COST MANAGEMENT Flashcards

(32 cards)

1
Q

Plan Cost Management

A

Establishes guidelines for managing, monitoring, and controlling project costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Basis of Estimates

A

Documents details about how cost estimates were made, including assumptions, constraints, and risk considerations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Alternatives Analysis in Cost Management

A

Used to compare costs of different options (e.g., purchasing vs. renting equipment).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Definitive Estimate Range

A

Most accurate, with a range of -5% to +10%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Accuracy vs. Precision in Cost Estimation

A

Accuracy is the correctness of the estimate, while precision is the closeness of multiple estimates to each other.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Experience and Estimation

A

Increases both accuracy and precision of cost estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Decision-Making Techniques in Estimation

A

Involves team members in the cost estimation process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Determine Budget Process

A

Aggregates costs and reserves to establish the project budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost Aggregation

A

Rolling up costs from activities to work packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project Manager’s Role in Cost Baseline

A

Responsible for monitoring and controlling costs according to the baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Project Manager’s Role in Cost Management

A

Monitoring expenses and identifying cost-saving opportunities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Management Reserves

A

Cover unpredictable risks and are included in the Project Budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Management Reserves and Project Manager’s Responsibility

A

Managing within the approved Cost Baseline and reporting major risks or issues.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Contingency Reserve

A

Allocated funds within the Cost Baseline to address identified risks and uncertainties during project execution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Earned Value Analysis (EVA)

A

Monitors and controls schedule and cost performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Cost Variance (CV) Formula

A

EV - AC (Earned Value minus Actual Cost).

17
Q

Schedule Variance (SV) Formula

A

EV – PV (Earned Value minus Planned Value).

18
Q

Cost Performance Index (CPI) Formula

A

EV / AC (Earned Value divided by Actual Cost).

19
Q

Schedule Performance Index (SPI) Formula

A

EV / PV (Earned Value divided by Planned Value).

20
Q

Performance Measurement Baselines in EVA

A

Used to compare actual results with baseline values.

21
Q

Reserve Analysis in Control Costs

A

Checks the status of contingency and management reserves.

22
Q

Cost Management Plan

A

Guides cost control activities within the project management plan.

23
Q

Probabilistic Estimate

A

Estimating costs with probabilities within a range.

24
Q

Lightweight Estimation Methods

A

Used for high-level cost estimates in Agile projects.

25
Relative Estimation
Based on comparing estimates with other estimations.
26
Detailed Documentation in Basis of Estimates
Includes assumptions and constraints for reliability and accuracy.
27
Leveraging Team Experience for Estimation
Encourages collaboration among team members of different experience levels.
28
Nominal Group Technique in Estimation Disagreements
Facilitates consensus-building and balanced estimates.
29
Cost Analysis for Budget Discrepancies
Conducting detailed analysis to understand higher budget allocations.
30
Change Requests in Control Costs
Created when corrective or preventive actions are needed.
31
Importance of Cost Management Projects
Ensures alignment with the approved budget and prevents overruns.
32
Transparency in Cost Management
Informing upper management and other key stakeholders about budget discrepancies and proposing solutions.