Module 6: Project cost management Flashcards

1
Q

Cost management main documents

A

Cost management plan, an activity cost estimate, and a cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Components of cost management plan

A
  • Units of measure (time for human resources in days, weeks, months)
  • Acceptable level of accuracy for the cost estimates
  • control thresholds that monitor cost deviations from baseline
  • rules of performance measurement
  • earned valued management rules of performance msmt.
  • reporting formats and frequency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Steps for Cost budgeting

A

1) make estimates.
2) Use WBS dictionary, project scope statements, activity cost estimates, schedule and anything else.
3) Create baseline and gives PM a guideline for managing costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Documents used to estimate costs

A
  • Cost management plan
  • HR management plan
  • scope baseline
  • project schedule
  • risk register
    Refine estimates as time goes on.
    Define rules and how assumptions were applied.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Major costs in a project

A
  • Human (base salary, benefits, overhead)
  • Materials
  • Services
  • Facilities
  • Financing costs/fees
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost estimation techniques

A

Analogue, bottom-up, parametric, three-point estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Analogue

A

Or ‘top-down’, based on another similar project. Looks from broader perspective. Not very accurate but less expensive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Bottom-up

A

Estimating individual activities and summing them up. More accurate, very time consuming and costly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Parametric

A

uses mathematical variables to estimate. Use correct historical information that can be extrapolated. Ex: $1000/sq foot to build a house. Simplistic example, projects are much more complex and require multiple variables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

3-point estimate

A

AKA triangular distribution. Most likely (realistic work effort), optimistic (best-case scenario), and pessimistic (worst case scenario). Add and divide by 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Relative cost management

A

Instead of using a range of numbers for estimates, agile projects use. Example is T-shirt sizing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost baseline

A

Is a time based budget that is used to measure and monitor cost performance throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project roadman

A

Agile projects, helps in creating the product backlog.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Planning poker

A

Used to estimate activity/story difficulty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Affinity estimates

A

use sticky notes to determine effort within a group (XS, S, M, L, XL)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Agile costing

A

Usually top-down. More uncertainty, change change from one sprint to another. Makes short-term predictions. Based on immediate past project performance.