Glossary 2 Flashcards
What is Earned Value (EV)?
The estimated (monetary) value of the work accomplished expressed in terms of the budget authorized for that work. It is also referred to as the budgeted cost of work performed (BCWP).
What is Planned Value (PV)?
The authorized budget assigned to scheduled work.
What is a Control Account?
A management control point in the WBS where Earned Value measurements take place. It is also known as a Cost Account.
Define Earned Value Management (EVM).
A project management methodology that integrates scope, schedule and cost to measure project performance and progress in an objective manner.
What are Activity Attributes?
Additional details to describe an activity, such as activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
What is an Activity List?
A list of project activities that shows the activity description, activity identifier and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
What is an Approved Change Request?
A change request that has been processed through the integrated change control process and approved.
What is a Change Request?
A formal proposal to modify any document, deliverable, or baseline. It may include corrective actions, preventive actions, defect repairs, and updates to project documentation and plans.
What is a Communications Management Plan?
A component of the project, program, or portfolio management plan that describes how, when, and by whom information about the project will be administered and disseminated.
Define Contract.
A mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.
What is a Cost Management Plan?
A component of a project or program management plan that describes how costs will be planned, structured, and controlled.
What is a Cost Baseline?
The approved time-phased budget of the project (excluding any management reserves) that is used to compare actual costs to planned costs in order to determine variance and need for preventive or corrective action.
What is a Deliverable?
Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.
What is an Estimate?
A quantitative assessment of the likely amount or outcome of a variable, such as project costs, resources, effort, or durations. It should always include some indication of accuracy (e.g., ± x percent).
What is Estimate at Completion (EAC)?
The expected total cost of completing all the work on a project expressed as the sum of the actual cost to date and the estimate to complete.
What is Estimate to Complete (ETC)?
The expected cost to complete all the “remaining work” on a project.
What is a Resource Management Plan?
A component of the project management plan that describes how project resources are acquired, allocated, monitored, and controlled.
What is an Input?
Any item, whether internal or external to the project, which is required by a process before that process proceeds. May be an output from a predecessor process.
What are Lessons Learned?
The knowledge gained during a project which shows how project events were addressed or should be addressed in the future with the purpose of improving future performance. They can be identified at any point during the project.
What is an Output?
A product, result, or service generated by a process.
What are Work Performance Reports?
The physical or electronic representation of work performance information compiled in project documents, intended to generate decisions, actions, or awareness.
What are Procurement Documents?
The documents utilized in bid and proposal activities, including Invitation for Bid, Invitation for Negotiations, Request for Information, Request for Quotation, Request for Proposal and seller’s responses.
What is a Procurement Management Plan?
A component of the project or program management plan that describes how a project team will acquire goods and services from outside of the performing organization.
What is a Project Calendar?
A calendar of working and non-working days for a project. It typically defines holidays, weekends, and shift hours.