Developing Schedule Flashcards

(11 cards)

1
Q

what 3 things does a developing schedule need to have

A
  • a project network diagram
  • activity duration estimates
  • understanding of critical path method
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what does a developing schedule determine

A
  • start and finish for all project activities, taking into account the activity
    sequences, activity durations, resource requirements and schedule constraints
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

how to calculate earliest start (ES) and finish (EF) of an activity

A

ES = Maximum EF value from immediate predecessor(s)
EF = ES + Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

how to calculate latest start (LS) and finish (LF) of an activity

A

LF = Minimum (or lowest) LS value from immediate successor(s)
LS = LF - Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is the total float of an activity

A
  • the amount of time an activity can be delayed without delaying the overall project duration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

how to calculate total float

A

= LS – ES or LF – EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is the total float of critical activities

A
  • 0
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what is a critical path

A
  • the line of critical activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is free float

A
  • the amount of time an activity can be delayed without delaying the early start of any immediate successor activity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

how to determine free float of an activity

A

= ES of successor – EF of predecessor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly