What are the actions taken by the 1st arriving BC at Collpase operations

A
  • Establish a staging area and assign a company officer to be the Staging Area Manager until replaced by a BC
  • Transmit a preliminary report regarding the location of the ICP and the Staging Area. The dispatcher can assist in identifying a Staging Area
  • Designate a debris examination area, which should be a paved area near the site and be examined to ensure it does not contain any people remains or potential evidence before any debris is moved there
  • Ensure the ICP is located at or in the immediate vicinity of the incident site, in an area outside of the operations site and collapse zone
1
Q

The 3rd and 4th engine companies should

A

Take separate hydrants on separate mains and position at the rear of the collapsed structure

2
Q

1st alarm Engine company responsibilities starting form the highest priority

A
  • Extinguish active fire in the affected building & surrounding debris
  • Protect exposures
  • Extinguish burning vehicles within the vicinity of the collapse
  • If no fire stretch precautionary 2 1/2 line
  • If terrorist event 2 1/2 line located between two apparatus for protection
3
Q

What engine company ensures 3 1/2 line for TL supply

A

2nd engine ensures

1st engineer should CONSIDER this line

4
Q

What engines in the 1st alarm may perform CFRD

A

All but 1st due engine

5
Q

What Engines arriving on the 1st alarm at a Collapse may assist in the removal of lightly buried victims

A

3rd and 4th due engines

6
Q

When is a 10-60 transmitted for a Major Response

A

If collapse conditions are present requiring an EXTENSIVE RESCUE OR SEARCH the signal 10-60 must be transmitted and the Collapse Rescue Plan implemented

7
Q

While operating at a collapse of a building under construction the 1st arriving ladder officer is trying to obtain information about previous conditions pertaining to the building involved. Who should he seek out

A

Construction Manager

Site Safety Manager

8
Q

FEMA Standard signaling

1) Cease operations
2) Evacuate area
3) Resume operations

A

Cease operations - 1 long blast 3 seconds long
Evacuate area - 3 short blasts 1 second each
Resume operations - 1 long blast and 1 short blast

9
Q

What members of the FDNY may operate Con Ed Vacuum trucks in conjunction with Con Ed when directed by the IC

A

Trained members of SOC

10
Q

The 5 stages of the collapse rescue plan in order are

A

1) Reconnaissance
2) Accounting for and removal of surface victims
3) Search of voids
4) Selected debris removal and tunneling
5) General debris removal

11
Q

Wen is general debris removal started

A

After all other methods have been employed, people are still missing and their location is unknown. The phase is begun when it is certain that their are no other survivors, all voids have been searched, and the selected debris removal and tunneling demonstrates there is no chance for survival for the missing victims

12
Q

While operating at a collapse scene you notice a V with a circle around it and a horizontal line thru the middle of the V. What does this mean

A

The confirmed victim is deceased

13
Q

What unit is responsible for water supply

A

1st arriving Engine company

14
Q

What units is responsible to ensure a 3 1/2 line is stretched to the 1st tower ladder at a collapse operation

A

2nd arriving engine company

15
Q

What units can assist in the removal of lightly buried victims at a collapse operation and also perform CFRD duties

A

3rd and subsequent arriving engines

16
Q

What unit shall immediately begin the process of controlling gas, electric and water services at a collapse operation

A

2nd arriving ladder company

17
Q

If dangerous void entries or tunneling operations are to be made at a collapse operation, a _________ should be relocated to quarters near the incident or assigned to the staging area for rapid intervention of members if a secondary collapse occurs

A

3rd Rescue Company

18
Q

At collapse operations where do Tower Ladders position

A

To cover the building and exposures

Out of the collapse zone

19
Q

At collapse operations where do the aerial ladders position

A

Aerial ladder only near front if 100 foot reach is needed

20
Q

Position of the 1st and 2nd engine at collapse operations

A

On hydrants outside of the block unless the Stang is needed

21
Q

What is the position of 2nd alarm engine companies

A

Seal off the street

22
Q

Procedure for a collapse by the chief

A
Transmit a 10-60
Preliminary report
Command Post & Staging Area locations
Transmit 2nd Alarm if there is fire
Make sure TL response 
EMS triage area
23
Q

What utility is turned off 1st and what company is responsible to turn off the utilities

A

Gas is turned off 1st

2nd due ladder responsible for utilities

24
Q

Collapse Rescue Plan as per Dunn

A

Secure the area - have PD restrict access
Survey for victims
Utilities off - gas 1st
Immediate rescue if surface victims
Explore accessible voids
Time out - withdraw firefighters - reevaluate
Select debris removal
General debris removal - Rescue and SSL only