You are managing a waterfall project. In the middle of the project the customer asks you to revise the scope defined at the beginning of the project. As an experienced project manager what should you do?
SELECT THE CORRECT ANSWER
Deny the request as the scope of work was frozen during planning
Accept the request and update the project charter
Generate a change request and follow the change control process
Consult with your sponsor on the customer request
Correct Option:D
EXPLANATION
The customer wants to change the scope defined at the beginning of the project. That scope was a part of the project charter, which is the responsibility of the sponsor. Hence, the project manager needs to talk to the sponsor.
3 QUALITY
During the quality testing of the new software integration project, the results show performance variance from the quality management plan. Thus, the project manager asked the quality team to investigate the root cause of the variance and resolve it to get back on track. What type of action did the project manager request?
SELECT THE CORRECT ANSWER
Corrective Action
Preventive Action
Defect Repair
Project Tracking
Correct Option:A
EXPLANATION
Finding the root cause and taking action to bring the project back on track come under Corrective Action.
5 NEXT CLOSING
Your company decided to terminate your 24 months’ project in the 7th month of execution because of insufficient budget. What you should do as a project manager?
SELECT THE CORRECT ANSWER
You must meet the top management and convince them to reconsider their decision.
If the management decide to terminate the project, the project manager cannot do anything.
You must submit a report mentioning that you completed the project successfully as you have been delivering the deliverables on time for seven months.
You should transfer the finished and unfinished deliverables to the relevant stakeholders.
Correct Option:D
EXPLANATION
If the project is terminated as a result of insufficient budget, it is most likely a project exit criteria. The project manager should look at the project closing process, which includes handing over the deliverables to the relevant stakeholders.
6 AGILE
You joined in as the project manager of an ongoing hybrid project after 6 months of project start date. You heard the team members saying that despite a robust change control system, there are too many changes in the project and the requirements keeps changing. What should you do?
SELECT THE CORRECT ANSWER
Halt all the changes until you know the reason for the previously done changes
Consider changing the development approach
Update the change management plan
Tell the team that changes are normal in hybrid projects
Correct Option:B
EXPLANATION
If the requirements are changing too rapidly, the project manager should consider changing the development approach from hybrid to agile.
9 NEXT AGILE
You are the project manager of an ongoing agile software development project and you completed your second release. What should you do to prepare for the next release?
SELECT THE CORRECT ANSWER
Manage changes to the scope baseline of the previous release
Review the backlog items
Confirm the validity of the project scope statement
Review the resource utilization
Correct Option:B
EXPLANATION
In agile projects, the project manager and product owner need to reprioritize the backlog items based on the work done during a sprint and the release, so after finishing the release, the project manager and product owner should review the backlog.
10
During the project management plan review meeting, one of the senior directors raised a concern that one major deliverable was missing in the scope of work. What should you do as a project manager?
SELECT THE CORRECT ANSWER
Initiate change management process
Tell the director the change can not be added as the scope is already defined
Review the requirement documentation and requirement traceability matrix (RTM)
Change the plan to include missing deliverable
Correct Option:C
EXPLANATION
As a project manager, you should look into the requirement documentation to see if the requirement was captured.
13 NEXT CLOSING
You were managing a project to set up a car assembly line. The assembly line is almost ready and you have closed all the procurements, submitted the final report, and also took feedback from all the relevant stakeholders. What should you do next?
SELECT THE CORRECT ANSWER
Hand over the assembly line to the operations team
Prepare a report to show how the project achieved all the business objectives
Give final payment to all the vendors and contractors
Send out formal notice to close the project
Correct Option:A
EXPLANATION
Once the project finishes, the project manager and the project team need to hand over the project to relevant stakeholders
14 NEXT PLANNING
You are about to start the planning of a large and complex project in a very regulated environment. Due to the size and regulatory considerations, the planning becomes really critical. What is the first thing you should do to start the planning process?
SELECT THE CORRECT ANSWER
Start stakeholder identification so that you can engage the required stakeholders in the planning process
Get the statement of work from the customer and share it with all the stakeholders so that everybody knows what the priorities are
Review the project charter to understand high-level requirements of the project
Conduct a project kick-off meeting with the stakeholders to inform and engage them and to take their commitment
Correct Option:C
EXPLANATION
Project charter gives all the high-level information, and the information becomes the base for detailed planning.
15 VZORCE
You are working on a cement plan maintenance project. The total estimated budget for project is $100000. At 40% completion of the actual work, the actual cost spent is $60000. At the same pace, how much more money will it take to complete the project?
SELECT THE CORRECT ANSWER
$123,512
$97,889
$122,678
$89,254
Correct Option:D
EXPLANATION
The question says “how much more” money you would need to complete the project. So the question requires us to calculate the ETC. First we will calculate EV by using the formula %completeBAC(40%100000), which would be $40000, then we will derive the CPI by the formula EV/AC (40000/60000), which would be 0.67. We need to use the CPI to calculate EAC by the formula BAC/CPI (100000/0.67), which would be 149254, and finally we need to calculate ETC by the formula EAC-AC (149254-60000) = 89254.
16 MONITORING AND CONTROL
Your are managing a large construction project. Currently, you and your team are following the monitor and control project work process. Which of the following activities you and team might carry out during this process?
SELECT THE CORRECT ANSWER
Accepting or rejecting the change requests
Performing quality control activities on the deliverables
Getting formal acceptance on the deliverables from the customer (customer validation)
Comparing the actual progress against the baseline and the project management plan to keep the project under control
Correct Option:D
EXPLANATION
The question asks about the process of monitor and control project work and not about monitoring and controlling process groups. The process group includes all the options, but the process of monitor and control project work includes comparing the actual progress against the project management plan and making sure the project runs on track.
18 QUALITY ASSURANCE
You are managing a defect rate reduction project for a manufacturing process. To analyze and improve the process, you and the team are now involved in the quality assurance process. Which of the following could help in improving the process?
SELECT THE CORRECT ANSWER
Add a zero inventory process to the project
Consult with the quality control department
Make a process improvement plan with a Kanban expert
Consult with a Six Sigma Black Belt consultant
Correct Option:D
EXPLANATION
Six sigma is a lean project management concept, which is centralized around process improvement. The six sigma consultant can help in reducing the error rate.
20During the project review meeting with the team, you identified a significant variance. It is because of an issue in configuration. If the issue is not fixed before the next client inspection, your project might be canceled, However, after further review with the team, you came to know that bringing the project back on track is only a minor correction to the configuration element. What should you do first?
SELECT THE CORRECT ANSWER
Contact your sponsor
Talk to the customer and inform them about the findings
Raise a change request
Change the configuration element to bring the project back on track
Correct Option:C
EXPLANATION
Because the change is in configuration, the first thing the project manager should do is to raise a change request.
21
You are an experienced project manager working on a large software development project. Using a hybrid approach in this project, you are trying to break the work package into activities for scheduling purposes. During the decomposition of the testing work package, you need more information about the project which will come only once the development work is at least 60% complete. Since the development work will take about four months to complete, how you would proceed with the decomposition?
SELECT THE CORRECT ANSWER
Review the project scope statement to check if there is a possibility to reduce some work from development work package
Review the project management plan to determine how to proceed with the decomposition
Contact the solution architects to see if they could help in decomposition
Breakdown the development work package for now and decompose the testing work package later after getting the required information
Correct Option:D
EXPLANATION
One of the decomposition techniques is Rolling Wave Planning. The project manager decompose the work packages as they move into execution and more information is available. The best option here is to decompose the development work package for now and wait for the required information to decompose the testing work package later.
22 DEFINITION
You and the team are trying to estimate the time periods required by each activity. In this process, you are using a document which contains information on categories of labour, material, and equipment resources. To complete the project work, you also want to know the skill set, grade of supplies, and required certifications. Which of the following documents would you primarily refer for this purpose?
SELECT THE CORRECT ANSWER
Resource management plan
Work breakdown structure
Resource breakdown structure
Project management plan
Correct Option:C
EXPLANATION
The team is in the estimate activity duration process. One of the inputs to that process is the resource breakdown structure, which has information related to labour, material, and equipment resources.
23
You are using a rented facility from where the team of developers and testers are working. The weekly renewal of the facility is bound to happen on Monday, next week. The development work is delayed and will take another week. You had a discussion with the landlord to renew the contract for one more week but the landlord informs you that the facility is already booked. What should you do next?
SELECT THE CORRECT ANSWER
Update this risk in your risk register
Update this issue in the issue log
Update the resource management plan
Update procurement documentation
Correct Option:C
EXPLANATION
Since the issue has already occurred, there is no need to change the facility. The facility is a part of physical resources, the resource management plan needs to be updated with this change.
24 RISK
The project management plan explains that the predictive life cycle has been selected to produce the project deliverables. During which of the following areas will the overall project risk be the lowest?
SELECT THE CORRECT ANSWER
Initiation
Planning
Monitor and control
Closing
Correct Option:D
EXPLANATION
The overall project risk is highest at the beginning of the project and is lowest during the closing.
27
A few deliverables in your project demand procurement of goods and services from outside the organization. You have instructed your team to document all individual project risks related to the procurement activities. How should the team proceed with this activity?
SELECT THE CORRECT ANSWER
Review and update the risk management plan
Update the risk register
Review procurement documentation
Interview the vendors and contractors to identify the risks
Correct Option:C
EXPLANATION
Although the team is performing the identification of the risk process from the risk management knowledge area, the risks are related to procurement. The procurement documents such as bid documents and statement of work can be useful in the identification of the risks. Procurement documentation is also an input to the risk identification process.
28 WHICH DOCUMENT
The project you are currently managing has five phases. At the phase gate meeting, the management wants to determine if the phase has met the success criteria so they can proceed to the next phase. Along with the project management plan, what is the other document that should be referred?
SELECT THE CORRECT ANSWER
Business case and Project charter
Issue log
Risk register
Lessons learned register
Correct Option:A
EXPLANATION
To explain the success criteria, the project manager should refer to the business case and the project charter, along with the project management plan, as these documents contain the business objectives and other high level information about the project.
29 CHANGE MAN.
As per the organization policy, the Change Control Board (CCB) should review all the changes. They should also follow all the activities which are defined in the PMBOK for the change control. Since the project manager and the team are not the part of the CCB, which of the following activities may the CCB perform?
SELECT THE CORRECT ANSWER
Submit change request
Implement approved changes
Update project management plan
Terminate project
Correct Option:A
EXPLANATION
As the CCB is required to follow the change control activities, and the project manager is not part of the CCB, it is responsible for submitting the change request.
30 WHICH DOCUMENT
You are an experienced project manager working on an automobile project. Before working on one of the work packages to design clutch plates for the new vehicle, you wanted to review the acceptance criteria for the work package. Which document should you refer to?
SELECT THE CORRECT ANSWER
Project management plan
Requirements traceability matrix
Project scope statement
WBS Dictionary
Correct Option:D
EXPLANATION
The WBS Dictionary contains work package information such as owners, scheduled activities, and acceptance criteria.
33 THEORY
According to Tuckman’s ladder, in which area would a team experience maximum coordination and synergy?
SELECT THE CORRECT ANSWER
Performing
Norming
Forming
Adjourning
Correct Option:A
EXPLANATION
According to Dr. Bruce Tuckman’s ladder of team dynamics, a team has maximum coordination and synergy during the performing phase.
35 VZORCE
Your project sponsor wants you to calculate the Expected Monitory Value of two different alternatives available to complete the project per the decision tree. Which of the following formulas will you use to calculate the EMV?
SELECT THE CORRECT ANSWER
Probability * Impact
Positive outcome - Negative outcome
Negative outcome - Positive outcome
Average of the above options
Correct Option:B
EXPLANATION
The formula for calculating the EMV is Positive outcome - Negative outcome.
36 RISK
You are in the process of prioritizing the risks in the project with your team. Which of the following will have the least effect on the prioritization of the risk process?
SELECT THE CORRECT ANSWER
Reviewing risk register
Reviewing stakeholder register
Reviewing assumptions log
Reviewing the risk report
Correct Option:D
EXPLANATION
Reviewing the risk report will have the least impact on the prioritization process as the reports are made after the risks are identified and prioritized and the mitigation plans are prepared.
38 RISK
While managing a large and complex project, you followed all the best practices of project management. However, you still identified a lot of critical risks during the project, and so, it was not able to achieve the objectives. What went wrong?
SELECT THE CORRECT ANSWER
The risks were not identified properly.
The qualitative risk analysis was not done.
The quantitative risk analysis was not done.
The risk mitigation plans were poorly implemented.
Correct Option:D
EXPLANATION
Since you followed all the good practices, you must have done the identification and qualitative and quantitative risk analysis,.The only possible reason for the failure of the project could be that the risk response plan was not properly implemented.