Case Study Flashcards

1
Q

As NRM 1, do we include a contingency for design development risks?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What were the perceived benefits of the 2-week PCSA period?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What design information was missing at contract award?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What needs to happen between contractor appointment and construction phase?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How long should this period be?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where is this set out?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How did CDM apply to this project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does the importance of Value Engineering relate to the client’s key drivers?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What was your role in identifying the alternative construction solutions?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Talk me through how you used your knowledge of construction technology to identify issues with Option B – Concrete Rib Deck?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Talk me through how you priced the variation Option C – Installation of shallow steel beams with internal timber joist work.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Talk me through the structure of your procurement schedule?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What were your reasons for engaging with the supply chain in respect of the Tier 1 joinery as Option A?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

As a QS, did you/the project team/client not have confidence that ‘I believed the costs provided to be a true representation….’?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What benefit(s) did you consider engaging with the wider market for these works provided, to offset the additional time it took?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

From an ethical perspective, what issues were there in asking the supply chain to incur costs tendering for works that were unlikely to be awarded?

A
17
Q

Talk me through how you used the elemental cost plan to identify potential areas of Value Engineering?

A
18
Q

What advice did you give in respect to Key Issue 1?

A
19
Q

Had you not undertaken Option A, would there have been a programme impact?

A
20
Q

Talk me through ‘the pitfalls of negotiated tendering’ as happened on this project?

A
21
Q

What advice did you give with respect to Key Issue2?

A