Can you explain how you managed change effectively under the NEC3 contract on RR framework?
Rigorous change control procedure in place, monthly cost reports reporting on the change, Weekly slots for EWNs as a topic within the weekly meetings, Weekly CE/Change meetings commercially.
What is the formal role of the quantity surveyor in any contracts you’ve used, as defined in the contract?
QS role managing the project’s financial aspects, ensuring cost control, and providing expertise in contractual matters, however we are not named in the JCT or NEC.
How did you go about establishing entitlement for a claim that you’ve received from a contractor in the past?
This involves understanding the facts, showing the cause, effect, and the contractual basis for the claim.
How did you quantify risk on the UoN project?
Assessed the potential hazards by determining their likelihood and severity, and then use a risk matrix or other methods to assign numerical values to each risk. This process helps prioritize risks and develop appropriate mitigation strategies.
How did you contribute to the risk mitigation strategy?
Contributed toward the frequent risk register reviews held on the project – quantified risk when required.