Cost (week 4) Flashcards
(16 cards)
What is a budget?
Estimate of income and expenditure for a set period of time
What are resources?
People, equipment, materials or services required for an activity
What is earned value management?
Technique for measuring project performance & progress,
Combines measurement of scope, schedule & cost,
Involves PV and EV
What are fixed costs? Give examples.
Costs that don’t change with the time line of project
E.g. head office bills, wages/salaries for permanent staff, finance, leasing costs
What are indirect costs? Give examples.
Costs that are spread against many projects, can’t be linked to one project
E.g. project manager, project accountant
What are variable costs? Give examples.
Costs that change during life cycle of project
E.g. labour, plant, materials, sub-contractors, site management
What are direct costs? Give examples.
Costs that are directly attributable to project
E.g. concrete, concreter, concrete pump
What are the steps of Cost Management?
- Plan cost management
- Estimate costs
- Determine budget
- Control costs
What is ROM?
Rough Order of Magnitude (preliminary estimate): used in preliminary planning, assists go/no go decisions, low level of accuracy
What is Detailed Cost Estimate?
Increased accuracy, used to define tasks & schedules, based on systems and methods of measurement
Describe Preliminary Estimate (ROM). What is the margin of error?
- 20-25% margin of error
- early planning stages
- systems based WBS
- feasibility focus
- large contingency
- low confidence
Describe Intermediate Estimate. What is the margin of error?
- 10-15% margin of error
- schematic design & development stage
- focus on systems, alternatives & comparisons
- begin migration from systems to resources
- frequently updated
- gradual reduction of contingency
Describe Final Estimate. What is the margin of error?
- 2-3% margin of error
- for bidding, construction and control
- multiple bidders, comparisons of major tasks & systems
- very detailed take-offs and specifications
- contingency reduced
- post-contract data can be used for future projects
What is PV and what is it used for?
PV: planned value
Used for Budget Cost of Work Schedule (BCWS)
What is EV and what is it used for?
EV: earned value
Used for Budgeted Cost of Work Performed (BCWP)
What are BCWS and BCWP?
BCWS: budgeted cost of work scheduled
BCWP: budgeted cost of work performed