Module 13: Overview of monitoring and controlling projects Flashcards

1
Q

Controlling

A

Managing changes, making improvements, and taking corrective action to prevent possible problems. PM must ensure change is controlled efficiently and effectively.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Monitoring

A

Tracking changes against the project plan and baselines created during project planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project integration management

A

Control project work and ensure that change control is implemented in all areas of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Earned Value Management

A

Integrates scope, time (schedule), and cost. Start with baseline of each. Used for future comparisons. Provides performance information. PM able to see whether the project is on, behind or ahead of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Planned value

A

AKA budgeted cost of work scheduled (BCWS). Need to know budgeted cost at completion and the percentage of work completed so far.
10% complete, estimated cost = 10,000, EV = $1,000 (10% of 10,000).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Earned Value

A

AKA budgeted cost of work performed (BCWP)
% of actual work completed based on what was planned (rate of work).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Actual cost

A

AKA actual cost of work performed (ACWP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Variances

A

Schedule (SV), cost (CV), schedule performance index (SPI), cost performance index (CPI).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule variance

A

Amount ahead or behind schedule. SV = planned value (PV) - Earned value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost variance

A

measures budget deficit or surplus. CV = actual cost (AC) - earned value (EV). negative = over-budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule performance index

A

SPI (how efficiently team uses time). Ratio of EV:PV. SPI < 1 = less work completed as planned. >1 = more work completed than planned. SPI = 1, work going according to plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

CPI

A

Most important measure. How monies were used against project budget based on work completed so far. <1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project schedule managment

A

Biggest challenge a PM faces. Least amount of flexibility as it moves whether you like it or not. People get sick, vacation, and sometimes do not work out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly