{ "@context": "https://schema.org", "@type": "Organization", "name": "Brainscape", "url": "https://www.brainscape.com/", "logo": "https://www.brainscape.com/pks/images/cms/public-views/shared/Brainscape-logo-c4e172b280b4616f7fda.svg", "sameAs": [ "https://www.facebook.com/Brainscape", "https://x.com/brainscape", "https://www.linkedin.com/company/brainscape", "https://www.instagram.com/brainscape/", "https://www.tiktok.com/@brainscapeu", "https://www.pinterest.com/brainscape/", "https://www.youtube.com/@BrainscapeNY" ], "contactPoint": { "@type": "ContactPoint", "telephone": "(929) 334-4005", "contactType": "customer service", "availableLanguage": ["English"] }, "founder": { "@type": "Person", "name": "Andrew Cohen" }, "description": "Brainscape’s spaced repetition system is proven to DOUBLE learning results! Find, make, and study flashcards online or in our mobile app. Serious learners only.", "address": { "@type": "PostalAddress", "streetAddress": "159 W 25th St, Ste 517", "addressLocality": "New York", "addressRegion": "NY", "postalCode": "10001", "addressCountry": "USA" } }

12. Scheduling Flashcards

(4 cards)

1
Q

What is time scheduling?

A

It is to set when which activity ist to be carried out.

Key to detailed plannng and monitoring of time, cost and quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are prerequisites for time scheduling?

A
  • phase model
  • project structures (WBS, work packages)
  • effort estimation
  • in a first step, resources may not be taken into account
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain the terms free float and total float.

A

Free float:
The amount of time that an activity can be delayed without delaying the early start date of any successive activity.

Total float:
The amount of time that an activity can be delayed from its early start date without delaying the project finish date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain what the critical path is?

A

The critical path is the longest sequence of activities towards logical end points or the end of the project -> must be completed in order to finish in time.