure the programme roles and
responsibilities are mapped to the team roles
D. Additional project roles should be defined, to ensure the business role represents the
wider customer view at the delivery level
A 2.2.2 A. Correct. The programme and project management
team structures and roles need to be integrated so that
there are clear lines of responsibility from top to bottom.
Ref 7.3.3
B. Incorrect. Although roles need to be integrated, this is not
because of the need for continued business justification. Ref
7.3.3
C. Incorrect. This is an activity for a project within an agile
environment, not a programme. Ref 7.3.5
D. Incorrect. This is an activity for a project within an agile
environment, not a programme. Ref 7.3.5
During stage 1, when preparing the communication management approach, the project
manager included the record company’s Marketing Manager as a stakeholder. The
Marketing Manager will be checking with focus groups that the music in the album has a
market. Without a market for the album there will be no business justification for the project
to continue.
How well does this action apply the ‘organization’ theme, and why?
A. It applies it well, because stakeholders external to the customer organization can
exert a powerful influence on the project’s success
B. It applies it well, because the Marketing Manager will need to be aware of
progress information about the stage and receive reports from the focus groups
C. It applies it poorly, because stakeholders are those groups or individuals who will
be affected by the project’s outputs, such as delivery channels
D. It applies it poorly, because the focus groups should be included in the
communication management approach as stakeholders, not the Marketing
Manager
2.2.2 A. Incorrect. It is true that stakeholders external to the
customer organization can exert influence on the project.
However, this does not explain why defining the Marketing
Manager as an internal stakeholder with communication
needs is an appropriate application of the
‘organization
’
theme. Ref 7.3.9
B. Correct. Stakeholders are individuals or groups that
have an interest in the project. They may be internal or
external to the customer organization and may affect or
be affected by the project. The communication
management approach is used to document how
stakeholder engagement will be carried out. The
Marketing Manager is an internal stakeholder with a
clear need for bi
-directional communication with the
focus groups. The information shared could affect the
business justification for the project. Ref 7.3.9, glossary
C. Incorrect. This is an appropriate application of the ‘organization’ theme. Also, a stakeholder is any individual or
group that has an interest in a project, who may affect or be
affected by it. Ref 7.1, 7.3.9
D. Incorrect. The focus groups are stakeholders who should
be included in the communication management approach.
However, this does not mean that the Marketing Manager is
not also a stakeholder whose communication needs should
be included. Ref 7.3.9, glossary
QUALITY
The Music Album Project is approaching the end of stage 3 and the project manager is planning
stage 4.
Here are three actions related to managing quality for stage 4.
Which role (A-F) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
19. Review the quality criteria for the ‘registered
artwork’ to recommend additional people to be
involved in the quality review
20. Agree that the ‘launch event plan’ should be
presented to the project board in the format of a
slide deck
21. Document that the ‘launch event plan’ should be
presented to the project board in the format of a
slide deck
A. Executive
B. Senior user
C. Project manager
D. Team manager
E. Project assurance
F. Project support
19
E 2.3.1b E. Correct. Project assurance should assist the project
board and project manager by reviewing the product
descriptions and advising the project manager on
suitable quality reviewers. Ref tab 8.1
A, B, C, D, F. Incorrect. Ref tab 8.1, A.17.2
20
B 2.3.1b B. Correct. The ‘launch event plan’ is a key user product
and the format and presentation of this product would
be included in the product description. The senior user
approves product descriptions for key user products. Ref
tab 8.1, A.17.2
A, C, D, E, F. Incorrect. Ref tab 8.1, A.17.2
C 2.3.1b C. Correct. The project manager prepares and maintains
product descriptions. Ref tab 8.1
A, B, D, E, F. Incorrect. Ref tab 8.1, A.17.2
The product description for the ‘launch event plan’ was updated at the end of stage 3 to
include more detailed quality criteria. The ‘launch event plan’ was created during stage 4.
The ‘launch event plan’ was then approved by the project manager after checking that it met
the defined quality criteria.
Is this an appropriate way to manage quality, and why?
A. Yes, because the project manager should ensure that the quality controls for the ‘launch
event plan’ will meet the defined quality criteria
B. Yes, because the project manager should ensure that product descriptions are updated
when planning the next stage
C. No, because it is the senior user who should confirm the customer quality expectations
and acceptance criteria for the project
D. No, because it is the senior user who should provide resources to review and approve
the ‘launch event plan’ according to the defined quality criteria
A. Incorrect. The project manager should ensure that team
managers implement the quality control measures agreed in
product descriptions and work packages. However, the senior
user should provide resources to undertake user quality
activities and product approval, rather than the project
manager giving approval. Ref tab 8.1
B. Incorrect. It is true that as part of the ‘plan the next
management stage’ activity, product descriptions should be
updated for the products to be delivered in the next stage.
However, this does not explain why it is the senior user, not
the project manager, who should approve the delivered
product. Ref 19.4.1, tab 8.1
C. Incorrect. It is true that the senior user should confirm the
customer quality expectations and acceptance criteria for the
project. However, this does not explain why it is the senior
user, not the project manager, who should approve the
delivered product. Ref tab 8.1
D. Correct. The senior user should provide resources to
undertake user quality activities and product approval.
Therefore, the project manager should not approve the
‘launch event plan’. Ref tab 8.1
The album will be recorded by an external supplier. The project manager is concerned that
the record company will have no access to check the quality of the recorded songs before
the album is completed. Therefore, the project manager has requested that the contract
with the supplier includes a requirement to review the quality of the songs after each one is
recorded.
Is this appropriate, and why?
A. Yes, because the customer should specify their rights of inspection as well as the quality
expectations for a product
B. Yes, because the senior supplier should approve the quality methods to be used to
check the quality of the recorded songs
C. No, because the team manager should ensure that the recorded songs meet the quality
criteria specified in the product description
D. No, because there should be a shared understanding between the customer and the
supplier of the quality levels required
A 2.3.2 A. Correct. It is important to be clear about who is
responsible for which aspect of quality. This is
particularly important in commercial customer/supplier
situations, where the contract needs to make clear what
the quality expectations are. It is also advisable to define
the customer’s rights of inspection and audit in terms of
what can be inspected or audited, how often and how
much notice needs to be given for any inspection or
audit. Ref 8.3.7
B. Incorrect. The senior supplier approves the quality
methods, techniques and tools adopted in product
development. However, this does not explain why it is also
advisable to define the customer’s rights of inspection. Ref
8.3.7, tab 8.1
C. Incorrect. The team manager is responsible for producing
products consistent with product descriptions. However, this
does not explain why it is also advisable to define the
customer’s rights of inspection. Ref 8.3.7, tab 8.1
D. Incorrect. There must be a shared understanding between
the customer and the supplier of the quality expected.
However, this does not explain why the customer should
specify their right to inspect the quality of a product or
products. Ref 8.3.6, 8.3.7
PLANS
Here are three items of content included in the stage plan for stage 3 of the Music Album Project.
Under which heading (A-F) should each item be recorded?
Choose only ONE heading for each item of information. Each heading can be used once, more
than once, or not at all.
24. Inexperienced singers usually need several
attempts at recording a song. Therefore, more
time has been allowed for this activity in the stage
plan
25. The project manager will review the issue register
daily for priority 1 and 2 issues
26. The recording studio’s health and safety policies
and procedures
A. Plan prerequisites
B. External dependencies
C. Lessons incorporated
D. Monitoring and control
E. Budgets
F. Tolerances
24
C 2.4.1a C. Correct. Lessons incorporated are details of relevant
lessons from previous similar projects, which have been
reviewed. Therefore, this is an example of a lesson being
incorporated. Ref A.16.2
A, B, D, E, F. Incorrect. Ref A.16.2
25 D 2.4.1a D. Correct. Monitoring and control details of how the plan
will be monitored and controlled. The project manager
will determine how and when they want to monitor
aspects of the project. Ref A.16.2
A, B, C, E, F. Incorrect. Ref A.16.2
26 B 2.4.1a B. Correct. The work in stage 3 will be dependent on
compliance with the recording studio’s health and safety
policies and procedures. These already exist outside of
the project, so therefore are an external dependency. Ref
A.16.2
A, C, D, E, F. Incorrect. Ref A.16.2
. During stage 3, it was decided to change the design of the ‘artwork’ to attract attention and
help promote sales. The project board agreed to pay for the change using the change
budget. The project plan was later updated to show the amount of change budget still
available to the project.
Was it appropriate to update the project plan, and why?
A. Yes, because the project board will use the project plan and project justification when
deciding whether to carry out future changes or not
B. Yes, because the project board will have used the project plan and project justification
when deciding whether to carry out this change or not
C. No, because the project plan provides a baseline against which the project board
monitors project progress
D. No, because using the change budget for the change will not impact the project cost
budget
A 2.4.2 A. Correct. It is appropriate to update the amount of
change budget remaining, as this information will be of
value when making decisions regarding requests for
change in the future. Ref 15.4.4, 9.2.1.1, A.16.2
B. Incorrect. The project plan provides the business case with
planned costs and is used by the project board as a baseline
to monitor project progress against. The project board will
consider business justification and impact to the project
when they make decisions relating to requests for change.
However, this does not explain why the action described is
appropriate, as the decision to approve the request for
change has already taken place. Ref 15.4.4, 9.2.1.1
C. Incorrect. The project plan is used by the project board as a
baseline for measuring actual progress. However, this does
not explain why updating the amount of change budget
remaining is an appropriate action in this situation. Ref
9.2.1.1
D. Incorrect. The use of the change budget will not require a
change to the project budget. However, this does not explain
why it is appropriate to update the amount of change budget
remaining. Ref A.16.2, glossary
. The project is in the initiation stage. In consultation with the senior user, the project
manager has made some changes to the description of the final product ‘album ready for
launch’. The project manager’s next task is to plan the project.
Which action demonstrates the project manager’s immediate priority, and why?
A. Create a hierarchy of products for the ‘album ready for launch’, because it is necessary
to understand the major products and their component products
B. Create a hierarchy of products for the ‘album ready for launch’, because the
interdependencies between the component products need to be understood
C. Identify the product interdependencies between the ‘recorded album’ and the ‘artwork’,
because this is necessary in order to decide on activities and resources
D. Identify the product interdependencies between the ‘recorded album’ and the ‘artwork’,
because this is necessary in order to explore their more detailed characteristics
A. Correct. After finalizing the description of the project
product, a hierarchy of products is produced, known as a
product breakdown structure. The project product is
broken down into its major products, which are then
further broken down until an appropriate level of detail
for the plan is reached. Only after identifying a product it
is possible to explore and understand its detailed nature
and other features such as purpose and function. Ref
9.3.1.2, fig 9.6, 9.2
B. Incorrect. The hierarchy of products, known as the product
breakdown structure, is helpful in identifying the products at
the level of detail necessary for a plan. It is a product flow
diagram that identifies and defines the dependencies
between the products. Ref 9.3.1.2
C. Incorrect. A product flow diagram is used to identify and
define the sequence in which the products will be developed
and any dependencies between them. This is created in the
fourth step of ‘defining and analyzing the products’. It is true
that the products and their interdependencies should be
identified before deciding what activities and resources are
required to deliver those products. However, identifying the
products is the immediate priority. Ref 9.3.1.2, fig 9.6, 9.1.3
D. Incorrect. A product flow diagram is used to identify and
define the sequence in which the products will be developed
and any dependencies between them. This is created after
producing a hierarchy of the products within the project,
known as a product breakdown structure, and then writing
more detailed product descriptions. Identifying the products
is the immediate priority. Ref 9.3.1.2, fig 9.6
RISK
When negotiating a contract with the singer, information was received that the singer may sign a
contract with another record company.
Here are three actions relating to the management of this risk.
During which activity relating to the recommended risk management procedure (A-F) should they
occur?
Choose only ONE activity for each action. Each activity can be used once, more than once, or not
at all.
29. The reason that the singer may sign with another
company is that this other company may offer more
favourable terms
30. The contract terms are updated to make them
more favourable
31. The Contracts Manager signs a revised contract
with more favourable terms than the previous offer
A. Identify the risk
B. Estimate the risk
C. Plan the response
D. Implement the response
E. Communicate about the
risk
F. Fund the response from the
risk budg
29 A 2.5.1c A. Correct. This identifies the risk cause that the singer
may be offered more favourable terms by another record
company. Ref 10.4.1.2
B, C, D, E, F - Incorrect. Ref 10.4.1.2, 10.4.4
30 D 2.5.1c D. Correct. This is an ‘implement’ the response activity as
it is an action to reduce the chances of the singer signing
with the other company. Ref 10.4.4
A, B, C, E, F - Incorrect. Ref 10.4.1.2, 10.4.4
31 D 2.5.1c D. Correct. This is an ‘implement’ the response activity as
it is an action to reduce the chances of the singer signing
with the other company. Ref 10.4.4
A, B, C, E, F - Incorrect. Ref 10.4.1.2, 10.4.4
The singer has signed a contract with the record company. The contract specified that the
singer would perform at a large international festival on a Friday night. It is hoped that this
may increase international sales of the album. However, the audience is usually bigger on a
Saturday. Therefore, the project manager managed to negotiate for the singer to perform on
Saturday, rather than Friday.
Has the project manager exploited the opportunity to increase album sales, and why?
A. Yes, because the positive effect on album sales is not guaranteed
B. Yes, because the project manager’s response will make the risk cause a certainty
C. No, because the singer now has the opportunity to appear on Saturday
D. No, because performing on Saturday may have a greater impact on album sales
B 2.5.2 A. Incorrect. Arranging for the singer to perform at the festival
on Saturday would exploit the opportunity offered, ensuring
that the larger audience is reached. While it is true that the
increase in sales is not guaranteed, this does not explain why
this response exploits the opportunity. Ref tab 10.3
B. Correct. The exploit response is about making the
uncertain situation certain by removing the risk. This can
often be achieved by implementing the cause of an
opportunity. Therefore, funding the singer to perform at
the festival on Saturday, instead of the Friday, would
exploit the opportunity offered, ensuring that the larger
audience is reached. Ref tab 10.3
C. Incorrect. It is true that the singer now has the opportunity
to appear on the Saturday. However, as the project manager
has negotiated for the singer to perform at the festival on
Saturday this exploits the opportunity offered, ensuring that
the larger audience is reached. Ref tab 10.3
D. Incorrect. It is true that performing on the Saturday may
have a greater impact on album sales. However, funding the
singer to perform at the festival on Saturday exploits the
opportunity offered, ensuring that the larger audience is
reached. Ref tab 10.3
The Marketing Director will analyse the opinions of focus groups to check that the album will
be marketable and generate sufficient sales. At the end of the initiation stage, the following
risk was recorded in the risk register:
“There is a threat that the project will be no longer viable which would result in the project
needing to be stopped.”
How well does this identify the risk, and why?
A. It identifies it well, because the impact that the risk could have on the project and its
viability is clearly understood
B. It identifies it well, because risks should be identified continuously throughout the
project and recorded in the risk register
C. It identifies it poorly, because the source of the risk has not been understood so the
relevant risk responses cannot be selected
D. It identifies it poorly, because the effect of the risk has not been understood so the
relevant risk responses cannot be selected
C 2.5.2 A. Incorrect. The risk effect should describe the impact(s) that
the risk would have on the project objectives should the risk
materialize. The risk event and effect have been defined, but
not the risk cause
. Ref 10.4.1.2
B. Incorrect. Risks can, and should, be identified at any time
during the management and delivery of the project. However,
the risk event and effect have been defined, but not the risk
cause. Ref 10.4.1.2
C. Correct. The risk cause should describe the source of
the risk. An important aspect of identifying risks is being
able to provide a clear and unambiguous expression of
each one. Without understanding the risk cause, it is not
possible to manage the risk effectively. Ref 10.4.1.2
D. Incorrect. The risk effect should describe the impacts that
the risk would have on the project objectives, should the risk
materialize. The risk effect is clearly described. Therefore, this
does not explain why the risk is poorly identified. Ref 10.4.1.2
CHANGE
An issue has been raised that the singer wants to add an extra song to the recorded album.
Making this change would take stage 3 beyond its cost tolerance.
Here are three actions that are carried out when managing the issue.
During which step of the issue and change control procedure (A-E) should they be carried out?
Choose only ONE step for each action. Each step can be used once, more than once, or not at all.
34. The project manager asks the senior user to
confirm the priority of adding the song, before
considering what action to recommend
35. When the impact is reviewed, it is decided that the
issue should be managed formally, rather than
informally
36. The project board requests a plan to record the
extra song
A. Capturing issues
B. Assessing issues
C. Proposing corrective actions
D. Deciding on corrective
actions
E. Implementing corrective
actions
34
B 2.6.1c B. Correct. As part of the ‘assessing issues’ step, it may be
necessary to request advice from the project board to
check their understanding of the issue’s priority or
severity before proposing resolutions. Ref 11.4.2
A, C, D, E. Incorrect. Ref 11.4.1
-
5
35
B 2.6.1c B. Correct. During the ‘assessing issues’ step, when the
impact is reviewed, the decision can be taken that the
issue needs to be managed formally rather than
informally, as may have been decided during ‘capturing
issues’. Ref 11.4.1, 11.4.2
A, C, D, E. Incorrect. Ref 11.4.1
-
5 2.6.1c D. Correct. As part of the ‘deciding on corrective actions’
step, the project manager checks if the issue could be
handled without the need to escalate it to the project
board. If not, the issue will be escalated to the project
board for a decision and they may ask for an exception
plan. Ref 11.4.4
A, B, C, E. Incorrect. Ref 11.4.1
-
5