Beddown Planning Flashcards

(6 cards)

1
Q

What occurs in the “set the Theatre” Stage?

A

Establish airfield, prep the FOS, Maintain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the three bare base minimum requirements?

A

Stabilized runway, Source of water that can be made potable, capable of supporting assigned aircraft & providing mission-essential resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What factors drive plan consideration?

A

Mission & Intel, Existing infrastructure, local environmental positions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the tenants of land use planning in the AOR?

A

Close proximity, walking distance, efficient utilities, security buffers, existing traffic circulation + utility systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the principles of a bare base?

A

layout a grid, place industrial uses at the perimeter, make it walkable/safe, build places to gather, make it defendable, allow for flexibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Four stages of a beddown?

A
  1. Initial - C+72hrs
  2. Intermediate - C + 10days
  3. Follow on Stage - C + 30days
  4. Sustainment Stage - C+>30days