Risk Management Flashcards
(51 cards)
Who owns risk under JCT?
Apportioned between either client / contractor, will be influenced by contract selection and terms
Difference between a risk and an issue?
- Issue has already occurred / is certain to occur
- Risk is not certain to occur
Difference between a threat and an opportunity?
- Threat = negative risk
- Opportunity = positive risk
What are some risks associated with existing buildings?
- Asbestos
- Structural deterioration
- Poor workmanship
- Construction not meeting new regulations
What documents can be provided to inform contractor of risks associated with existing buildings?
- Asbestos register and management plan
- Structural survey
How can a project team reduce design risk for employer?
- Use trusted and experienced design team
- Transfer design risk in procurement (i.e. D&B, CDP)
- Effective, regular management of risk register
- Early contractor involvement (buildability input)
How do you monitor risks throughout the life cycle of your project?
- Identify, monitor cost element of risks, including planned responses and financial allowance
- Corrective action when risk materialises
- Monitor actions of risk owner to ensure mitigation strategy deployed
- Measure effectiveness of risk responses
Once project risks have been identified, how do you allocate risks to a specific ‘owner’?
- Individual / party best able to manage it
- Allocation clearly identified on risk register
What are the 4 risk categories identified in NRM for cost estimating purposes?
- Employer Change
- Employer Other (fund availability, acceleration, sequencing, special contractual arrangements)
- Design Development (change in scope, statutory/legal/planning requirements)
- Construction (access restrictions, existing buildings/conditions/surveys, statutory authority delays
What is a risk allowance?
Monetary allowance set aside on risk register to cover costs should risk be realised
How would you calculate risk allowances?
- Order of cost stage - simple % (unless detailed info available)
- Cost plan onwards - risk allowances assessed based on total cost of risk (should it be realised) and probability of occurrence
Techniques available to quantify risk?
Expected monetary value
Your client is concerned about entering into contract with preferred contractor, what can be done to alleviate cost risk through contractual mechanisms?
Retention bond, performance bond/PCG, advance payment bond, materials off site bond
How did you arrange a risk workshop on xxx project?
- Benchmarked initial risks from similar prev projects to populate risk register
- Liaised with wider design team to identify further risks
- Presented populated risk register at meeting, discuss likelihood and monetary impact to calculate expected monetary value
How did you monitor and quantify risk through design stages on one of your projects?
- Initially benchmarked risk %, comparing other projects, level of design, abnormals, procurement/tender route
- Review % at each RIBA design stage
- Produced risk register, continuously monitored throughout
- Drew down on contingencies when required
How do you calculate risk at RIBA stage 2?
- Benchmark against similar projects
- Assessed design accuracy, site abnormals, procurement and tendering strategy
What documents are included in the tender pack to inform the management of risk?
Pre-construction information (contains site location, operating hours, access route, evacuation plans, any asbestos surveys, contract details, permits required)
How do you carry out risk analysis and risk management?
- If the project is being undertaken within a wider programme of similar projects, experienced clients may have access to risk registers from previous schemes that can be used as a starting point.
- A risk management workshop can also be organised with all members of the design team coming together to identity project specific risk items.
- The risk register can be updated during the meeting and will form the basis of risk management for the project.
- These risks will be continually monitored as the project progresses.
- Identified risks can either be removed or we can aim to reduce their probably of occurring and put in mitigation measures if they do occur.
What is risk defined as?
- An uncertain event that will have an effect on the achievement of the project objectives should it occur.
- Risks are measured in terms of their likelihood (probability) and consequence (impact).
What is risk management?
- A process for identifying, assessing and responding to risks associated with the delivery of an objective such as a construction project.
- Risk management establishes a set of procedures by which risks are managed.
- It comprises an intuitive approach where project teams look to manage risk in a more proactive manner.
Can you expand on the Identify, Assess, Respond approach?
- Identification takes place after the project and its objectives have been well defined.
- A risk cannot be effectively managed before it has been identified.
- Risk identification should be carried out as early as possible.
- Assessment can be carried out to determine the probability and impact of each risk item and its effect on cost, time and performance of the project. A qualitative approach can also be undertaken to describe the risk and effect on project performance.
- Response actions aim to reduce the probability of the risk arising or to mitigate its impact should the risk arise.
What is a Risk Event?
- An event that can be predicted to at least some degree, generally based on historical data or experience and making a decision according to the probability of a particular event occurring.
What is an uncertain or unforeseen event?
- A random event that defies prediction.
Why is risk management needed in construction?
- Projects are typically complex, all have time, cost and quality targets which must be met.
- Risk is present in all projects and surveyors are routinely involved in making decisions which have a major impact on risk.
- Risk management cannot eliminate risk, but techniques can be used to reduce the impact of events that may cause failure to reach the desired targets.