Controlling a Stage Flashcards
Which stage forms the main part of the PM work?
Controlling a stage
What are three main categories of activities for Controlling a stage
1) Work packages
2) Issues
3) Monitoring and reporting
What are three activities related to “issues” which are part of the Controlling a stage process?
Escalate issues and risks
Take corrective action
Capture an examine issues and risks
What are three activities related to “work packages” which are part of the Controlling a stage process?
Authorising work packages
Reviewing work package status
Receiving completed work packages
What are three activities related to “monitoring and reporting” which are part of the Controlling a stage process?
Review stage status
Reporting highlights
What happen in the ‘Review the management stage status” activity?
Look at big picture, looking at what has happened vs what is expected, making sure risks and issues are under control and if necessary triggering corrective action.
How are the the project board informed of progress in the controlling a stage process?
Highlight report
What is “taking corrective action”?
Any action required to maintain project schedule - modifying work packages or creating new one