Why was Option C chosen for this project?
What were the Z-Clause amendments for this project
How was the project tendered to ensure best value was achieved?
How does the form of contract vary from the standard NEC3 or 4 contract at that time?
What was the role of the PM on the project in relation to this issue?
Why were there so many revised quotations for the CE?
What was the escalation process?
Why did you feel this issue required legal counsel?
What was your interaction with this particular part of the issue
What was the cost to the client for all the input from you and the PM on the project? Was this covered off in your fees?
Explain your understanding of the Healthy Buildings case noted in this case study
On the initial quotation, why did you believe that option 2 was a viable solution without your intervention or assessment?
What was the risk of instructing a revised quotation?
What were the ‘failure to address other comments’ by the contractor?
What did you do to assess the quotations to ensure they were competently submitted in terms of cost?
Can you clarify how many quotations where received, as its slightly confusing (you have noted WTE-35, QTE-43 and QTE-52) for the reader
The second revised quote (QTE-52) was significantly more on both cost and programme implications, why was this?
What were the remaining risks for this second option if instructed?
Why were the submissions late?
What was the time restriction in the contract?
What was the benefit of having such restrictions in place?
What was the PM’s assessment of the claim?
Why was the claim (QTE-60) so much higher and longer in impact?
What is the supporting position on the Healthy Buildings case for both parties?