What is the purpose of the change theme?
Identify, asses and control any potential and approved changes to Project baseline
What is a baseline?
Reference levels against which an entity is monitored and controlled
Define issue…
Anything during a project which unless resolved, will result in a change to a baselined product, plan, or performance target
What are the 3 types of issue that may arise during a project:
1) Request for change
2) Off-specification
3) Problem or concern
What is a “request for change”
A proposal to change a baseline (CHANGE)
What is “off specification”
Something that should be provided, but is currently or is forecast not to be, provided (MISSING PRODUCT)
Problem or concern
Any other matter which requires the PM to resolve or maybe escalate to the project board (MINOR BUT NOTED)
Which process is Change Control approach defined in?
Initiating a project
Where is the Change Control Approach refined?
Managing a stage boundary process
Which product are part of the change control process?
1) Change control approach
2) Configuration item record
3) Product status accounts
4) Daily log
5) Issue register
6) Issue reports
What does the change control approach document?
1) Change control
2) Issue management
3) Records
4) Timing of activities
5) Assessment scales
2 things to consider when change arises
Change authority and change budget
What is the Configuration item record?
Records documentation information about a product, such as:
Status, version and variance
What is the Product status account?
State of all products within defined limits (a stage, or the whole project)
What is the Daily log?
Records problems, concerns and possible required action about the Project where the PM can manage informally