Medium Difficulty 2 Flashcards
What is Early Start Date (ES)?
In the critical path method, the earliest possible date on which a schedule activity can start without violating any schedule constraint.
What is Late Finish Date (LF)?
In the critical path method, the latest possible date that a schedule activity can complete without delaying the project or violating any schedule constraint.
What is Late Start Date (LS)?
In the critical path method, the latest possible date that a schedule activity can begin without delaying the project or violating any schedule constraint.
What is a Near-Critical Activity?
A schedule activity that has low total float.
What is Budget at Completion (BAC)?
The budget for all the work on the project. It is also the total planned value for the project.
What is Cost Performance Index (CPI)?
A measure of cost efficiency on a project. It is the ratio of earned value (EV) to actual cost (AC).
What is Cost Variance (CV)?
It is the amount of budget deficit or surplus at a given point in time, and is expressed as the difference between earned value (EV) and actual cost (AC).
What is a Schedule Performance Index (SPI)?
A measure of schedule efficiency expressed as the ratio of Earned Value (EV) to Planned Value (PV).
What is Schedule Variance (SV)?
A measure of schedule performance expressed as the difference between the Earned Value (EV) and the Planned Value (PV).
What is To-Complete-Performance-Index (TCPI)?
The cost performance that must be achieved on the remaining work to meet a BAC (or EAC) target. It is the ratio of “remaining work” to the “funds remaining”.
What is Actual Cost (AC)?
The “actual” cost incurred for the work accomplished. It is also referred to as the actual cost of work performed (ACWP).
What is Earned Value (EV)?
The estimated (monetary) value of the work accomplished expressed in terms of the budget authorized for that work. It is also referred to as the budgeted cost of work performed (BCWP).
What is Planned Value (PV)?
The authorized budget assigned to scheduled work.
What is a Control Account?
A management control point in the WBS where Earned Value measurements take place. It is also known as a Cost Account.
Define Earned Value Management (EVM).
A project management methodology that integrates scope, schedule and cost to measure project performance and progress in an objective manner.
What are Activity Attributes?
Additional details to describe an activity, such as activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
What is an Approved Change Request?
A change request that has been processed through the integrated change control process and approved.
What is a Change Request?
A formal proposal to modify any document, deliverable, or baseline. It may include corrective actions, preventive actions, defect repairs, and updates to project documentation and plans.
What is a Communications Management Plan?
A component of the project, program, or portfolio management plan that describes how, when, and by whom information about the project will be administered and disseminated.
Define Contract.
A mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.
What is a Cost Management Plan?
A component of a project or program management plan that describes how costs will be planned, structured, and controlled.
What is a Cost Baseline?
The approved time-phased budget of the project (excluding any management reserves) that is used to compare actual costs to planned costs in order to determine variance and need for preventive or corrective action.
What is Estimate at Completion (EAC)?
The expected total cost of completing all the work on a project expressed as the sum of the actual cost to date and the estimate to complete.
What is Estimate to Complete (ETC)?
The expected cost to complete all the “remaining work” on a project.