Earned value Analysis Flashcards

(17 cards)

1
Q

PV
(Planned Value - Definition)

A

The authorized budget assigned to scheduled work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV

A

Earned Value
EV = sum of planned value of completed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC

A

Actual Cost
of work completed to a point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC

A

Budget at Completion
Sum of all budgets for the work to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV (Cost Variance)

A

CV = EV - AC

Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV (Schedule Variance)

A

SV = EV - PV

Positive = Ahead of schedule
Neutral = On schedule
Negative = Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

VAC (Variance at Completion)

A

VAC = BAC - EAC

Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPI (Cost Performance Index)

A

CPI = EV / AC
Agile CPI = Completed Features value / Actual costs to date

Greater than 1.0 = Under planned cost
Exactly 1.0 = On planned cost
Less than 1.0 = Over planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SPI (Schedule Performance Index)

A

SPI = EV / PV
SPI = Completed Features / Planned Features
SPI = ES / AT (Earned schedule / Actual time)

Greater than 1.0 = Ahead of schedule
Exactly 1.0 = On schedule
Less than 1.0 = Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC (Estimate at Completion)
(when no change to plan, CPI is constant going forward)

A

EAC = BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

EAC (Estimate at Completion)
(Atypical, cost deviated but expect to complete as planned)

A

EAC = AC + BAC - EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

EAC (Estimate at Completion)
(Flawed - plan no longer valid)

A

EAC = AC + Bottom-up ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EAC (Estimate at Completion)
(If both CPI and SPI influence the remaining work)

A

EAC = AC + [(BAC - EV)/(CPI * SPI)]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

ETC (Estimate to Complete)
(assuming work proceeds on plan)

A

ETC = EAC - AC
ETC = (BAC - EV)/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

ETC (Estimate to Complete)
(reestimate remaining work from the bottom up)

A

ETC = Reestimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

TCPI (To Complete Performance Index)
(efficiency that must be maintained in order to complete on plan)

A

TCPI = (BAC - EV)/(BAC - AC)

Greater than 1.0 = Harder to complete
Exactly 1.0 = Same to complete
Less than 1.0 = Easier to complete

17
Q

TCPI (To Complete Performance Index)
(efficiency that must be maintained in order to complete the current EAC)

A

TCPI = (BAC - EV)/(EAC - AC)

Greater than 1.0 = Harder to complete
Exactly 1.0 = Same to complete
Less than 1.0 = Easier to complete