Activities in Starting up a project Flashcards

1
Q

Who is appointed in starting up a project process?

A

The Executive and the Project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What do we capture in starting up a project?

A

Lessons learned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Designing and appointing the project management team is part of what process?

A

Starting up a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What type of business case is created during starting up a project?

A

Outline business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What Is the project brief, which is assembled during starting up a project, made up of?

A

Outline business case
The project product description
Project approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What do we select during starting up a project?

A

The project approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the first plan across the whole of PRINCE 2, which takes place during starting up a project process?

A

Initiation stage plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What two items go to the Project board (directing a project process), as the request to initiate a project?

A

Stage Plan (Initiation)
Project Brief - Made up of Outline business case
project approach
Project product description

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is an input to the Starting up a project process?

A

Project Mandate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What products are created in the Starting up a project process?

A

Lessons log
Project Brief
Daily Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly