Sybex Glossary PMP Flashcards
(363 cards)
acceptance
Acceptance is a strategy for threats or opportunities and is part of a tool and technique of the Plan Risk Responses process. This strategy implies that the organization is willing to accept the consequences of the risk should it occur.
acceptance criteria
Acceptance criteria refers to the product of the project and includes the process and the criteria that will be used to determine whether the deliverables and the final product or service of the project are acceptable and satisfactory.
Achievement Theory
This motivational theory says people are motivated by the need for three things: achievement, power, and affiliation.
Acquire Project Team
This process involves attaining human resources and assigning them to the project. Human resources may come from inside or outside the organization. Acquire Project Team belongs to the Executing process group.
activity attributes
Activity attributes describe the characteristics of activities, such as the activity identifier or code, descriptions, constraints, and assumptions associated with the activity, predecessor activities, successor activities, resource requirements, the individual responsible for completing the work, and so on. The activity attributes are an extension of the activity list and are used in the schedule model tool and technique of the Develop Schedule process.
activity duration estimates
Activity duration estimates are quantifiable estimates of the number of work periods needed to complete the schedule activities listed. They are an output of the Estimate Activity Durations process.
activity list
This is an extension of the WBS that contains all the activities of the project and a description of each activity. The activity list is an output of the Define Activities process.
activity on arrow (AOA)
This is a network diagramming method that places activities on arrows, which connect to dependent activities using nodes. This is also known as the arrow diagramming method.
activity on node (AON)
This is a network diagramming method that places activities on nodes, which connect to dependent activities using arrows. This is also known as the precedence diagramming method.
actual cost (AC)
This is the actual cost of work to date or during a given time period, including direct and indirect costs.
addition
This is a type of project ending where the project evolves into an ongoing operation.
Administer Procurements
This process involves monitoring vendor performance and
ensuring that all the requirements of the contract are met.
advertising
This is the act of informing potential vendors that an RFP, RFQ, or other procurement document is available. This is a tool and technique of the Conduct Procurements process.
alternatives identification
This is a technique used to discover different methods or ways of accomplishing the project. Alternatives identification is a tool and technique of the Define Scope process.
analogous estimating
This technique uses the actual duration of a similar, completed activity to determine the duration of the current activity. This is also called top-down estimating and uses both expert judgment and historical information.
appeals
See contested changes.
appraisal costs
Appraisal costs are the costs expended to examine the product or process and make certain the requirements are being met. Appraisal costs might include costs associated with aspects such as inspections and testing.
approval requirements
Approval requirements refer to how the objectives, deliverables, project management documents, and other outcomes and results of the project will be approved.
arbitration
This is a negotiation technique used to settle contract disputes. All parties come to the table with a third, disinterested party who is not a participant in the contract to try to reach an agreement. The purpose of arbitration is to reach an agreement without having to go to court.
arrow diagramming method (ADM)
This is a network diagramming method that places activities on arrows, which connect to dependent activities using nodes. This is also known as activity on arrow.
assumption
This is an event or action believed to be true. Project assumptions should always be documented.
attributes
These are measurements of deliverables (or certain characteristics of the deliverable) that meet one of two options: conforming or nonconforming. Conforming meets the requirement; nonconforming does not. This is an inspection technique (which is a tool and technique) of the Perform Quality Control process.
avoid
The avoid strategy is used for risks that pose threats to the project or have negative impacts. It’s part of a tool and technique of the Plan Risk Responses process. This strategy requires changes to the project plan in order to avoid or eliminate risk events and their
impacts to the project objectives.
backward pass
This is a calculation used in CPM to determine late start and late finish dates for activities.