Formulas Flashcards

1
Q

PERT

A

Aka beta distribution or weighted average
O+(4 x R)+P/6 = PERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Standard Deviation

A

P - O/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Variance

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule Variance

A

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Performance Index

A

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Performance Index

A

SPI = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate at Completion

A

EAC = Budget at Completion/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate to Complete

A

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Variance at Completion

A

VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

To Complete Performance Index

A

TCPI = ( BAC- EV)/(BAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Present Value Formula

A

PV = FV/(1+R)n

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Communication Channels

A

N(N-1)/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Expected Monetary Value

A

EMV = Probability / MV of impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Point of Total Assumption

A

PTA = ((Ceiling Price - Target Price)/Buyers Share) +Target Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Future Value

A

FV = PV x (1+R)n

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Net Present Value

A

(CF1/(1+r)) x (CF2/(1+r)) - Investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Early Finish

A

Early finish/EF = earliest start + duration – 1

18
Q

Late Start

A

Late Start/LS = LF – duration + 1.

19
Q

Standard depreciation

A

(cost of assets – scrap value)/useful life

20
Q

BAC

A

BAC = estimated cost + contingency reserves + management reserves.

21
Q

Planned Value

A

PV = % of work completed x BAC

22
Q

Earned Value

A

EV = % of work completed x BAC

23
Q

Expected Present Value

A

EPV = Probability of PV x PV

24
Q

Rolled Throughput yield

A

RTY = Y1 x Y2 x Y3 x….

25
Activity duration
Work = duration/days x units/hours
26
Safety margin
1/2 way between average and worst
27
Ceiling Price
Ceiling Price is: (Target Cost + Buyer’s Share of the cost overruns + Seller’s Target Profit or Fixed Fee).
28
Target Price
Target Price will be: (Target Cost + Seller's Target Profit or Fixed Fee)
29
Cost Overrun
Cost Overrun = Actual Cost – Target Cost
30
Buyer's share of cost overrun
Buyer’s share of Cost overrun = Buyer’s ratio x cost overrun
31
Seller's share of cost overrun
Seller’s share of Cost overrun = seller’s ratio x cost overrun
32
Payback period
Investment / periodic cash flow
33
Finding slack for a single activity not on the critical path
Critical path days – activity path days = slack for the activity.
34
Return on Investment
ROI = Financial value - project cost / project cost x 100
35
Total Float
Using any activity not on the critical path. Late finish date - Early finish date OR Sum of critical path days - sum of non critical path days
36
Free float
For a single task: ES of the successor activity - EF of the current activity - 1
37
burn rate
Actual Cost/ Earned Value
38
Probability of occurrence
Prob of Oc = # of favorable events that can occur / # of total events that can occur
39
triangular distribution in 3 point estimating
Aka simple averages. = O+P+R / 6
40
Throughput yield
of quality products / total # of products