Stakeholders & Communication (week 11) Flashcards
(10 cards)
What are the tools & techniques for identifying stakeholders?
- Stakeholder analysis
- Meetings
- Expert judgement
- Environmental factors
- Classification
Describe prioritising stakeholders.
Level of power vs. Level of interest
- High vs. high: manage closely
- High vs. low: keep satisfied
- Low vs. high: keep informed
- Low vs. low: monitor
What does the Stakeholder Register comprise of?
- name & contact details
- role in the project
- type of stakeholder
- reporting lines
What are the steps of Communication Management?
- Plan
- Manage
- Control
What are the types of communcation?
- internal/external
- formal/informal
- vertical/horizontal
- official/unofficial
- written/oral
- verbal/nonverbal
What is the formula for communication channels?
n(n-1)/2
What is the communication model?
Encode -> Transmit message -> Decode ->Acknowledge -> Feedback/response
What are the critical items for a Communication Plan?
- stakeholder communication requirements
- information and reason for distribution
- time frame / frequency of distribution
- receipt / acknowledgement requirements
- responsibility for communication
- methods used to convey information
- escalation process (management chain)
- glossary of common terminology
- flow charts
What is Project Governance?
The management framework within which project decisions are made. The role of project governance is to provide a decision making framework that is logical, robust and repeatable. The alignment of the project with stakeholders’ needs & objectives, and business strategy. Fits within the larger context of the portfolio, program or organisation.
What does Project Governance include?
- documented policies
- procedures & standards
- stakeholder management
- communication plan