Chapter 3 Flashcards
1
Q
what are the five PM process groups that all have to be included in a project
A
- initiating (defining and authorizing project)
- planning (maintaining a workable schedule)
- executing (coordinating people and resources to carry out various plans)
- monitoring and controlling
- closing
2
Q
explain PRINCE2
A
generic project management methodology with8 process groups and 45 separate subprocesses
3
Q
explain agile methods
A
adaptive product life cycle used when deliverables have a high degree of change and a high frequency of delivery (kanban, scrum, scrumban, XP, SAFE)
4
Q
explain rational unified process framework
A
iterative software development process that focuses on team productivity and anables all team members to deliver software best practives to the organization (joint application development, rapid application development)