Procurement and Tendering Flashcards

(15 cards)

1
Q

What is procurement?

A

the overall process of acquiring construction work or services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What should be considered when selecting a procurement route?

A
  • the specifics of the project
  • time
  • cost
  • control
  • quality
  • risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main procurement methods?

A
  • traditional
  • design and build
  • management contracting
  • construction management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is traditional procurement?

A

the design is completed by the clients design team before competitive tenders are invited and a main contractor is employed to build what the designers have specified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How does traditional procurement work?

A
  • the contractor takes responsibility and financial risk for the construction of the works to the design produced by the clients design team for the contract sum within the contract period
  • the client takes the responsibility and risk for the design and design team performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When might traditional procurement be appropriate?

A
  • if the employer has had the design prepared
  • if the design is substantially completed at time of contractor selection
  • the client wishes to retain control over the design and specification
  • if cost certainty at start on site is important
  • the shortest overall programme is not the client’s main priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the advantages of traditional procurement?

A
  • retaining control over the design can lead to higher quality
  • it offers increased levels of cost certainty before commencement
  • design changes are reasonably easy to arrange and value
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the disadvantages of traditional procurement?

A
  • the overall project duration may be longer than others due to lack of overlap between design and construction
  • there is no input into design and planning by the contractor
  • a strategy based on price competition can lead to adversarial relations
  • there is a dual point of responsibility with the design team controlling the design and the contractor retaining responsibility for the construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is design and build?

A

where the contractor is responsible for the design, planning, organisation, control and construction of the works to the employer’s requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How does design and build work?

A

the employer gives the tenderers the employer’s requirements and the contractors responds with the contractors proposals, which include the price for the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When might design and build be appropriate?

A
  • where there is a need to make an early start on site as there can be overlap between design and construction
  • where the client wishes to minimise their risk as they transfer design responsibility to the main contractor
  • for technically complex projects requiring the contractor’s expertise
  • where the employer des not want to retain control over design development
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the advantages of design and build?

A
  • there is a single point of responsibility for the design and construction
  • there is early commencement on site
  • early price certainty is increased
  • the client can benefit from the contractor’s experience harnessed during the design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the disadvantages of design and build?

A
  • clients may find it hard to prepare a sufficiently comprehensive brief
  • the client has to commit to a concept design early
  • variations from the original brief are difficult to arrange and are often expensive
  • it is harder to compare tenders and harder to determine whether value for money is being achieved
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How much design input will the contractor have in design and build?

A
  • this depends on the amount of design work the employer has already had completed at the time of tender
  • this can range from full design to production information and coordination only
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who carries out the design for the contractor in design and build?

A
  • it may be outsourced to a separate design company
  • they may have in house design capabilities or the clients team may be novated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly