A.Tell the vendor that you cannot accept the gifts as per company policy
B.Accept the gifts as it is a local custom, but promptly inform your manager
C.Return the gifts, because accepting them could be interpreted as a personal gain
D.Accept the gifts, as they are not very expensive
Answer: B Explanation: A project manager has the responsibility to refrain from offering or accepting inappropriate payments, gifts, or other forms of compensation for personal gain, unless it is in agreement with applicable laws or customs of the country where the project management services are being provided.
A.Managing procurement relationships, monitoring contract performance, and making changes/corrections to contracts as appropriate.
B.Procurements should be finalized prior to closing the project
C.Procurement information should be stored in a records management system
D.The project sponsor signs off on the project after the final lessons learned is complete
Answer: A Explanation: This is the definition for the Control Procurements Process, which is performed during monitoring and controlling.
A.Unidentifiable Risks
B.Residual Risks
C.Secondary Risks
D.Inherent Risks
Answer: B Explanation: Components of the risk register…include: Residual risks that are expected to remain after planned responses have been taken, as well as those that have been deliberately accepted.
A.Subject matter expert
B.Integrator
C.Encoder
D.Risk manager
Answer: B Explanation: In the project management context, integration includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully managing stakeholder expectations, and meeting requirements.
A.Costs of non conformance
B.Targets for improved performance
C.Process boundaries and process metrics
D.Continual process improvement analysis meetings during Executing
Answer: A Explanation: Costs of non conformance are rework, etc. The areas to be considered in the process improvement plan include process boundaries, process configuration, process metrics, and targets for improved performance.
A.Matrix
B.Functional
C.Projectized
D.Balanced
Answer: B Explanation: A classic functional organization… is a hierarchy where each employee has one clear superior. Staff members are grouped by specialty, such as production, marketing, engineering, and accounting at the top level.
A.Quality Function Deployment (QFD)
B.Joint Application Development (JAD)
C.Voice Of Customer (VOC)
D.Key Performance Indicators (KPI)
Answer: A Explanation: Quality Function Deployment (QFD) is an example of a facilitated workshop technique that helps determine critical characteristics for new product development. KPI is a type of performance measurement used to evaluate the success of the project. (E.g. zero defects, meets business requirements, customer satisfaction.)
A.Team-building activities
B.Ground rules
C.Interpersonal skills
D.Core team rules of conduct
Answer: B Explanation: Ground rules establish clear expectations on acceptable behavior by project team members. Early commitment to clear guidelines decreases misunderstandings and increases productivity. Discussing ground rules allows team members to discover values that are important to one another.
A.Project Management Plan
B.Contract Change Control Plan
C.Procurement Management Plan
D.Cost Management Plan
Answer: C Explanation: The procurement management plan describes how the procurement processes will be managed from developing procurement documents through contract closure. The procurement management plan can include guidance for:
A.Source selection criteria, P-I matrix
B.Staffing management plan, Communications management plan
C.Quality metrics, Quality checklists
D.Activity list, Resource Calendars, Resource Breakdown Structure, Risk Register
Answer: D Explanation: Helpful inputs. Note that risk register is included as part of the contingency reserves needed for “reserve analysis.”
A.28
B.21
C.18
D.36
Answer: D Explanation: There will be 9 people in your team (this includes 8 team members and you, the project manager). So, the number of communication channels = 9 * (9 - A) / 2 = 9 * 8 / 2 = 36.
73.All of the following are inputs for the Monitor and Control Project Work Process, except:
●
A.Project management plan, enterprise environmental factors, organizational process assets
B.Validated changes, work performance information
C.Change requests & work performance reports
D.Schedule & cost forecasts
Answer: C Explanation: These are actually outputs for this process.
A.A critical resource went on sick leave for a long period of time, which had not been anticipated earlier.
B.The cost of raw materials required for construction increased by 10%. (You had anticipated a cost increase of 12% in your project plans.)
C.In anticipation of delays, the project was crashed to decrease the duration.
D.There was four days waiting time in the curing of concrete, and work could not be done during that time.
Answer: C Explanation: Option C: This is the correct answer, because crashing of a project results in decreased duration and increased costs. This verifies the given data on CPI and SPI. Options 1 and 4: They are ruled out, because they do not verify the given data that SPI>1. Option B: This is also ruled out, because it does not verify the given data that CPI<1.
A.P-I Matrix Assessments
B.Continuous Process Improvement
C.Control Risks
D.Risk Response Analysis
Answer: C Explanation: The Control Risks is the process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.
A.Organizational process assets
B.Approved change requests
C.Project management plan
D.Change control tools
Answer: D Explanation: Change control tools are a technique used in Perform Integrated Change Control process. The activities performed during the Direct and Manage Project Work process include but are not limited to manage sellers and suppliers, create project deliverables, implement the planned methods and standards, etc.
A.Team members are often collocated.
B.There is a “home” for project team members after a project is completed.
C.You have a great deal of authority and independence.
D.Organizational units (or departments) either report directly to you or provide support services to the various projects.
Answer: B Explanation: One disadvantage of a projectized organization is that there is “no home” for the project team members once the project is completed. All the remaining features mentioned above are features of a projectized organization.
A.Perform Quality Assurance and Plan Quality Management
B.Plan Quality Management and Perform Quality Control
C.Perform Quality Control, Plan Quality Management, and Perform Quality Assurance
D.Perform Quality Assurance and Perform Quality Control
Answer: D Explanation: Quality metrics are used in the Perform Quality Assurance and Perform Quality Control processes—Not in Planning.
A.Professional and technical associations
B.Competitors
C.Consultants
D.Other units within the organization
Answer: B Explanation: Expert judgment is available from:
A.Legitimate (formal, based on position)
B.Laissez faire
C.Expert
D.Penalty
Answer: A
A. Contract change control, procurement performance reviews, payment systems
B. Performance reporting, inspections, audits
C. Claims administration, records management system
D. Procurement audits, closed procurements
Answer: D Explanation: Closed procurements is performed during the Close Procurements process.
A.Mathematical analyses like CPM, GERT, and PERT indicate the dates on which the activity can be scheduled, given resource limits and other constraints.
B.Duration compression techniques, including fast tracking and crashing, can help in decreasing the project schedule.
C.WBS classification allows for useful activity ordering and sorting.
D.The duration of the project is the sum of the duration of all the activities in the project.
Answer: D Explanation: The duration of the project should be calculated after drawing a network diagram and determining the critical path. The duration of the project is the length of the critical path and not the sum of the duration of all the tasks in the project.
A.Three Needs Theory
B.Expectancy Theory
C.Theory Y
D.Situational Leadership II Theory
Answer: B Explanation: Victor Vroom is attributed with the Expectancy Theory. People “expect” to be recognized/rewarded, so plan on how to link their performance with their desired reward. (Three Needs: David MCleland. Theory Y: Ouichi. Situational Leadership II: Hersey & Blanchard)
A.Do nothing and continue to work as before.
B.Take the appropriate person in ABC Bank into confidence and discuss this issue with her to determine what to do.
C.Disclose the evaluation criteria to your (seller) organization and help their business grow.
D.Remove yourself from the project—this is a conflict of interest.
Answer: B Explanation: Option B (best answer): This is the correct answer. Since the evaluation criteria are proprietary information of ABC Bank, it is important for you to discuss the matter directly with the appropriate person in the ABC Bank. Option A: This introduces conflict of interest as to whether to act or not in favor of your current employer. Option C: This is unethical, because proprietary information of the buyer should not be disclosed. Option D: This is an extreme step that could be taken only if required after talking to the buyer.
A..9
B.0.48
C.1.7
D..3
Answer: B Explanation: CV = EV - AC
So, EV = CV + AC = 65,000 + 125,000 = 190,000.
TCPI = (BAC-EV) / (BAC-AC)
= (250000-190000) / (250000-125000)
= 60000/125000
= 0.48