ch6 Flashcards

(20 cards)

1
Q

What is the main goal of Project Time Management?

A

To ensure the timely completion of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name the six processes in Project Time Management.

A

Plan schedule management, define activities, sequence activities, estimate activity resources, estimate activity durations, and develop schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of the Plan Schedule Management process?

A

To establish policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define “Activity” in project time management.

A

A distinct, scheduled portion of work performed during the course of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the output of the Define Activities process?

A

Activity list, activity attributes, and milestone list.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does the Sequence Activities process involve?

A

Identifying and documenting relationships among project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Name one common method used to sequence activities.

A

Precedence Diagramming Method (PDM).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the four types of dependencies in PDM?

A

Finish-to-Start (FS), Finish-to-Finish (FF), Start-to-Start (SS), Start-to-Finish (SF).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of estimating activity resources?

A

To determine the type and quantities of resources required to perform each activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is an important output of Estimate Activity Resources?

A

Resource breakdown structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the goal of Estimate Activity Durations?

A

To estimate the number of work periods needed to complete individual activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are some tools for estimating activity durations?

A

Expert judgment, analogous estimating, parametric estimating, three-point estimating, and reserve analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define “Critical Path”.

A

The sequence of activities that determines the earliest possible completion date of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Float or Slack?

A

The amount of time an activity can be delayed without delaying the project completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the techniques used in developing the project schedule?

A

Critical path method, critical chain method, resource optimization, modeling techniques, and schedule compression.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Fast Tracking in schedule compression?

A

Performing activities in parallel that were originally planned in sequence.

17
Q

What is Crashing in schedule compression?

A

Adding resources to shorten the duration of activities.

18
Q

What is a milestone in a project schedule?

A

A significant point or event in a project.

19
Q

What is the output of the Develop Schedule process?

A

Project schedule, schedule baseline, schedule data, and project calendar.

20
Q

What is the purpose of schedule control?

A

To monitor the status of the project to update the schedule and manage changes to the schedule baseline.