Process Groups
1-Initiating
2-Planning
3-Executing
4-Monitoring and Controlling
5-Closing
How many processes does the process group “Initiating” have?
2
How many processes does the process group “Planning” have?
24
How many processes does the process group “Executing” have?
10
How many processes does the process group “Monitoring and Controlling” have?
12
How many processes does the process group “Closing” have?
1
How many processes are in knowledge area “Project Integration Management”?
7
How many processes are in knowledge area “Project Scope Management”?
6
How many processes are in knowledge area “Project Schedule Management”?
6
How many processes are in knowledge area “Project Cost Management”?
4
How many processes are in knowledge area “Project Quality Management”?
3
How many processes are in knowledge area “Project Resource Management”?
6
How many processes are in knowledge area “Project Communication Management”?
3
How many processes are in knowledge area “Project Risk Management”?
7
How many processes are in knowledge area “Project Procurement Management”?
3
How many processes are in knowledge area “Project Stakeholders Management”?
4
Which knowledge areas do NOT have processes in process group “Initiating”?
1-Project Scope Management
2-Project Schedule Management
3-Project Cost Management
4-Project Quality Management
5-Project Resource Management
6-Project Communication Management
7-Project Risk Management
8-Project Procurement Management
Which knowledge areas do NOT have processes in process group “Planning”?
None
Which knowledge areas do NOT have processes in process group “Executing”?
1-Project Scope Management
2-Project Schedule Management
3-Project Cost Management
Which knowledge areas do NOT have processes in process group “Monitoring and Controlling”?
None
Which knowledge areas do NOT have processes in process group “Monitoring and Closing”?
1-Project Scope Management
2-Project Schedule Management
3-Project Cost Management
4-Project Quality Management
5-Project Resource Management
6-Project Communication Management
7-Project Risk Management
8-Project Procurement Management
9-Project Stakeholder Management
What are the processes of knowledge area “Project Integration Management”?
1-Develop Project Charter
2-Develop Project Management Plan
3-Direct and Manage Project Work
4-Manage Project Knowledge
5-Monitor & Control Project Work
6-Perform Integrated Change Control
7-Close Project or Phase
What are the processes of knowledge area “Project Scope Management”?
1-Plan Scope Management
2-Collect Requirements
3-Define Scope
4-Create WBS
5-Validate Scope
6-Control Scope
What are the processes of knowledge area “Project Schedule Management”?
1-Plan Schedule Management
2-Define Activities
3-Sequence Activities
4-Estimate Activity Durations
5-Develop Schedule
6-Control Schedule