Name a tool or technique which is used in all Integration processes.
Expert Judgment
When is Contract an input to the Develop Project Charter process?
When the project is being done for an external customer.
Which process produces the Scope Management Plan?
Plan Scope Management
Which process produces the Requirements Management Plan?
Plan Scope Management
Which process generates the Work Performance Data?
Direct and Manage Project Work
Which Project Integration Management processes use Project Management Information System as a tool?
- Direct and Manage Project Work - Manage Project Knowledge (under Information Management technique) - Monitor and Control Project Work
Which system is used for recording change requests?
Configuration Management System (which is a part of the Project Management Information System)
In which processes are inspections performed?
- Validate Scope - Control Quality - Control Procurements
Why is requirements documentation needed for scope validation?
Deliverables are verified against the requirements and acceptance criteria specified in the requirements documentation.
In which process are prototypes useful?
Collect Requirements
Which is the only initiating process which uses Project Charter as an input?
Identify Stakeholders
What is SWOT Analysis used for in the context of project management?
Identifying risks (SWOT Analysis is a technique for the Identify Risks process)
How is Reserve Analysis used in managing risks?
Reserve Analysis compares the amount of the contingency reserves remaining to the amount of risk remaining at any time in the project in order to determine if the remaining reserve is adequate. It is a technique used in the Monitor Risks process.
Which technique is used for measuring deviation from baseline plans in order to determine the need for preventive or corrective actions?
Variance Analysis
Project Charter is an input to which processes (name any 4)?
- Develop Project Management Plan - Plan Scope Management - Collect Requirements - Define Scope - Plan Schedule Management - Plan Cost Management - Plan Risk Management - Identify Stakeholders; and more…
Name the Process Groups which have the Project Management Plan or one of its subsidiary plans as an input to all their processes.
- Executing - Monitoring and Controlling - Closing
What are the two key items that you need in order to collect project requirements?
- Project Charter - Stakeholder Register
Which two project management processes use the Decomposition technique?
- Create WBS - Define Activities
List the project management processes that use WBS as an input.
WBS is not an input to any process! However, Scope Baseline, which includes the Project Scope Statement, WBS, and WBS Dictionary, is an input to several processes such as Define Activities, Estimate Costs, Determine Budget, Identify Risks, and Perform Qualitative Risk Analysis.
What are the two main outputs of the Validate Scope process?
- Accepted Deliverables - Change Requests
Which processes employ the Bottom-up Estimating technique?
- Estimate Activity Durations - Estimate Costs - Estimate Activity Resources
What is the purpose of Project Schedule Network Diagrams?
To develop (project) schedule.
List the processes that have Resource Calendars as output.
- Control Schedule - Acquire Resources - Develop Team - Conduct Procurements
List the processes that use Resource Breakdown Structure as an input.
- Manage Project Knowledge - Estimate Activity Durations - Control Resources