Udemy Practitioner - Flashcards
(50 cards)
Question 3: Incorrect
The project is initiated to meet the requirement of the new investment. The new investor has most of the resources and products required for the project to be finished. Therefore the CEO requests to have only 2 stages for the project for faster delivery.
Which principle is being applied, and why?
A) ‘Manage by stages’, because stages have to be aligned to organizational polices.
B) ‘Manage by stages’ because this is the minimum number of stages required by PRINCE2
C) ‘Define roles and responsibilities’, because business sponsors ensure investment value for money.
D) ‘Define roles and responsibilities’, because CEO has the final say on the project setting.
Correct: (B) ‘Manage by stages’ because this is the minimum number of stages required by PRINCE2
3.4 a project must have at least two management stages: initiation stage and one management stage.
Question 6: Incorrect
In stage 3, the team manager has attended a technical conference for new mobile functionalities and found out that, one particular function would enhance the feature of the product being developed. Hence he asks the development team to take extra tasks to enhance the product.
Is this an appropriate application of ‘focus on product’ principle, and why?
A) Yes, because focus on products means keeping the customer satisfied.
B) Yes, because quality is the main focus for delivering products.
C) No, because the product being developed should be within agreed boundary.
D) No, because external sources cannot be used for internal products.
(C) No, because the product being developed should be within agreed boundaries.
3.6 - An output oriented project is one that agrees and defines the project product prior to undertaking the activities required to produce it. The set of agreed products defines the scope of a project and provides the basis for planing and control.
This is referring to “scope cree”. By asking the development team to take on extra tasks to enhance the project is uncontrolled change.
Question 8: Incorrect
The project relies heavily on the software vendor to deliver “beta version of mobile app”, one of the main products. Because of that, the project manager decides to copy the PID as part of the contract to avoid any misunderstandings between the company and the vendor, and also to deliver product fast.
Is this appropriate, and why?
A) Yes, because it would encourage the fast delivery, ensure alignment and maintain momentum.
B) Yes, because it may eliminate potential external and internal dependencies.
C) No, because writing epics and user stories should be carried out, instead of combining PID and contract, to promote agile approach.
D) No, because it may limit the adaptability to fulfill the contract’s obligation.
D) No, because it may limit the adaptability to fulfill the contracts obligation.
4.3.4.3 Try to avoid including the PID as part of contract.
The PID and contract fulfill different purposes. One aspect of a contract is to describe who is liable if either party fails to fulfill its contractual obligations. The content of the PID should focus on practical management arrangements to make sure that each party can fulfill its obligations: the PID must reflect the contract conditions. Try to avoid including the PID as part of the contract documentation, as it may limit the project managers ability to adapt it if the PID has to go through a formal contractual review for each change.
Question 9: Incorrect
BUSINESS CASE
Here are three statements from the business case for the Shopping Mobile App Project.
Under which heading of the business case (A-F) should the statements be recorded? Choose only one for each statement. Each heading can be used once, more than once, or not at all.
The ongoing maintenance of cloud infrastructure will be funded by IT Operation.
A) Reason
B) Business options
C) Expected benefits
D) Expected dis-benefits
E) Cost
F) Major Risks
E) Cost
A.2.2 Business case
Costs: A summarum of the project costs ( Taken from the project plan), the ongoing operations and maintenance costs and their funding arrangements.
Question 10: Incorrect
Here are three statements from the business case for the Shopping Mobile App Project.
Under which heading of the business case (A-F) should the statements be recorded? Choose only one for each statement. Each heading can be used once, more than once, or not at all.
The sales of the current supermarket stores may be decreased due to increasing use of the mobile app.
A) Reason
B)Business Options
C)Expected benefits
D) Expected dis-benefits
E)Costs
F) Major Risks
F) Major Risks
Gives a summary of the KEY RISKS associated with the project, together with the likely impact and plans should they occur.
Question 13: Incorrect
The mobile technologies are evolving very quickly and it is hard to decide the right approach to the mobile app development. Because of that, the senior user suggests to make a prototype. The project manger then develops the business case in a very short time of period.
Is this appropriate, and why?
A) Yes, because the assumption can be quickly verified.
B) Yes, because the project manager should consider the senior user’s suggestion.
C) No, because business case should be assessed thoroughly and take longer time to validate.
D) No, because making a prototype will lead to over-budget and should be avoided.
A) Yes, because the assumption can be quickly verified.
6.3.5
If there is a high level of uncertainty, the business case should be developed very quickly and the assumptions tested quickly.
Question 14: Incorrect
ORGANIZATION
Use the ‘Additional Information’ in the Scenario Booklet to answer this question. Here are three roles relating to the Shopping Mobile App Project.
Which individual (A-F) would be most appropriate for each role? Choose only one individual for each role. Each individual can be used ONCE, or not at all.
Executive
I don’t have the booklet….tee hee
Toward the end of stage 4, the project assurance reminds the project manager to inform only the project board, that the project is closing. The project manager insists to inform all stakeholders.
How well does the project managers action apply the organization theme and why?
A) It applies it well, because the project manager is responsible to undertake stakeholder engagement.
B) It applies it well, because the project assurance is not at the managing level, project manager should ignore any advice.
C) It applies it poorly, because the project manager should inform the project board to authorize the project closure.
D) It applies it poorly, because the project manager should listen to the project assurance’s advice and engage stakeholders with different approaches.
A) It applies it well, because the project manager is responsible to undertake stakeholder engagement.
7.1., 7.2.2
Question 24: Incorrect
PLANS
Here are three statements that are considered when planning the Shopping Mobile App Project.
Which step in PRINCE2’s recommended approach to planning do they apply to? Choose only one step for each statement. Each step can be used once, more than once, or not at all.
‘Obtaining the company’s UX guidelines’ is required to create product ‘mobile app UX design’.
A) Designing a Plan
B) Defining and analyzing products
C) Identifying activities and dependencies
D) Preparing estimates
E)Preparing schedule
F) Documenting plan
C) Identifying activities and dependencies
9.3.1.3 The dependency between activities is identified during ‘identifying activities and dependencies’
Question 25: Incorrect
Here are three statements that are considered when planning the Shopping Mobile App Project.
Which step in PRINCE2’s recommended approach to planning do they apply to? Choose only one step for each statement. Each step can be used once, more than once, or not at all.
The dependency between ‘mobile app UX design’ and ‘beat version of mobile app’ is identified.
A)Designing a plan
B) Defining and analyzing the products
C) Identifying activities and dependencies
D) Preparing estimates
E) Preparing Schedule
F) Documenting plan
B) Defining and analyzing the products
9.3.1.2
Question 26: Incorrect
Here are three statements that are considered when planning the Shopping Mobile App Project.
Which step in PRINCE2’s recommended approach to planning do they apply to? Choose only one step for each statement. Each step can be used once, more than once, or not at all.
Stage 2 is defined to be 8 weeks long.
A) Designing a Plan
B) Defining and analyzing the products
C) Identifying activities and dependencies
D) preparing estimates
E) Preparing a schedule
F) Documenting a plan
A) Designing a Plan
9.3.1.1 The length of management stages is planned during ‘designing a plan’
Question 27: Incorrect
The project manager is struggling in planning therefore he seeks the project consultant’s help. The project consultant advises him that all plans should be consistent and thoroughly discussed with concrete details to avoid misalignment.
Is this appropriate, and why?
A) Yes, because detailed scope eliminates frustration and rework.
B) Yes, because consistent plans remove dependencies.
C) No, because communication management approach addresses the problems caused by misalignment
D) No because some plans can be less detailed.
Correct: D) No, because some plans can be less detailed.
9.1.2 Considering the planning horizon, high-level and detailed plans are created.
this is the ‘planning horizon’. You can waste a bunch of time trying to make the “perfect plan.” But after a few weeks your plans will most certainly be inaccurate.
Question 28: Incorrect
Two weeks later the project will be approaching the end stage 2, unfortunately the testing engineer is sick and has applied 3 weeks sick leave. It is filed and reported to the management. The project manager is then instructed to develop a plan for this.
Is this appropriate, and why?
A) Yes, because any problems occurred during ‘managing product delivery’, the project manager should develop this type of plan.
B) Yes, because it is the responsibility of a project manager to develop this type of plan.
C) No, because team managers should also be responsible for developing the plan.
D) No, because it is vital to define and analyze the situation first before planning for responses.
(B) Yes, because it is the responsibility of a project manager to develop this type of plan.
9.2.2, Table 9.1 Project Manager is responsible for preparing the exception plan.
Question 29: Incorrect
RISK
Here are three actions relating to the management of risks.
Which response (A-F) is described in each action? Choose only one response for each action. Each response can be used once, more than once, or not at all.
Because the new advertisement of the company, which is outside the project, is a big success, it is likely that more customers are willing to download and try the new Shopping Mobile App launched in the coming future. The project team is preparing enough capacity to secure the benefits.
A) Avoid
B) Exploit
C) Accept
D) Reduce
E) Enhance
F) Prepare
E) Enhance
Table 10.3 the team enhances the opportunity by preparing enough capacity.
Question 35: Incorrect
The following issue has been recorded in the issue report: “The new product would affect the current POS system’s response time.”
Here are three items of content included in the issue report.
Under which heading (A-F) should each item be recorded? Choose only one heading for each item of information. Each heading can be used once, more than once, or not at all.
The Operation manager logged down the incident in the incident log.
A) Issue type
B) Raised by
C) Issue report Author
D) Issue description
E) Recommendation
F) Decision
(B) Raise by
A.13.2 Issue Report
Question 38: Incorrect
A user found out that he forgot his password to access the testing environment. The project manager looked into it and figured out that it could be resolved immediately in the same day, hence he captured it in the daily log.
Is this appropriate, and why?
A) Yes, because daily log is used to capture problems solved in a day.
B) Yes, because the project manager can decide the best course of action.
C) No, because the project manager should capture it in the issue log instead.
D) No, because the issue should be escalated to project board to decide whether to be recorded in issue log.
B) Yes, because the project manager can decide the best course of action.
11.4.1 When issue can be solved immediately, it can be counted as ‘informal,’ informal issue can be managed in “Daily loge.”
Question 40: Incorrect
Here are three statements relating to the Shopping Mobile App Project.
In which management product (A-F) should this tolerance be recorded? Choose only one product for each tolerance. Each product can be used once, more than once, or not at all.
‘Testing environment’ should be delivered 5 weeks after the start of stage 4.
A) Project Plan
B) Stage Plan
C) Work Package
D) Project Product Description
E) Product Description
F) Business Case
C) Work Package
12.2.1, table 12.1 Cost, work level tolerances.
Question 44: Incorrect
STARTING UP A PROJECT
Here are three actions that take place during the ‘starting up a project’ process.
Which theme (A-F) is being applied? Choose only one theme for each action. Each theme can be used once, more than once, or not at all.
Design the reporting line for the management of flaws found in the mobile app.
A) Business case
B) Organization
C) Risk
D) Progress
E) Plans
F) Quality
B) Organization
14.4.3 When designing the project management team based on their roles, the reporting line can be designated.
Question 47: Incorrect
During the ‘starting up a project’ process, the newly appointed manager is collecting all the proposed system designs for the mobile app for later use of initiating the project. He does not filter them at all because making all the prototypes would help to find out the best solution and ensure the viability of the project.
Is this appropriate, and why?
A) Yes, because ensuring viability of a project is the desired outcome.
B) Yes, because prototyping is a technique for preparing business case.
C) No, because time would be wasted during initiation the project.
D) No, because agile approach is recommended to start up a project.
C) No, because time would be wasted during initiating the project
14.2 Unsound assumptions should be avoided to ensure time is not wasted.
Question 52: Incorrect
INITIATING A PROJECT
Here are three actions relating to the ‘initiating a project’ process.
In which activity (A-F) should each action be recorded? Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
Look into the company’s information repository to see whether there are similar projects that contain suitable processes recommended by the programme management for the Shopping Mobile App Project
A) Agree the tailoring requirements
B) Prepare the risk management approach
C) Prepare the change control approach
D)Prepare the quality management approach
A) Agree the tailoring requirements
16.4.1 Seek lessons from similar projects related to tailoring. Checking whether there are suitable processes for the project that indicates tailoring.
Question 56: Incorrect
CONTROLLING A STAGE
Here are three actions that are carried out during the ‘controlling a stage’ process.
During which activity (A-F) should each action be carried out? Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
The project manager updates the issue report for the completion of bugs-fixing of the ‘cloud automation scripts’.
A) Authorize a work package
B) Review work package status
C) Review the management status
D) Report highlights
E) Capture and assess issues and risks
F) Take corrective action
Explanation: (F) Take corrective action
17.4.8 Completion of fixing bugs indicates status of the corrective action, which is updated in the issue report.
Question 58: Incorrect
Here are three actions that are carried out during the ‘controlling a stage’ process.
During which activity (A-F) should each action be carried out?
Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
The project manager reviews the estimated time to complete the technical documentation from the information provided by team manager regularly.
A) Authorize a work package
B) Review work package status
C) Review the management status
D) Report Highlights
E) Capture and assess issues and risks
F) Take corrective action
B). Review work package status
17.4.2 The project Manager reviews the work package progress from the checkpoint report, which is prepared by the team manager.
Question 59: Incorrect
During the ‘controlling a stage’ process, several parts of the product ‘testing scripts’ are finished and verified against the specifications. They are ready to be deployed in operation, so the project manager prepares the handover.
Is this appropriate, and why?
A) Yes, because products can be handed over by phases.
B) Yes, because product handover is done only during ‘controlling a stage.’
C) No, because handover is done during ‘closing a project.’
D) No, because whole set of a product is required to be finished before handover.
A) Yes, because products can be handed over by phases.
17.4.4 Products can be transferred to customer as part of a phased handover.
Question 63: Incorrect
MANAGING A STAGE BOUNDARY
The project is facing an external issue regarding privacy regulation. The project manager is requested by the project board to provide recommendations for the issue.
Which theme does this apply?
A) Change
B) Risk
C) Progress
D) Plan
D) Plan
19.4.5 This indicates that the project board requests for an exception plan which the project manager is going to create.