MOCK3 Flashcards
75 Q
- You recently went on an official trip to another country to discuss a business proposition with a potential vendor. The vendor took you out for lunch and offered you gifts, as it is customary in that country. You must:
A.Tell the vendor that you cannot accept the gifts as per company policy
B.Accept the gifts as it is a local custom, but promptly inform your manager
C.Return the gifts, because accepting them could be interpreted as a personal gain
D.Accept the gifts, as they are not very expensive
Answer: B Explanation: A project manager has the responsibility to refrain from offering or accepting inappropriate payments, gifts, or other forms of compensation for personal gain, unless it is in agreement with applicable laws or customs of the country where the project management services are being provided.
- All of the following relate to the Closing Process Group, except:
A.Managing procurement relationships, monitoring contract performance, and making changes/corrections to contracts as appropriate.
B.Procurements should be finalized prior to closing the project
C.Procurement information should be stored in a records management system
D.The project sponsor signs off on the project after the final lessons learned is complete
Answer: A Explanation: This is the definition for the Control Procurements Process, which is performed during monitoring and controlling.
- You have identified important risks and planned the appropriate responses. Some risks (e.g. possibility of natural disasters impacting the project) have been documented and accepted in your risk management plan. What are the remaining risks called?
A.Unidentifiable Risks
B.Residual Risks
C.Secondary Risks
D.Inherent Risks
Answer: B Explanation: Components of the risk register…include: Residual risks that are expected to remain after planned responses have been taken, as well as those that have been deliberately accepted.
- In a recent job interview, you are asked to define the most important characteristic of a project manager. Which of the following will be the best answer?
A.Subject matter expert
B.Integrator
C.Encoder
D.Risk manager
Answer: B Explanation: In the project management context, integration includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully managing stakeholder expectations, and meeting requirements.
- You have been asked to prepare a process improvement plan. You should consider all the following, except:
A.Costs of non conformance
B.Targets for improved performance
C.Process boundaries and process metrics
D.Continual process improvement analysis meetings during Executing
Answer: A Explanation: Costs of non conformance are rework, etc. The areas to be considered in the process improvement plan include process boundaries, process configuration, process metrics, and targets for improved performance.
- You are responsible for managing a project in your company but you have little authority and have to constantly report to a functional manager. To which organizational structure does your company best relate to?
A.Matrix
B.Functional
C.Projectized
D.Balanced
Answer: B Explanation: A classic functional organization… is a hierarchy where each employee has one clear superior. Staff members are grouped by specialty, such as production, marketing, engineering, and accounting at the top level.
- You are a project manager in a manufacturing company, and are developing a new product. In this context, you are conducting requirements workshop for the stakeholders to determine the product`s critical characteristics. Which technique would best be used for this purpose?
A.Quality Function Deployment (QFD)
B.Joint Application Development (JAD)
C.Voice Of Customer (VOC)
D.Key Performance Indicators (KPI)
Answer: A Explanation: Quality Function Deployment (QFD) is an example of a facilitated workshop technique that helps determine critical characteristics for new product development. KPI is a type of performance measurement used to evaluate the success of the project. (E.g. zero defects, meets business requirements, customer satisfaction.)
- You establish clear expectations regarding acceptable behavior by project team members. You believe that early commitment to clear guidelines will decrease misunderstanding and increase productivity. These expectations and guidelines are also known as:
A.Team-building activities
B.Ground rules
C.Interpersonal skills
D.Core team rules of conduct
Answer: B Explanation: Ground rules establish clear expectations on acceptable behavior by project team members. Early commitment to clear guidelines decreases misunderstandings and increases productivity. Discussing ground rules allows team members to discover values that are important to one another.
- You are in the process of determining the types of contracts to be used, need for standardized procurement documents, and ways of managing multiple providers. You can get the guidance for doing these activities through:
A.Project Management Plan
B.Contract Change Control Plan
C.Procurement Management Plan
D.Cost Management Plan
Answer: C Explanation: The procurement management plan describes how the procurement processes will be managed from developing procurement documents through contract closure. The procurement management plan can include guidance for:
- Types of contracts to be used
- Whether independent estimates will be used and if they are needed as evaluation criteria
- Managing multiple suppliers
- You are beginning the Estimate Activity Durations Process. Which of the following would be helpful?
A.Source selection criteria, P-I matrix
B.Staffing management plan, Communications management plan
C.Quality metrics, Quality checklists
D.Activity list, Resource Calendars, Resource Breakdown Structure, Risk Register
Answer: D Explanation: Helpful inputs. Note that risk register is included as part of the contingency reserves needed for “reserve analysis.”
- You are the project manager with seven team members. One more member will be joining the team after a week. What will be the number of communication channels once the new member joins your team?
A.28
B.21
C.18
D.36
Answer: D Explanation: There will be 9 people in your team (this includes 8 team members and you, the project manager). So, the number of communication channels = 9 * (9 - A) / 2 = 9 * 8 / 2 = 36.
73.All of the following are inputs for the Monitor and Control Project Work Process, except:
●
A.Project management plan, enterprise environmental factors, organizational process assets
B.Validated changes, work performance information
C.Change requests & work performance reports
D.Schedule & cost forecasts
Answer: C Explanation: These are actually outputs for this process.
- Half way through your construction project, the CPI is 0.85 and SPI is 1.25. What could be the possible reason?
A.A critical resource went on sick leave for a long period of time, which had not been anticipated earlier.
B.The cost of raw materials required for construction increased by 10%. (You had anticipated a cost increase of 12% in your project plans.)
C.In anticipation of delays, the project was crashed to decrease the duration.
D.There was four days waiting time in the curing of concrete, and work could not be done during that time.
Answer: C Explanation: Option C: This is the correct answer, because crashing of a project results in decreased duration and increased costs. This verifies the given data on CPI and SPI. Options 1 and 4: They are ruled out, because they do not verify the given data that SPI>1. Option B: This is also ruled out, because it does not verify the given data that CPI<1.
- Even after carefully performing risk management for the project, you realize that possibility of new risks occurring in the future still exists. You will be able to handle such risks if you perform:
A.P-I Matrix Assessments
B.Continuous Process Improvement
C.Control Risks
D.Risk Response Analysis
Answer: C Explanation: The Control Risks is the process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.
- Which of the following are not inputs to the Direct and Manage Project Work Process:
A.Organizational process assets
B.Approved change requests
C.Project management plan
D.Change control tools
Answer: D Explanation: Change control tools are a technique used in Perform Integrated Change Control process. The activities performed during the Direct and Manage Project Work process include but are not limited to manage sellers and suppliers, create project deliverables, implement the planned methods and standards, etc.
- You are a project manager in XYZ Company, which has a projectized organizational structure. In this environment, all of the following are true, except:
A.Team members are often collocated.
B.There is a “home” for project team members after a project is completed.
C.You have a great deal of authority and independence.
D.Organizational units (or departments) either report directly to you or provide support services to the various projects.
Answer: B Explanation: One disadvantage of a projectized organization is that there is “no home” for the project team members once the project is completed. All the remaining features mentioned above are features of a projectized organization.
- You have completed a NASA project for the launch of a weather forecasting satellite. The satellite is being tested for a specific quality metric. For which processes are quality metrics used?
A.Perform Quality Assurance and Plan Quality Management
B.Plan Quality Management and Perform Quality Control
C.Perform Quality Control, Plan Quality Management, and Perform Quality Assurance
D.Perform Quality Assurance and Perform Quality Control
Answer: D Explanation: Quality metrics are used in the Perform Quality Assurance and Perform Quality Control processes—Not in Planning.
- In projects, expert judgment will often be used throughout all the project integration processes as a common tool/technique. This can be provided by all of the following, except:
A.Professional and technical associations
B.Competitors
C.Consultants
D.Other units within the organization
Answer: B Explanation: Expert judgment is available from:
- Other units within the organization
- Consultants
- Stakeholders, including customers or sponsors
- Professional and technical associations
- Industry groups
- Subject matter experts
- In a previous project, the project manager told the team members what to do. The type of authority they likely had was:
A.Legitimate (formal, based on position)
B.Laissez faire
C.Expert
D.Penalty
Answer: A
- Which of the following would not be used during the Control Procurements Process?
A. Contract change control, procurement performance reviews, payment systems
B. Performance reporting, inspections, audits
C. Claims administration, records management system
D. Procurement audits, closed procurements
Answer: D Explanation: Closed procurements is performed during the Close Procurements process.
- All the following statements regarding the creation of duration estimates are correct, EXCEPT:
A.Mathematical analyses like CPM, GERT, and PERT indicate the dates on which the activity can be scheduled, given resource limits and other constraints.
B.Duration compression techniques, including fast tracking and crashing, can help in decreasing the project schedule.
C.WBS classification allows for useful activity ordering and sorting.
D.The duration of the project is the sum of the duration of all the activities in the project.
Answer: D Explanation: The duration of the project should be calculated after drawing a network diagram and determining the critical path. The duration of the project is the length of the critical path and not the sum of the duration of all the tasks in the project.
- Which of the following motivation theories is attributed to Victor Vroom?
A.Three Needs Theory
B.Expectancy Theory
C.Theory Y
D.Situational Leadership II Theory
Answer: B Explanation: Victor Vroom is attributed with the Expectancy Theory. People “expect” to be recognized/rewarded, so plan on how to link their performance with their desired reward. (Three Needs: David MCleland. Theory Y: Ouichi. Situational Leadership II: Hersey & Blanchard)
- The seller`s project is undertaken on contract and you are an employee of the seller. Since you earlier worked with ABC Bank, the buyer, you are aware of the evaluation criteria used in ABC Bank to select sellers. You understand this could be a potential conflict of interest situation. How do you propose to act?
A.Do nothing and continue to work as before.
B.Take the appropriate person in ABC Bank into confidence and discuss this issue with her to determine what to do.
C.Disclose the evaluation criteria to your (seller) organization and help their business grow.
D.Remove yourself from the project—this is a conflict of interest.
Answer: B Explanation: Option B (best answer): This is the correct answer. Since the evaluation criteria are proprietary information of ABC Bank, it is important for you to discuss the matter directly with the appropriate person in the ABC Bank. Option A: This introduces conflict of interest as to whether to act or not in favor of your current employer. Option C: This is unethical, because proprietary information of the buyer should not be disclosed. Option D: This is an extreme step that could be taken only if required after talking to the buyer.
- Calculate the to-complete-performance index (TCPI) of your project, given that the actual cost of your project is $125,000, cost variance is $65,000, and the budget at completion is $250,000.
A..9
B.0.48
C.1.7
D..3
Answer: B Explanation: CV = EV - AC
So, EV = CV + AC = 65,000 + 125,000 = 190,000.
TCPI = (BAC-EV) / (BAC-AC)
= (250000-190000) / (250000-125000)
= 60000/125000
= 0.48



