What is project schedule management
involves the processes required to ensure timely completion of a project
what are the six main processes of project schedule management
- planning schedule management
- defining activities
- sequencing activities
- estimating activity durations
- developing the schedule
- controlling the schedule
explain planning schedule managament?
Determining policies, procedures and documentation that will be used for planning, executing and controlling the project schedule
explain defining activities
the goal of defining activities is to ensure that the project team completely understands all the work it must do as part of the project scope so they can start scheduling the work
explain sequencing activities
does a certain activity have to be finished before another can start? can the project team do several activities parallel
explain estimate activity duration
- duration: includes the actual amount of time worked on a activity
- effort: number of workdays or hours required to complete a task
- Three-point estimate: optimistic, most likely and pessimistic case
explain developing the schedule
- The main output of this process is a project schedule
explain controlling