Contingency Water Flashcards
(23 cards)
What are the storage water planning factors required during contingencies?
5-day supply of water
60% potable
30 GPPD
What are the capabilities of a ROWPU kit?
2 ROWPUs/Kit
Can operate 20 hours/day; 4 hours for backwash and maintenance
1:1 product:reject ratio
1500 gph
Explain the 5 day storage requirement
60% of water is potable; 40% is non-potable
What are the design considerations?
water source, population, threat conditions, topography, weather, duration
Source Run Subsystem (SRS)
Source to treatment: Floor assembly/strainer, Diesel Pump, collapsible fabric tank
Water Production System (WPS)
Treatment Plant: Strainer+floor assembly, Diesel Pump, Electric Pump Assembly, 20,000 gallon fabric tanks, ROWPU, 3000 gallon collapsible fabric tank
550 Initial Subsystem
Distribution for 550 personnel: Diesel pump, 20,000 gallon tank, dual pumping station, 3000 gallon collapsible fabric tank, bladder water level controllers
550 follow on subsystem
Adds distribution for 550 personnel
Flightline extension
Extension to flightline from WPS
How much of potable water at a base will become wastewater?
70%
What is the water treatment and distribution time?
D+10 days to lay water lines, develop water and waste program
Personnel:Toilet Ratio?
1 toilet serves 20 people
What are the basic siting requirements for wastewater tanks?
100 yards from nearest dining facility; 100 feet from nearest water source; septic tank must be >400’ from leaching field
What is the wastewater generated/person before and after BEAR assets?
Initial: 15 GPPPD
BEAR: 21 GPPPD
What are the important separation distances? (hint - 4)
- Facility to macerator pump - 100 feet
- Macerator pump to dual pump lift station - 500 feet
- Dual pump lift station to wastewater tank - 100 feet
- Total distance facility to wastewater tank - 700 feet
550-initial subsystem (wastewater)
Sewage ejector systems, macerator pump lift station. dual pump lift station, 25000 gallon wastewater collection tank with mixing systems
550-follow subsystem
Sewage ejector system, sewage ejector lift station, macerator pump lift station
Evaporation Lagoon
Can’t use in PACAF lmao; net evaporation rate of 46in/year
Septic Tanks/Leach Field
solids settle to the bottom, effluent dispersed into drain field; <1000 - 15000 gpd; cleaned every 1-3 years
Package Plants
Modular or package form of sewage treatment plants; primary and secondary treatment
Conventional Treatment Plant
Most preferred treatment method; highest cost
Benefits of reducing water demand
less competition with local community; save money/resources/energy; reduce base vulnerability