Lecture 12 - Managing Risk for Software Project Flashcards

1
Q

What is risk deciphered as? (3)

A
  • Lack of information
  • Lack of time
  • Lack of control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the formula for calculating Risk exposure?

A

Risk exposure = Impact x Probability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is risk?

A

Something identified in advance that may or may not happen and can have positive or negative impact on project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are positive risks know as?

A

Opportunities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

TF: Project Management does not focus on threats (negative risks)

A

False. It does

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Lack of knowledge about an event that reduces confidence in conclusions drawn from data is an…

A

Uncertainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is risk tolerance?

A

Level of risk acceptable to an individual or organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is risk threshold?

A

Specific point at which risk becomes unacceptable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Risk averse?

A

Someone who does not want to be negatively impacted by threats

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

TF: Risk tolerance is considered the opposite of risk averse

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the ISO/IEC definition of risk?

A

The combination of the probability of an event and its negative consequence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the ISO/IEC definition of risk category?

A

A class or type of risk (technical, legal, safety, schedule, etc.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TF: Risk category is a characterization of a source of risk

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the risk management processes? (2)

A
  • Risk assessment
  • Risk control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the steps of risk assessment? (3)

A
  1. Risk identification
  2. Risk analysis
  3. Risk prioritization
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

TF: Risk assessment cannot be reassessed at the beginning of each iteration

A

False. It can

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is Risk identification?

A

Determines risks related to the overall project, product, and business

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the outcome of risk identification?

A

Collection of risk items

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are typical software project risk elements? (4)

A
  • Performance risk
  • Cost risk
  • Support risk
  • Schedule risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is performance risk?

A

Degree of uncertainty that the product will meet its requirements and be fit for intended use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is cost risk?

A

Degree of uncertainty that project budget will be maintained

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is support risk?

A

Degree of uncertainty that the resultant software will be easy to correct, adapt, and enhance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is schedule risk?

A

Degree of uncertainty that the project schedule will be maintained, and project will be delivered on time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are some causes of software project risks? (5)

A
  • Poor risk management practices
  • Under-defined scope/goals
  • Misunderstanding context, options, and opportunities
  • Poor time and priority management
  • Cultural inability to cut our losses
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is Risk analysis?
Assessment of the likelihood of occurrence of a risk and the impact of it on the project, product, business
26
What is qualitative assessment for the likelihood of occurrence for a risk?
The scale (low, moderate, significant, high)
27
What is quantitative assessment for the likelihood of occurrence for a risk?
Probability of occurrence
28
What is qualitative assessment for the impact on project, product, business of a risk item?
The scale (low, moderate, significant, high)
29
What is quantitative assessment for the impact on project, product, business of a risk item?
A number to represent the impact of a risk (ex: fire can cause 0.5 millions of damage in a facility)
30
What makes a risk of high concern?
If the risk has High impact and High likelihood of occurrence
31
Consider a fire which can cause 0.5 millions of damage in a facility. Let the probability of this event be 0.01. Then the risk exposure is...
RE = $0.5million x 0.01 = $5,000
32
What is risk prioritization?
Setting priorities in order to determine where to focus risk mitigation efforts
33
In risk prioritization, how do we determine the priority of each risk item in a quantitative model?
Combine the likelihood and impact
34
What are the three parts that make up Risk control?
- Risk Planning - Resolution - Risk Monitoring
35
What does the acceptance strategy in risk planning involve in risk control?
Means the project has decided not to change the project plan to deal with a risk or is unable to identify any other suitable response strategy
36
TF: Contingency plans is an example of the acceptance risk response strategy
True
37
TF: Identification of risk-trigger points is an example of the acceptance risk response strategy
True
38
TF: Using contingency allowance (time, budget, staff) is not an example of the acceptance risk response strategy
False. It is
39
What does the avoidance strategy in risk planning involve in risk control?
Changing the project plan to eliminate the risk to protect the project goals and objectives from its impacts
40
TF: Not using unfamiliar subcontractors is an example of the avoidance risk response strategy
True
41
TF: Adding resources or time to critical tasks during planning is not an example of the avoidance risk response strategy
False. It is
42
What does the transference strategy in risk planning involve in risk control?
Shifting the consequence and ownership of a risk to a third party
43
TF: Warranties and guarantees are an example of the transference risk response strategy
True
44
TF: Use of fixed-priced contract with subcontractors is an example of the transference risk response strategy
True
45
What does the mitigation strategy in risk planning involve in risk control?
Reduces the possibility and/or consequences of an adverse risk to an acceptable level
46
Adopting less complex processes is an example of what risk response strategy?
Mitigation
47
Plan for additional testing of complex elements is an example of what risk response strategy?
Mitigation
48
Using a more reliable or more stable vendor is an example of what risk response strategy?
Mitigation
49
Using a prototype in the development process is an example of what risk response strategy?
Mitigation
50
What is Risk Reduction Leverage?
The ratio of the reduction in risk exposure over the cost of the reduction
51
What is the Risk Reduction Leverage (RRL) formula?
RRL = [RE(before) - RE(after)]/cost of reduction
52
TF: An RRL value greater than 1 indicates cost effective risk reduction measures
True
53
TF: An RRL value less than 1 would indicates cost effective reduction measures
False. Indicates a non cost effective reduction measures
54
Slide 30 for RRL example
No answer slide?
55
What is the most powerful tool for determining net outcomes from both positive and negative risk events?
Decision tree analysis
56
A diagram that describes a decision under consideration and the implications of choosing one or another of the available alternatives is a...
Decision tree
57
TF: The set of outcomes for a decision tree adds up to 100%
True
58
How do you calculate the total impact for each branch of the decision tree?
EMV = P * I EMV: Expected Monetary Value P: Probability I: Impact
59
Slide 32 for Decision tree analysis technique
No answer?
60
Examining and documenting the effectiveness of risk responses in dealing with identified risks. Their root causes, and the risk management process is known as...
Project Risk Response audits
61
TF: Project risk response audits should not happen regularly
False. It should happen regularly
62
What is involved in Periodic project risk reviews? (3)
- Identification of new risks - Reassessment of current risks - Closing outdated risks
63
What are the steps of Risk Control Overview? (6)
- Identification - Analysis - Prioritization - Planning - Resolution - Monitoring
64
What are the elements that are included in Risk Monitoring/Controlling? (6)
- Risk log - ID number - Risk description - Risk owner - Action to be take - Outcome