What is the title of CPS 230?
Operational Risk Management
Which regulator set the regulatory requirement known as CPS 230?
APRA
What are the general goals of CPS 230?
Strengthening operational resilience & reducing disruption to customer, company & country
What are the three main expected outcomes of CPS 230?
What are the 3 key dates for NAB regarding CPS 230?
What 2 key things must we do to fundamentally shift how we manage Critical Operations?
How many Critical Operations does NAB have?
17
Regarding Critical Operations, what are some workstream highlights completed in April?
Why are we mobilising Critical Operations? (6 steps)
What activities will CO owners be completing in April?
What activities will CO owners be completing in May?
What activities will CO owners be completing in June?
What activities will CO owners be completing in August?
What activities will CO owners be completing in September?
What activities will CO owners be completing in October?
What 5 CPS 230 features have already been completed?
When was Identify Critical Operations completed?
Oct 23
When was Identify CO Owners completed?
Dec 23
When was Identify CO processes completed?
Feb 24
When are the two CO drops?
April and June 24
When will CO reporting be delivered?
August 24