Formulas Flashcards
PERT
Aka beta distribution or weighted average
O+(4 x R)+P/6 = PERT
Standard Deviation
P - O/6
Cost Variance
CV = EV - AC
Schedule Variance
SV = EV - PV
Cost Performance Index
CPI = EV / AC
Schedule Performance Index
SPI = EV/PV
Estimate at Completion
EAC = Budget at Completion/CPI
Estimate to Complete
ETC = EAC - AC
Variance at Completion
VAC = BAC - EAC
To Complete Performance Index
TCPI = ( BAC- EV)/(BAC - AC)
Present Value Formula
PV = FV/(1+R)n
Communication Channels
N(N-1)/2
Expected Monetary Value
EMV = Probability / MV of impact
Point of Total Assumption
PTA = ((Ceiling Price - Target Price)/Buyers Share) +Target Cost
Future Value
FV = PV x (1+R)n
Net Present Value
(CF1/(1+r)) x (CF2/(1+r)) - Investment
Early Finish
Early finish/EF = earliest start + duration – 1
Late Start
Late Start/LS = LF – duration + 1.
Standard depreciation
(cost of assets – scrap value)/useful life
BAC
BAC = estimated cost + contingency reserves + management reserves.
Planned Value
PV = % of work completed x BAC
Earned Value
EV = % of work completed x BAC
Expected Present Value
EPV = Probability of PV x PV
Rolled Throughput yield
RTY = Y1 x Y2 x Y3 x….