APC - Contract Practice Flashcards

(22 cards)

1
Q

What are the various JCT Contract Suites?

A
  • JCT SBC Contract (with/without/approx)
  • JCT Design & Build
  • JCT Intermediate Contract
  • JCT Minor Works Contract
  • JCT Management Contract
  • JCT Construction Management Contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How are JCT Contracts Governed in the UK?

A
  • JCT Contracts are Governed by the Law of England & Wales
  • They operate within the framework of English Contract Law including common law principles (Case Law) and Statutory Legislation (HGCRA 1996)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Are you aware of any Case Law?

A

I am aware of the T&T VS Ampleforth Abbey Trust, where construction began based on a LOI and no contract. There were delays which client could not claim LDs for. T&T found negligent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a LOI?

A

A LOI is a document issued to a contractor indicating the intention to enter a formal contract at a later date. Allows contractor to start work in the meantime.

Can be binding depending on wording/intent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can you tell me about the House Grants Construction and Regenerations Act 1996?

A
  • Form of Statutory Legislation that governs UK Construction Law
  • Improve Payment Practices (prohibiting ‘Pay When Paid’)
  • Providing Statutory Right to Adjudication (in all contracts)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why did you use JCT SBC on your project?

A
  • Procurement strategy was largely defined by this point.
  • I advise my client that since the programme had only allowed for 2 weeks to prepare, review and issue tender documents that producing a BOQ would delay the programme by circa 3 weeks.
  • Also would be an additional cost for producing them.
  • Not commonly used in the London fit out market.
  • Risk for quantities also sat with Contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When would you advise on using a JCT Intermediate Contract?

A
  • Medium size project
  • Works expected to finish within 1 year
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When would you advise on using a JCT Minor Contract?

A
  • Projects under £250-£500k
  • Completed within a few months - year
  • Simple project Design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When would you advise on using a JCT Major Contract?

A
  • High Value £10m+
  • Complex Projects w Significant Design
  • 18months to several years
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Difference between a Contract signed under Hand vs Deed

A

Under Hand - 6 year limitation period.
As a Deed - 12 year limitation period (2 directors and witnessed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the Valuation Rules under the JCT SBC/Intermediate Contract?

A

Valuation based on work properly executed on site and materials delivered to site. Measured Works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you name the Sections under a JCT?

A

Section 1 - Definitions and Interpretation
Section 2 - Carrying out the Works
Section 3 - Control of the Works
Section 4 - Payment
Section 5 - Variations
Section 6 - Injury, Damage and Insurance
Section 7 - Assignment, Performance Bonds and Guarantees & Collateral Warranties
Section 8 - Termination
Section 9 - Settlement of Disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why was the EOT for Spetisbury not granted?

A

There was no relevant event. The OOHs were already specified in the contract, therefore there was no change to the working condition following the instruction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What steps did you take in the EOT Process?

A
  • No Relevant Event so NO EOT was granted.
  • There was a letter agreed to extend the Completion Date, LDs remained.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How would you assess the EOT if it was true?

A

*Review the Supporting information
* Validate the Build Up (Labour/Materials/Site Operations)
* Consider any Mitigation, how has the contractor taken reasonable steps to mitigate this?
* Assess time related cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How as CA did you determine the EOT Claim?

A
  • Upon receiving the Notice of Delay I referred to Clause 2.20 Relevant Events to determine.
  • Confirm if this was a Relevant Event (in this case NO)
17
Q

Relevant Events vs Relevant Matter?

A

Relevant Event - Grant the contractor an EOT
Relevant Matter - Grant the contractor Loss & Expense

Not all RE’s are RM’s. Adverse Weather & Forece Majure are RE’s not RM’s.

JCT 2024 includes Epidemics as RE/RM

18
Q

How would you assess a Loss & Expense Claim?

A
  • Request all supporting information
  • Assess Claim (site overheads, labour, plant costs) referring to contract prelim rates
  • Ensure the information aligns to time delay.
19
Q

What are the JCT Timelines for Valuations?

A
  • Interim Valuation Date - 1 month form Possession of Site
  • Interim Valuation Date - 1 month thereafter
  • Due Date - 7 days after the IVD
  • Payment Notice - 5 days from Due Date
  • Final Date for Payment - 14 Days after Due Date
  • Pay Less Notice - 5 days before final date for payment
20
Q

What insurances are you aware of under the JCT?

A
  • Public Liability Insurance - Covers claims for injury or harm to public, property or third parties.
  • Employers Liability Insurance - Covers for Injury or harm to employees.
  • Works Insurance (Options A-C) - Covers for loss or damage to works during construction.
  • Professional Indemnity Insurance - Covers for negligence in working practice.
21
Q

What is a Performance Bond?

A

Is a surety provided by a third party which covers the client should the contractor fail in their obligations to the contract or to complete the works.

If the contractor defaults, the bond provider pays the client usually 10% of the construction works.

22
Q

What is a Parent Company Guarantee?

A

Legal Agreement where the parent company of the contractor guarantees the performance of its subsidiary under the contract, should the contractor:
* Fail to perform
* Becomes Insolvent
* Breaches Contract