Project Finance [Control and Reporting] Flashcards
(70 cards)
Related guidance to cost reporting?
Several RICS Black books:
- Cost Reporting
- Cashflow Forecasting
- Valuing Change
- Interim Valuations and Payment
- Final Account Procedures
What is the purpose of post-contract cost / financial reporting?
- Provide overview of client’s current financial commitment
- Inform client of the predicted final account costs of the project
- Can be benchmarked to initial budget and tender sum / pre contract predictions
- Give client understanding of potential savings / risks / VE additional monies required
What information would you include in a post-contract cost report?
- Summary
- Contract sum
- Instructed variations
- Anticipated variations
- Provisional sum adjustments
- VE options
- Anticipated final account (forecast)
- Risk allowances / contingencies
- Cashflow forecast and certified payments
- Commentary on project status
Difference between cost and price?
- Cost is the expense incurred in the production of a product / service
- Price refers to payment required for supply of a product / service
How would you deal with a large and (in your opinion) unrealistic claim for loss and expense in your cost report?
- Report claim and highlight concern with figure submitted
- Assuming CA deems the principal of the claim is valid, I would assess the claim
- Update client on a regular basis until conclusion reached
What is a cash flow projection (/ forecast)?
Financial planning tool showing predicted flow of cash in and out of project, typically shown month-by-month
- Typically form an ‘S curve’
What formula can be used to predict anticipated payments?
S curve algorithm
Difference between employer cash flow and contractor (/ construction) cash flow projections?
- Employer -> usually considers project in broader context, may include costs such as fees (statutory, consultant, legal), charges (land acquisition, marketing and sales)
- Contractor -> construction costs
How does [the employer] benefit from accurate cash flow projections?
- Assist with planning expenditure- ensures apt funding in place
- Gain understanding of potential financial commitment at specific point in the future
- Sense check monthly contractor valuations
If payments to the contractor are behind the projection, what might this indicate?
Construction works may be behind programme
If payments to the contractor are ahead of the projection, what might this indicate?
Construction works may be ahead of programme or the contractor is over-claiming
How would you create a cashflow forecast?
- I would need to have access to the construction programme and contract sum analysis in order to populate the cashflow.
- The values associated with each element of construction could be forecasted at times to reflect their installation within the programme.
- I would split the works into the different packages as shown on the contract programme and include individual s-curves for each package.
- Obtaining drawdown schedules from specialist subcontractors and professional consultants can also assist when populating the cashflow.
- An alternative approach would be to utilise a previous cashflow from a similar scheme or to use cashflow forecasting software although this may not be as accurate.
Different ways to produce a cash flow?
- S curve calculator to calculate expenditure over course of construction
- Use programme and pricing schedule to plot expenditure
- Request contractor to submit cashflow
If your construction budget was £2.5m and proposed construction period was 25 weeks, would a forecast cashflow expenditure of £100,000 per week be realistic?
- In reality this would not be very realistic as the cashflow expenditure per week is unlikely to have a flat or regular profile.
- In reality the expenditure is much more likely to have an S-curve profile where at the start of the scheme, the expenditure per week will be fairly low as the site setup and enabling works are undertaken.
- As the scheme progresses, items that are of higher value such as the steel frame and M&E installations will be undertaken. The cost expenditure per week at this stage will be much higher than at the start of the scheme.
- As the scheme draws to a close, minor finishing items such as decoration and cleaning packages will be undertaken again resulting in a lower expenditure cost per week.
Components of a cash flow?
Prelim costs, work packages, OH&P, retention, expenditure of loss and expense, provisional sums, instructions, variations
Contributors to increased costs on a construction project?
- Client driven changes
- Design development
- Site specific risks (contamination, ground obstructions, logistical issues, incoming services)
- External influences (market fluctuations, tax and insurances, Brexit, COVID - depends on contract)
Methods to bring the project back in budget?
Main options are to reduce scope or assess value engineering possibilities
Would there be a potential conflict on the scheme if the EA undertook commercial aspects of the contract?
- Post contract - not really as the EA and QS scope of services are to act impartially and in accordance with administering contract conditions, so technically there shouldn’t be too much variance between their assessment of say valuations etc.
- Pre-contract (EA not appointed yet) but could be PM - if they had a favourable contractor in mind this could skew their quality assessment if they knew the status of the cost rankings
Have you produced a change control tracker? If so, how?
- Description of changes, who this was raised by and when, categorise change according to status
- Any additional comments in other column as a running commentary
What are the typical responsibilities of the cost manager on a construction project?
Depends on scope of service, may include:
- managing risk allowance expenditure
- prepare pricing documents
- tender evaluation / analysis
- prepare interim valuatoins
- value variations
- assess contractor’s financial claims
- negotiate and agree final accounts
- produce cost estimates and cost plans
- advice on whole life costs
- cost reports, forecasts
- prepare and maintain cash flow forecast
Advantages of buildability?
- Better programming, sequencing, construction methods
- Potential for reduced capital and life cycle costs and improve building performance and maintenance characteristics
What are variations?
Alterations / modifications to design, quality or quantity of the contract works / site access / working conditions
Why might variations arise?
- a) change to specification.
- b) discrepancies between contract documents.
- c) discrepancies with statutory requirements.
- d) errors and omissions.
- e) deficiencies in employer’s requirements.
What form must architect’s instructions take?
- It is best practice under the majority of contracts for instructions to be made in writing.
- The QS is not usually authorised to make additions to the contract sum for instructions that are not in written form.