CONSTRUCTION Flashcards
(60 cards)
- Find the swell of a soil that weighs 2800
lb/cu yd (1661 kg/m3) in its natural state and 2000 lb/cu yd (1186 kg/m3) after excavation.
40%
Find the shrinkage of a soil that weighs 2800 lb/cu yd (1661 kg/m3) in its natural state and 3500 lb/cu yd (2077 kg/m3) after compaction.
20%
A soil weighs 1960 lb/LCY (1163 kg/LCM), 2800 lb/BCY (1661 kg/BCM), and 3500 lb/CCY (2077 kg/CCM). (a) Find the load factor and shrinkage factor for the soil. (b) How many bank cubic yards (BCY) or meters (BCM) and compacted cubic yards (CCY) or meters (CCM) are contained in 1 million loose cubic yards (593,300 LCM) of this soil?
(a) Load Factor = 0.70, Shrinkage
Factor = 0.80 (b) Bank Volume = 700,000
BCY or 415,310 BCM, Compacted Volume =
560,000 BCY or 332,248 BCM
Find the base width and height of a triangular spoil bank containing 100 BCY (76.5 BCM) if the pile length is 30 ft (9.14 m), the soil’s angle of repose is 37°, and its swell is 25%.
B = 7.45 m, H = 2.80 m
Find the base diameter and height of a conical spoil pile that will contain 100 BCY (76.5 BCM) of excavation if the soil’s angle of repose is 32° and its swell is 12%
D = 10.16 m, H = 3.17 m
Estimate the volume of excavation required (bank measure) for the basement shown in Figure 3. Values shown at each corner are depths of excavation. All values are in feet (m).
146.6 BCM
Find the volume (bank measure) of
excavation required for a trench 3 ft (0.92 m) wide, 6 ft (1.83 m) deep, and 500 ft (152 m) long. Assume that the trench sides will be approximately vertical.
255 BCM
Find the volume of excavation required for the area shown in Figure 4. The figure at each grid intersection represents the depth of cut at that location. Depths in parentheses represent meters.
14,596 BCM
Estimate the actual bucket load
in bank cubic yards for a loader bucket whose heaped capacity is 5 cu yd (3.82 m3). The soil’s bucket fill factor is 0.90 and its load factor is
0.80.
2.75 BCM
Find the expected production in loose cubic yards (LCM) per hour of a small hydraulic excavator. Heaped bucket capacity is 3⁄4 cu yd (0.57 m3). The material is sand and gravel with a bucket fill factor of 0.95. Job efficiency is 50 min/h. Average depth of cut is 14 ft (4.3 m). Maximum depth of cut is 20 ft (6.1 m) and average swing is 90
113 LCM/h
Find the expected production in loose cubic yards (LCM) per hour of a 3-yd (2.3-m3) hydraulic shovel equipped with a front-dump
bucket. The material is common earth with a bucket fill factor of 1.0. The average angle of swing is 75° and job efficiency is 0.80.
290 LCM/h
Determine the expected dragline
production in loose cubic yards (LCM) per hour based on the following information: Dragline size = 2 cu yd (1.53 m3)
Swing angle = 120°
Average depth of cut = 7.9 ft (2.4 m)
Material = common earth
Job efficiency = 50 min/h
Soil swell op = 25%
165 LCM/h
Estimate the production in loose cubic yards per hour for a medium-weight clamshell excavating loose earth. Heaped bucket capacity is 1 cu yd (0.75 m3). The soil is common earth with a bucket fill factor of 0.95. Estimated cycle time is 40 s. Job efficiency is estimated at 50 min/h.
53 LCM/h
A wheel tractorscraper weighing 100 tons (91 t) is being operated on a haul road with a tire penetration of 2 in. (5 cm). What is the total resistance (lb and kg) and effective grade when the scraper is ascending a slope of 5%; the scraper is descending a slope of 5%
9,100 kg, 10%
A wheel tractor-scraper weighing 100 tons (91 t) is being operated on a haul road with a tire penetration of 2 in. (5 cm). What is the total resistance (lb and kg) and effective grade when the scraper is descending a slope of 5%?
0 kg, 0%
A crawler tractor weighing
80,000 lb (36 t) is towing a rubber-tired scraper weighing 100,000 lb (45.5 t) up a grade of 4%. What is the total resistance (lb and kg) of the combination if the rolling resistance factor is 100 lb/ton (50 kg/t)?
5,535 kg
A four-wheel-drive tractor weighs 44,000 lb (20,000 kg) and produces a maximum rimpull of 40,000 lb (18,160 kg) at sea level. The tractor is being operated at an altitude of
10,000 ft (3050 m) on wet earth. A pull of 22,000 lb (10,000 kg) is required to move the tractor and its load. Can the tractor perform under these conditions? Use Equation 8 to estimate altitude deration
No, because the maximum pull as
limited by traction is less than the required pull
Use the performance curve of Figure 1 to determine the maximum speed of the tractor when the required pull (total resistance) is 60,000 lb (27,240 kg).
2.4 km/h
Using the performance curve of Figure 2, determine the maximum speed of the vehicle if its gross weight is 150,000 lb (68,000 kg), the
total resistance is 10%, and the altitude derating factor is 25%.
10 km/h
A power-shift crawler tractor has a rated blade capacity of 10 LCY (7.65 LCM). The dozer is excavating loose common earth and pushing it a distance of 200 ft (61 m). Maximum reverse speed in third range is 5 mi/h (8 km/h). Estimate the production of the dozer if job efficiency is 50
min/h
271 LCM/h
Estimate the hourly production in loose volume (LCY and LCM) of a 31/2-yd (2.68-m3) wheel loader excavating sand and gravel (average material) from a pit and moving it to a stockpile. The average haul distance is 200 ft (61 m), the effective grade is 6%, the bucket fill factor is 1.00, and job efficiency is 50 min/h
168 Lm3/h (Actual Board: 178 Lm3/h)
Estimate the production of a single-engine two-axle tractor scraper whose travel-time curves are shown in Figures 4 and 5 based on the following information:
Maximum heaped volume = 31 LCY (24 LCM)
Maximum payload = 75,000 lb (34,020 kg)
Material: Sandy clay, 3200 lb/BCY (1898 kg/BCM), 2650 lb/LCY (1571 kg/LCM), rolling resistance 100 lb/ton (50kg/t)
Job efficiency = 50min/h
Operating conditions = average
Single pusher
Haul route:
Section 1. Level loading area
Section 2. Down a 4% grade, 2000 ft (610 m)
Section 3. Level dumping area
Section 4. Up a 4% grade, 2000 ft (610 m)
Section 5. Level turnaround, 600 ft (183 m)
192 BCM/h
The estimated cycle time for a wheel
scraper is 6.5 min. Calculate the number of pushers required to serve a fleet of nine scrapers using single pushers. Determine the result for both backtrack and chain-loading methods.
2 and 3
Find the expected production of the
scraper fleet of Example 10 if only one pusher is available and the chain-loading method is used. Expected production of a single scraper assuming adequate pusher support is 226 BCY/h (173 BCM/h)
1,112 BCM/h